2018-131-L
- Let date
- Friday, July 12, 2019
- Contract
- 62H54 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- Light tower removal and replacement, installing new light towers, light poles, foundations, conduits, cables, and site restoration at I-57 at US 30 in Matteson and I-290/IL-53 at I-90 in Rolling Meadows.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Meade Inc. Low bidder | $1,225,424 | ||
| 2 | Hecker and Company, Inc. | $1,556,044 | +27.0% | |
| 3 | John Burns Construction Company | $1,644,146 | +34.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Meade Inc. | #2 Hecker and Comp… | #3 John Burns Cons… |
|---|---|---|---|---|---|---|---|---|
| 1 | X1400149 | LUM LED HM C | 125 | EACH | $525.41 | $720.00 | $940.00 | |
| 2 | X1400190 | REM HM LUMNRS SALVAGE | 57 | EACH | $32.72 | $269.00 | $190.00 | |
| 3 | X1400191 | MAINT LTG SYS LOC 1 | 12 | CAL MO | $1,184.54 | $900.00 | $100.00 | |
| 4 | X1400192 | MAINT LTG SYS LOC 2 | 12 | CAL MO | $1,184.54 | $900.00 | $100.00 | |
| 5 | X1400193 | MAINT LTG SYS LOC 3 | 12 | CAL MO | $2,369.08 | $1,340.00 | $100.00 | |
| 6 | X1400259 | LUM HIMAST LED TY D | 14 | EACH | $1,571.34 | $1,850.00 | $2,670.00 | |
| 7 | X1400341 | REM LUMINAIRE SALVAGE | 73 | EACH | $32.72 | $202.00 | $160.00 | |
| 8 | X2501800 | SEEDING CL 4 MOD | 0.48 | ACRE | $1,310.40 | $25,400.00 | $4,500.00 | |
| 9 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,926.40 | $11,200.00 | $11,900.00 | |
| 10 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $23,439.15 | $69,100.00 | $21,600.00 | |
| 11 | X8420502 | REM LT TOWER NO SALV | 18 | EACH | $2,620.56 | $4,500.00 | $4,780.00 | |
| 12 | X8420510 | REM TOWER FDN | 18 | EACH | $1,074.54 | $2,900.00 | $2,355.00 | |
| 13 | X8951011 | REM AERIAL CABLE | 200 | FOOT | $3.93 | $1.55 | $5.70 | |
| 14 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $11,340.00 | $10,700.00 | $9,925.00 | |
| 15 | Z0033020 | LUM SFTY CABLE ASMBLY | 125 | EACH | $63.63 | $40.00 | $365.00 | |
| 16 | 20101000 | TEMPORARY FENCE | 400 | FOOT | $6.30 | $4.05 | $6.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 68 | CU YD | $55.13 | $89.50 | $214.00 | |
| 18 | 21101615 | TOPSOIL F & P 4 | 3,048 | SQ YD | $7.19 | $0.1000 | $5.00 | |
| 19 | 25000210 | SEEDING CL 2A | 0.15 | ACRE | $708.75 | $25,400.00 | $5,000.00 | |
| 20 | 25000400 | NITROGEN FERT NUTR | 13 | POUND | $3.15 | $1.05 | $3.00 | |
| 21 | 25000500 | PHOSPHORUS FERT NUTR | 13 | POUND | $3.15 | $1.05 | $3.00 | |
| 22 | 25000600 | POTASSIUM FERT NUTR | 13 | POUND | $3.15 | $1.05 | $3.00 | |
| 23 | 25100630 | EROSION CONTR BLANKET | 3,048 | SQ YD | $1.05 | $1.05 | $2.50 | |
| 24 | 28000250 | TEMP EROS CONTR SEED | 10 | POUND | $15.75 | $0.1000 | $3.00 | |
| 25 | 28000400 | PERIMETER EROS BAR | 14,158 | FOOT | $2.89 | $2.95 | $2.15 | |
| 26 | 28000500 | INLET & PIPE PROTECT | 5 | EACH | $288.75 | $139.00 | $150.00 | |
| 27 | 28001100 | TEMP EROS CONTR BLANK | 400 | SQ YD | $2.63 | $1.05 | $5.00 | |
| 28 | 31101400 | SUB GRAN MAT B 6 | 60 | SQ YD | $78.50 | $42.50 | $47.85 | |
| 29 | 42000060 | WELDED WIRE REINF | 60 | SQ YD | $113.83 | $16.00 | $10.00 | |
| 30 | 50200100 | STRUCTURE EXCAVATION | 81 | CU YD | $104.70 | $136.00 | $247.55 | |
| 31 | 50300225 | CONC STRUCT | 45 | CU YD | $1,298.94 | $2,080.00 | $2,828.00 | |
| 32 | 50300300 | PROTECTIVE COAT | 86 | SQ YD | $14.53 | $3.20 | $1.00 | |
| 33 | 50800205 | REINF BARS, EPOXY CTD | 5,860 | POUND | $2.80 | $6.50 | $2.30 | |
| 34 | 66900200 | NON SPL WASTE DISPOSL | 255 | CU YD | $151.73 | $144.00 | $202.00 | |
| 35 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,575.00 | $1,710.00 | $1,500.00 | |
| 36 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $3,150.00 | $2,740.00 | $3,000.00 | |
| 37 | 66901002 | ON-SITE MON REG SUB | 15 | CAL DA | $1,260.00 | $907.00 | $1,200.00 | |
| 38 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $3,045.00 | $2,130.00 | $2,900.00 | |
| 39 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,100.00 | $1,890.00 | $2,000.00 | |
| 40 | 67100100 | MOBILIZATION | 1 | L SUM | $70,000.00 | $93,600.00 | $98,000.00 | |
| 41 | 81028240 | UNDRGRD C GALVS 4 | 510 | FOOT | $25.34 | $38.50 | $84.90 | |
| 42 | 81603081 | UD 3#2#4GXLPUSE 1.5 P | 15,460 | FOOT | $8.64 | $11.49 | $15.45 | |
| 43 | 83050825 | LT P A 47.5MH 15DA | 52 | EACH | $2,903.90 | $3,540.00 | $2,900.00 | |
| 44 | 83504500 | LT TOWER 120MH LM 8 | 3 | EACH | $54,678.74 | $52,200.00 | $58,835.00 | |
| 45 | 83600365 | LP F M 15BC 10" X 8' | 52 | EACH | $1,008.64 | $1,260.00 | $1,850.00 | |
| 46 | 83700350 | LT TOWER FDN 54D | 60 | FOOT | $1,523.01 | $1,970.00 | $1,115.00 | |
| 47 | 83800205 | BKWY DEV TR B 15BC | 52 | EACH | $310.74 | $443.00 | $375.00 | |
| 48 | 84100110 | REM TEMP LIGHT UNIT | 2 | EACH | $785.28 | $854.00 | $1,705.00 | |
| 49 | 89502380 | REMOV EX HANDHOLE | 3 | EACH | $785.28 | $506.00 | $1,750.00 |