(123,124,125)RS-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $3,358,134 | ||
| 2 | McCarthy Improvement Company | $4,562,179 | +35.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 McCarthy Improv… |
|---|---|---|---|---|---|---|---|
| 1 | X4400196 | HMA SURF REM SPL | 3,331 | SQ YD | $9.00 | $12.25 | |
| 2 | X7030005 | TEMP PAVT MKING REMOV | 51,218 | SQ FT | $1.20 | $1.20 | |
| 3 | X7830060 | GRV RCSD PM LTR & SYM | 127 | SQ FT | $6.00 | $6.00 | |
| 4 | X7830070 | GRV RCSD PVT MRKG 5 | 4,730 | FOOT | $0.5000 | $0.5000 | |
| 5 | X7830076 | GRV RCSD PVT MRKG 9 | 927 | FOOT | $0.7500 | $0.7500 | |
| 6 | X7830078 | GRV RCSD PVT MRKG 13 | 381 | FOOT | $2.50 | $2.50 | |
| 7 | X7830090 | GRV RCSD PVT MRKG 25 | 53 | FOOT | $5.00 | $5.00 | |
| 8 | Z0004405 | HMA SCAR | 138,142 | SQ YD | $0.5000 | $0.7000 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,285.00 | $5,000.00 | |
| 10 | Z0028415 | GEOTECHNICAL REINF | 420 | SQ YD | $1.50 | $6.25 | |
| 11 | Z0034105 | MATL TRANSFER DEVICE | 24,000 | TON | $2.20 | $3.15 | |
| 12 | 20200100 | EARTH EXCAVATION | 126 | CU YD | $35.00 | $150.00 | |
| 13 | 20400800 | FURNISHED EXCAVATION | 375 | CU YD | $50.00 | $116.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 121 | SQ YD | $12.50 | $10.00 | |
| 15 | 25200110 | SODDING SALT TOLERANT | 121 | SQ YD | $85.00 | $15.00 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $5.00 | $2.00 | |
| 17 | 30300001 | AGG SUBGRADE IMPROVE | 70 | CU YD | $50.00 | $122.00 | |
| 18 | 35101400 | AGG BASE CSE B | 280 | TON | $30.00 | $120.00 | |
| 19 | 40600290 | BIT MATLS TACK CT | 119,792 | POUND | $0.8000 | $0.0100 | |
| 20 | 40600525 | LEV BIND HM N50 | 110 | TON | $250.00 | $229.00 | |
| 21 | 40600627 | LB MM IL-9.5FG N50 | 9,270 | TON | $70.00 | $104.50 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 1,402 | SQ YD | $10.00 | $13.00 | |
| 23 | 40600990 | TEMPORARY RAMP | 544 | SQ YD | $15.00 | $24.00 | |
| 24 | 40601005 | HMA REPL OVER PATCH | 1,209 | TON | $145.00 | $152.00 | |
| 25 | 40603310 | HMA SC "C" N50 | 14,730 | TON | $70.00 | $100.00 | |
| 26 | 40800050 | INCIDENTAL HMA SURF | 1,585 | TON | $135.00 | $232.00 | |
| 27 | 42400200 | PC CONC SIDEWALK 5 | 228 | SQ FT | $18.50 | $47.50 | |
| 28 | 42400800 | DETECTABLE WARNINGS | 44 | SQ FT | $30.00 | $55.00 | |
| 29 | 44000158 | HMA SURF REM 2 1/4 | 30,403 | SQ YD | $2.00 | $3.15 | |
| 30 | 44000600 | SIDEWALK REM | 153 | SQ FT | $7.20 | $16.00 | |
| 31 | 44002227 | HMA RM OV PATCH 6 3/4 | 3,200 | SQ YD | $25.00 | $59.00 | |
| 32 | 44200156 | PAVT PATCH T2 13 | 139 | SQ YD | $125.00 | $360.00 | |
| 33 | 44200160 | PAVT PATCH T3 13 | 50 | SQ YD | $125.00 | $340.00 | |
| 34 | 44200162 | PAVT PATCH T4 13 | 232 | SQ YD | $125.00 | $145.00 | |
| 35 | 44201803 | CL D PATCH T2 13 | 17 | SQ YD | $200.00 | $235.00 | |
| 36 | 48102100 | AGG WEDGE SHLD TYPE B | 9,872 | TON | $25.00 | $17.40 | |
| 37 | 63000001 | SPBGR TY A 6FT POSTS | 537.5 | FOOT | $20.00 | $20.00 | |
| 38 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $2,750.00 | $2,750.00 | |
| 39 | 63100169 | TR BAR TRM T1 SPL FLR | 4 | EACH | $2,600.00 | $2,600.00 | |
| 40 | 63200310 | GUARDRAIL REMOV | 1,175 | FOOT | $4.85 | $4.85 | |
| 41 | 63500105 | DELINEATORS | 12 | EACH | $60.00 | $60.00 | |
| 42 | 66700305 | PERM SURV MKRS T2 | 1 | EACH | $450.00 | $1,900.00 | |
| 43 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,675.00 | $3,100.00 | |
| 44 | 67100100 | MOBILIZATION | 1 | L SUM | $200,000.00 | $273,500.00 | |
| 45 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,500.00 | $2,500.00 | |
| 46 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $20,000.00 | $34,300.00 | |
| 47 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $2,000.00 | $2,000.00 | |
| 48 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $100.00 | |
| 49 | 70103815 | TR CONT SURVEILLANCE | 5 | CAL DA | $500.00 | $975.00 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 17,636 | FOOT | $0.5000 | $1.20 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 2,012 | SQ FT | $1.75 | $5.00 | |
| 52 | 70300210 | TEMP PVT MK LTR & SYM | 127 | SQ FT | $2.50 | $2.50 | |
| 53 | 70300220 | TEMP PVT MK LINE 4 | 148,694 | FOOT | $0.1000 | $0.1000 | |
| 54 | 70300240 | TEMP PVT MK LINE 6 | 714 | FOOT | $0.1500 | $0.1500 | |
| 55 | 70300250 | TEMP PVT MK LINE 8 | 927 | FOOT | $0.2000 | $0.2000 | |
| 56 | 70300260 | TEMP PVT MK LINE 12 | 381 | FOOT | $0.3000 | $0.3000 | |
| 57 | 70300280 | TEMP PVT MK LINE 24 | 86 | FOOT | $2.45 | $2.45 | |
| 58 | 72501000 | TERMINAL MARKER - DA | 12 | EACH | $35.00 | $9.00 | |
| 59 | 78000100 | THPL PVT MK LTR & SYM | 127 | SQ FT | $6.50 | $6.50 | |
| 60 | 78000200 | THPL PVT MK LINE 4 | 4,730 | FOOT | $1.07 | $1.07 | |
| 61 | 78000500 | THPL PVT MK LINE 8 | 927 | FOOT | $2.14 | $2.14 | |
| 62 | 78000600 | THPL PVT MK LINE 12 | 381 | FOOT | $3.22 | $3.22 | |
| 63 | 78000650 | THPL PVT MK LINE 24 | 53 | FOOT | $6.45 | $6.45 | |
| 64 | 78005110 | EPOXY PVT MK LINE 4 | 143,964 | FOOT | $0.6100 | $0.6100 | |
| 65 | 78005130 | EPOXY PVT MK LINE 6 | 714 | FOOT | $0.9200 | $0.9200 | |
| 66 | 78005180 | EPOXY PVT MK LINE 24 | 33 | FOOT | $4.50 | $4.50 | |
| 67 | 78100100 | RAISED REFL PAVT MKR | 144 | EACH | $34.62 | $34.62 | |
| 68 | 78200005 | GRDRAIL REF TYPE A | 14 | EACH | $9.00 | $35.00 | |
| 69 | 78300200 | RAISED REF PVT MK REM | 154 | EACH | $10.00 | $10.25 |