17-00001-05-BT
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Rowe Construction, a div of UCM, Inc. Low bidder | $2,132,081 | ||
| 2 | Stark Excavating, Inc. | $2,161,859 | +1.4% | |
| 3 | Halverson Construction Co., Inc. | $2,267,520 | +6.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rowe Constructi… | #2 Stark Excavatin… | #3 Halverson Const… |
|---|---|---|---|---|---|---|---|---|
| 1 | XX006985 | SHOULDER EXCAVATION | 120 | CU YD | $115.00 | $120.00 | $75.00 | |
| 2 | XX008340 | TIMBER BRDGE APP RAIL | 80 | FOOT | $82.50 | $165.00 | $165.00 | |
| 3 | X0300010 | BIT MATLS FS | 4,856 | POUND | $1.05 | $1.00 | $0.9500 | |
| 4 | X0322508 | PED TRUSS SUPERSTR | 2,100 | SQ FT | $155.10 | $141.00 | $125.00 | |
| 5 | X0350805 | FOLD DOWN BOLLARDS | 11 | EACH | $578.54 | $320.00 | $750.00 | |
| 6 | X6640535 | CH LK FENCE 6 ATT STR | 20 | FOOT | $132.00 | $170.00 | $212.00 | |
| 7 | X6640560 | CH LK FENCE 6 SPL | 20 | FOOT | $82.50 | $180.00 | $156.00 | |
| 8 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $20,000.00 | $20,000.00 | $105,000.00 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $35,000.00 | $24,000.00 | $17,500.00 | |
| 10 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 5,980 | CU YD | $34.30 | $40.00 | $55.00 | |
| 13 | 20800150 | TRENCH BACKFILL | 21.2 | CU YD | $32.63 | $26.00 | $150.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 24,637 | SQ YD | $5.01 | $4.50 | $4.50 | |
| 15 | 25000200 | SEEDING CL 2 | 5.25 | ACRE | $1,973.67 | $1,020.00 | $970.00 | |
| 16 | 25000400 | NITROGEN FERT NUTR | 473 | POUND | $1.77 | $3.20 | $1.00 | |
| 17 | 25000500 | PHOSPHORUS FERT NUTR | 473 | POUND | $1.77 | $3.20 | $1.00 | |
| 18 | 25000600 | POTASSIUM FERT NUTR | 473 | POUND | $1.77 | $3.20 | $1.00 | |
| 19 | 25100115 | MULCH METHOD 2 | 5.25 | ACRE | $3,060.43 | $1,020.00 | $970.00 | |
| 20 | 28000250 | TEMP EROS CONTR SEED | 508 | POUND | $4.80 | $7.50 | $3.00 | |
| 21 | 28000305 | TEMP DITCH CHECKS | 24 | FOOT | $8.61 | $22.00 | $35.00 | |
| 22 | 28000400 | PERIMETER EROS BAR | 19,665 | FOOT | $3.52 | $3.25 | $4.00 | |
| 23 | 28000500 | INLET & PIPE PROTECT | 8 | EACH | $150.68 | $230.00 | $300.00 | |
| 24 | 35101400 | AGG BASE CSE B | 10,464 | TON | $38.50 | $48.00 | $35.00 | |
| 25 | 40200800 | AGG SURF CSE B | 452 | TON | $50.58 | $31.50 | $40.00 | |
| 26 | 40300200 | BIT MATLS PR CT | 5.4 | TON | $1,821.60 | $1,660.00 | $1,656.00 | |
| 27 | 40300400 | BIT MATLS C&S CT | 11.7 | TON | $1,282.60 | $1,200.00 | $1,166.00 | |
| 28 | 40300500 | COVER COAT AGG | 52 | TON | $58.30 | $54.00 | $53.00 | |
| 29 | 40300600 | SEAL COAT AGG | 41 | TON | $56.10 | $51.00 | $51.00 | |
| 30 | 40600275 | BIT MATLS PR CT | 45,321 | POUND | $0.0100 | $0.0100 | $0.8500 | |
| 31 | 40600290 | BIT MATLS TACK CT | 4,401 | POUND | $1.25 | $1.25 | $0.9500 | |
| 32 | 40602965 | HMA BC IL-9.5FG N50 | 1,683 | TON | $122.00 | $122.00 | $113.00 | |
| 33 | 40604050 | HMA SC IL-9.5 C N50 | 1,647 | TON | $122.00 | $122.00 | $111.00 | |
| 34 | 42400300 | PC CONC SIDEWALK 6 | 567 | SQ FT | $29.34 | $20.00 | $15.00 | |
| 35 | 42400800 | DETECTABLE WARNINGS | 183 | SQ FT | $39.66 | $25.00 | $30.00 | |
| 36 | 48101200 | AGGREGATE SHLDS B | 1,308 | TON | $42.00 | $42.00 | $55.00 | |
| 37 | 50104400 | CONC HDWL REM | 1 | EACH | $3,070.86 | $720.00 | $410.00 | |
| 38 | 50200100 | STRUCTURE EXCAVATION | 5 | CU YD | $101.20 | $92.00 | $200.00 | |
| 39 | 50300225 | CONC STRUCT | 23.6 | CU YD | $1,474.00 | $1,340.00 | $1,155.00 | |
| 40 | 50300300 | PROTECTIVE COAT | 35 | SQ YD | $7.70 | $7.00 | $8.00 | |
| 41 | 50301350 | CONC SUPSTR APP SLAB | 11.8 | CU YD | $1,100.00 | $1,000.00 | $625.00 | |
| 42 | 50800105 | REINFORCEMENT BARS | 3,730 | POUND | $3.14 | $2.75 | $2.75 | |
| 43 | 50800205 | REINF BARS, EPOXY CTD | 4,140 | POUND | $2.86 | $2.60 | $2.50 | |
| 44 | 51200957 | FUR M S PILE 12X0.250 | 100 | FOOT | $247.50 | $225.00 | $265.00 | |
| 45 | 51202305 | DRIVING PILES | 100 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 46 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $7,700.00 | $7,000.00 | $4,300.00 | |
| 47 | 52100520 | ANCHOR BOLTS 1 | 8 | EACH | $129.80 | $118.00 | $110.00 | |
| 48 | 54001001 | BOX CUL END SEC C1 | 1 | EACH | $7,880.69 | $6,000.00 | $4,000.00 | |
| 49 | 54001002 | BOX CUL END SEC C2 | 1 | EACH | $7,880.69 | $6,000.00 | $4,000.00 | |
| 50 | 54002020 | EXPAN BOLTS 3/4 | 61 | EACH | $43.72 | $27.00 | $80.00 | |
| 51 | 54003000 | CONC BOX CUL | 13.8 | CU YD | $2,585.00 | $2,350.00 | $3,150.00 | |
| 52 | 54010403 | PCBC 4X3 | 12 | FOOT | $852.30 | $680.00 | $1,100.00 | |
| 53 | 542D0223 | P CUL CL D 1 18 | 88 | FOOT | $59.06 | $55.00 | $55.00 | |
| 54 | 542D5473 | P CUL CL D 1 EQRS 18 | 534 | FOOT | $52.93 | $47.00 | $50.00 | |
| 55 | 54213660 | PRC FLAR END SEC 15 | 1 | EACH | $2,998.05 | $2,000.00 | $975.00 | |
| 56 | 54248510 | CONCRETE COLLAR | 0.6 | CU YD | $6,112.55 | $8,000.00 | $12,500.00 | |
| 57 | 54261718 | STEEL FL END SEC 18" | 6 | EACH | $393.03 | $950.00 | $525.00 | |
| 58 | 54261818 | STL FL ES EQ RS 18" | 10 | EACH | $486.95 | $870.00 | $450.00 | |
| 59 | 58600101 | GRANULAR BACKFILL STR | 32 | CU YD | $66.00 | $60.00 | $75.00 | |
| 60 | 58700300 | CONCRETE SEALER | 486 | SQ FT | $1.71 | $1.55 | $1.60 | |
| 61 | 67100100 | MOBILIZATION | 1 | L SUM | $66,272.00 | $68,500.00 | $136,051.22 | |
| 62 | 72000100 | SIGN PANEL T1 | 144 | SQ FT | $27.67 | $24.00 | $31.00 | |
| 63 | 72800100 | TELES STL SIN SUPPORT | 476 | FOOT | $20.90 | $16.20 | $22.50 | |
| 64 | 78000100 | THPL PVT MK LTR & SYM | 151 | SQ FT | $33.00 | $30.00 | $30.00 | |
| 65 | 78000200 | THPL PVT MK LINE 4 | 574 | FOOT | $9.69 | $9.00 | $8.81 | |
| 66 | 78000600 | THPL PVT MK LINE 12 | 260 | FOOT | $24.20 | $22.00 | $22.00 | |
| 67 | 78000650 | THPL PVT MK LINE 24 | 40 | FOOT | $27.50 | $25.00 | $25.00 |