2018-031-RS-SW
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $1,651,036 | ||
| 2 | K-Five Construction Corporation | $1,858,918 | +12.6% | |
| 3 | Plote Construction, Inc. | $1,864,719 | +12.9% | |
| 4 | Arrow Road Construction Co. | $1,867,190 | +13.1% | |
| 5 | Builders Paving, LLC | $1,898,000 | +15.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 K-Five Construc… | #3 Plote Construct… | #4 Arrow Road Cons… | #5 Builders Paving… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $2,000.00 | $20,000.00 | $2,000.00 | $4,995.00 | $5,000.00 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 32 | UNIT | $235.21 | $225.00 | $315.00 | $173.00 | $100.00 | |
| 3 | X2700004 | PREF PL PM TB LINE 7 | 344 | FOOT | $8.00 | $12.18 | $8.00 | $8.00 | $10.00 | |
| 4 | X4060004 | P HMA SC SMA 9.5 N80 | 6,089 | TON | $96.74 | $103.50 | $100.00 | $108.30 | $95.00 | |
| 5 | X5537800 | SS CLEANED 12 | 784 | FOOT | $2.50 | $1.20 | $1.00 | $2.63 | $2.65 | |
| 6 | X6030310 | FR & LIDS ADJUST SPL | 18 | EACH | $800.00 | $1,200.00 | $1,100.00 | $840.00 | $840.00 | |
| 7 | X7030005 | TEMP PAVT MKING REMOV | 1,109 | SQ FT | $0.9500 | $0.0100 | $0.9500 | $0.0100 | $0.0100 | |
| 8 | X7830070 | GRV RCSD PVT MRKG 5 | 1,032 | FOOT | $2.50 | $1.70 | $1.50 | $1.50 | $1.40 | |
| 9 | Z0004562 | COMB C C&G REM & REPL | 873 | FOOT | $39.61 | $42.24 | $60.00 | $37.80 | $38.00 | |
| 10 | Z0018500 | DRAINAGE STR CLEANED | 12 | EACH | $550.00 | $359.22 | $295.00 | $577.50 | $580.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $15.00 | $25.46 | $15.00 | $10.00 | $20.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 16 | CU YD | $101.01 | $98.33 | $100.00 | $89.25 | $90.00 | |
| 13 | 21101615 | TOPSOIL F & P 4 | 146 | SQ YD | $9.98 | $11.55 | $10.00 | $9.98 | $10.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 2 | POUND | $4.00 | $4.63 | $4.00 | $4.00 | $4.00 | |
| 15 | 25000500 | PHOSPHORUS FERT NUTR | 2 | POUND | $4.00 | $4.63 | $4.00 | $4.00 | $4.00 | |
| 16 | 25000600 | POTASSIUM FERT NUTR | 2 | POUND | $4.00 | $4.63 | $4.00 | $4.00 | $4.00 | |
| 17 | 25200110 | SODDING SALT TOLERANT | 146 | SQ YD | $15.00 | $17.35 | $15.00 | $15.00 | $15.00 | |
| 18 | 25200200 | SUPPLE WATERING | 1 | UNIT | $25.00 | $28.92 | $25.00 | $25.00 | $25.00 | |
| 19 | 40600290 | BIT MATLS TACK CT | 41,934 | POUND | $0.6000 | $0.0100 | $0.0100 | $0.8700 | $0.0100 | |
| 20 | 40600400 | MIX CR JTS FLANGEWYS | 94 | TON | $80.00 | $70.00 | $55.00 | $185.00 | $440.00 | |
| 21 | 40600827 | P LB MM IL-4.75 N50 | 2,563 | TON | $91.75 | $100.00 | $88.00 | $91.75 | $82.00 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 389 | SQ YD | $14.96 | $7.00 | $22.00 | $5.00 | $20.00 | |
| 23 | 42001300 | PROTECTIVE COAT | 386 | SQ YD | $1.00 | $1.00 | $0.5000 | $1.05 | $1.05 | |
| 24 | 42400200 | PC CONC SIDEWALK 5 | 1,146 | SQ FT | $10.80 | $12.18 | $9.85 | $10.50 | $10.50 | |
| 25 | 42400800 | DETECTABLE WARNINGS | 104 | SQ FT | $35.00 | $42.62 | $36.00 | $36.75 | $36.75 | |
| 26 | 44000159 | HMA SURF REM 2 1/2 | 62,123 | SQ YD | $3.60 | $2.76 | $3.00 | $4.10 | $4.00 | |
| 27 | 44000600 | SIDEWALK REM | 1,102 | SQ FT | $2.98 | $2.62 | $3.60 | $2.26 | $2.25 | |
| 28 | 44003510 | MEDIAN REMOVAL (PD) | 30 | SQ FT | $35.00 | $42.62 | $13.00 | $36.75 | $36.75 | |
| 29 | 44201811 | CL D PATCH T1 14 | 125 | SQ YD | $88.75 | $55.00 | $125.00 | $60.00 | $230.00 | |
| 30 | 44201815 | CL D PATCH T2 14 | 994 | SQ YD | $74.63 | $55.00 | $125.00 | $60.00 | $150.00 | |
| 31 | 44201819 | CL D PATCH T3 14 | 746 | SQ YD | $65.46 | $50.00 | $125.00 | $60.00 | $115.00 | |
| 32 | 44201821 | CL D PATCH T4 14 | 622 | SQ YD | $56.91 | $50.00 | $125.00 | $60.00 | $115.00 | |
| 33 | 48102100 | AGG WEDGE SHLD TYPE B | 128 | TON | $42.16 | $75.00 | $100.00 | $46.15 | $52.00 | |
| 34 | 60300105 | FR & GRATES ADJUST | 5 | EACH | $500.00 | $608.85 | $800.00 | $525.00 | $525.00 | |
| 35 | 60300305 | FR & LIDS ADJUST | 3 | EACH | $400.00 | $487.08 | $600.00 | $420.00 | $420.00 | |
| 36 | 66900200 | NON SPL WASTE DISPOSL | 16 | CU YD | $130.00 | $144.60 | $300.00 | $115.00 | $130.00 | |
| 37 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,850.00 | $3,000.00 | $1,850.00 | $1,500.00 | $1,500.00 | |
| 38 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $3,300.00 | $7,000.00 | $3,300.00 | $2,000.00 | $2,500.00 | |
| 39 | 66901002 | ON-SITE MON REG SUB | 15 | CAL DA | $680.00 | $725.00 | $0.0100 | $700.00 | $600.00 | |
| 40 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $900.00 | $3,000.00 | $900.00 | $1,000.00 | $2,000.00 | |
| 41 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,750.00 | $3,500.00 | $3,000.00 | $2,500.00 | $3,000.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $97,173.82 | $225,000.00 | $111,800.00 | $109,000.00 | $113,000.00 | |
| 43 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $56,485.91 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 44 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 45 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $9,999.00 | $1.00 | $152,000.00 | $1.00 | $1.00 | |
| 46 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $111,000.00 | $1.00 | $188,609.35 | $117,488.69 | |
| 47 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 48 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 49 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 6,654 | FOOT | $0.0100 | $1.74 | $1.00 | $0.8400 | $0.6500 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 1,109 | SQ FT | $0.0700 | $1.16 | $3.60 | $2.45 | $1.40 | |
| 52 | 70300210 | TEMP PVT MK LTR & SYM | 1,009 | SQ FT | $1.25 | $0.0100 | $0.0100 | $0.0100 | $1.25 | |
| 53 | 70300220 | TEMP PVT MK LINE 4 | 26,269 | FOOT | $0.2000 | $0.0100 | $0.0100 | $0.0100 | $0.2200 | |
| 54 | 70300240 | TEMP PVT MK LINE 6 | 4,658 | FOOT | $0.3000 | $0.0100 | $0.0100 | $0.0100 | $0.3000 | |
| 55 | 70300250 | TEMP PVT MK LINE 8 | 564 | FOOT | $0.4000 | $0.0100 | $0.0100 | $0.0100 | $0.4800 | |
| 56 | 70300260 | TEMP PVT MK LINE 12 | 296 | FOOT | $0.6000 | $0.0100 | $0.0100 | $0.0100 | $0.6600 | |
| 57 | 70300280 | TEMP PVT MK LINE 24 | 613 | FOOT | $1.20 | $0.0100 | $0.0100 | $0.0100 | $1.25 | |
| 58 | 70300520 | PAVT MARK TAPE T3 4 | 3,327 | FOOT | $0.8500 | $1.45 | $2.05 | $0.0100 | $1.25 | |
| 59 | 78000100 | THPL PVT MK LTR & SYM | 1,009 | SQ FT | $4.00 | $5.38 | $4.00 | $4.00 | $4.50 | |
| 60 | 78000200 | THPL PVT MK LINE 4 | 26,269 | FOOT | $0.5000 | $0.7400 | $0.5300 | $0.5300 | $0.6200 | |
| 61 | 78000400 | THPL PVT MK LINE 6 | 4,658 | FOOT | $0.7500 | $1.17 | $0.7300 | $0.7300 | $0.9800 | |
| 62 | 78000500 | THPL PVT MK LINE 8 | 564 | FOOT | $1.00 | $1.67 | $1.00 | $1.00 | $1.40 | |
| 63 | 78000600 | THPL PVT MK LINE 12 | 296 | FOOT | $1.50 | $2.57 | $1.40 | $1.40 | $2.15 | |
| 64 | 78000650 | THPL PVT MK LINE 24 | 613 | FOOT | $4.00 | $5.56 | $4.00 | $4.00 | $4.65 | |
| 65 | 78009004 | MOD URETH PM LINE 4 | 688 | FOOT | $8.00 | $5.98 | $3.50 | $3.50 | $5.00 | |
| 66 | 78100100 | RAISED REFL PAVT MKR | 646 | EACH | $30.00 | $34.67 | $23.00 | $23.00 | $29.00 | |
| 67 | 78300200 | RAISED REF PVT MK REM | 581 | EACH | $11.26 | $15.00 | $8.00 | $3.87 | $12.00 | |
| 68 | 88600600 | DET LOOP REPL | 1,152 | FOOT | $18.92 | $35.00 | $17.00 | $17.00 | $17.00 | |
| 69 | 89502376 | REBUILD EX HANDHOLE | 1 | EACH | $2,100.00 | $5,000.00 | $2,100.00 | $2,100.00 | $4,000.00 |