(15,15X)RS-4
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Christ Bros. Asphalt, Inc. Low bidder | $657,842 | ||
| 2 | The Kilian Corporation | $750,440 | +14.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Christ Bros. As… | #2 The Kilian Corp… |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 11,035 | SQ FT | $0.00 | $0.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 13,675 | FOOT | $1.91 | $3.25 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 3,318 | TON | $2.93 | $4.75 | |
| 4 | Z0070100 | SURV MONUMENT COV ASY | 3 | EACH | $750.00 | $175.00 | |
| 5 | 40600290 | BIT MATLS TACK CT | 8,889 | POUND | $2.82 | $1.95 | |
| 6 | 40600990 | TEMPORARY RAMP | 50.7 | SQ YD | $14.34 | $0.0100 | |
| 7 | 40603340 | HMA SC "D" N70 | 3,318 | TON | $84.98 | $106.00 | |
| 8 | 44000155 | HMA SURF REM 1 1/2 | 39,506 | SQ YD | $2.49 | $2.95 | |
| 9 | 44200168 | PAVT PATCH T2 14 | 48 | SQ YD | $238.58 | $295.00 | |
| 10 | 44200172 | PAVT PATCH T3 14 | 40 | SQ YD | $238.58 | $295.00 | |
| 11 | 44200174 | PAVT PATCH T4 14 | 107 | SQ YD | $238.58 | $255.00 | |
| 12 | 48102100 | AGG WEDGE SHLD TYPE B | 532 | TON | $19.50 | $30.00 | |
| 13 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $1,500.00 | $2,800.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $54,544.00 | $61,000.00 | |
| 15 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $65,262.00 | $33,525.00 | |
| 16 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.00 | $5,200.00 | |
| 17 | 70300100 | SHORT TERM PAVT MKING | 3,730 | FOOT | $0.9400 | $0.3000 | |
| 18 | 70300150 | SHRT TRM PAVT MK REM | 415 | SQ FT | $0.00 | $7.00 | |
| 19 | 70300220 | TEMP PVT MK LINE 4 | 33,105 | FOOT | $0.00 | $0.00 | |
| 20 | 78000200 | THPL PVT MK LINE 4 | 33,105 | FOOT | $0.6200 | $0.5400 | |
| 21 | 78100100 | RAISED REFL PAVT MKR | 171 | EACH | $37.11 | $38.00 | |
| 22 | 78300200 | RAISED REF PVT MK REM | 171 | EACH | $20.72 | $7.00 |