2019-015-RS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $2,634,888 | ||
| 2 | Plote Construction, Inc. | $2,714,847 | +3.0% | |
| 3 | Arrow Road Construction Co. | $2,722,904 | +3.3% | |
| 4 | Peter Baker & Son Co. | $2,736,295 | +3.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 Plote Construct… | #3 Arrow Road Cons… | #4 Peter Baker & S… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $12,000.00 | $10,000.00 | $8,500.00 | $3,600.00 | |
| 2 | X4060004 | P HMA SC SMA 9.5 N80 | 6,299 | TON | $96.00 | $90.00 | $111.00 | $116.80 | |
| 3 | X5537800 | SS CLEANED 12 | 1,000 | FOOT | $7.95 | $3.50 | $7.95 | $1.50 | |
| 4 | X6030310 | FR & LIDS ADJUST SPL | 56 | EACH | $950.00 | $925.00 | $925.00 | $915.00 | |
| 5 | X7030005 | TEMP PAVT MKING REMOV | 17,191 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 6 | Z0004562 | COMB C C&G REM & REPL | 2,000 | FOOT | $55.00 | $45.00 | $43.00 | $43.00 | |
| 7 | Z0018500 | DRAINAGE STR CLEANED | 135 | EACH | $335.00 | $315.00 | $335.00 | $225.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 154.2 | SQ FT | $20.00 | $16.00 | $17.00 | $10.00 | |
| 9 | Z0033700 | LONG JOINT SEALANT | 37,180 | FOOT | $2.30 | $1.85 | $2.00 | $2.35 | |
| 10 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $8,000.00 | $7,000.00 | $5,000.00 | $4,000.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 54 | CU YD | $65.00 | $125.00 | $125.00 | $125.00 | |
| 12 | 21101615 | TOPSOIL F & P 4 | 300 | SQ YD | $2.00 | $7.98 | $7.98 | $7.98 | |
| 13 | 25000400 | NITROGEN FERT NUTR | 6 | POUND | $2.00 | $4.00 | $4.00 | $4.00 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 6 | POUND | $2.00 | $4.00 | $4.00 | $4.00 | |
| 15 | 25200110 | SODDING SALT TOLERANT | 300 | SQ YD | $14.00 | $14.00 | $14.00 | $14.00 | |
| 16 | 25200200 | SUPPLE WATERING | 3 | UNIT | $200.00 | $25.00 | $25.00 | $25.00 | |
| 17 | 35501316 | HMA BASE CSE 8 | 55 | SQ YD | $75.00 | $102.00 | $125.00 | $75.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 45,780 | POUND | $0.0100 | $0.0100 | $0.9000 | $0.0100 | |
| 19 | 40600400 | MIX CR JTS FLANGEWYS | 102 | TON | $465.00 | $400.00 | $150.00 | $605.00 | |
| 20 | 40600635 | LEV BIND MM N70 | 7,070 | TON | $74.00 | $72.00 | $75.50 | $71.20 | |
| 21 | 40600982 | HMA SURF REM BUTT JT | 396 | SQ YD | $28.00 | $11.10 | $7.00 | $5.00 | |
| 22 | 40603335 | HMA SC "D" N50 | 6 | TON | $275.00 | $220.00 | $400.00 | $300.00 | |
| 23 | 42001300 | PROTECTIVE COAT | 260 | SQ YD | $1.00 | $3.00 | $3.00 | $3.00 | |
| 24 | 42300200 | PCC DRIVEWAY PAVT 6 | 49 | SQ YD | $63.00 | $95.00 | $95.00 | $95.00 | |
| 25 | 42400200 | PC CONC SIDEWALK 5 | 2,335 | SQ FT | $9.00 | $9.00 | $8.50 | $8.50 | |
| 26 | 42400300 | PC CONC SIDEWALK 6 | 83 | SQ FT | $10.00 | $20.00 | $20.00 | $20.00 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 390 | SQ FT | $35.00 | $38.00 | $38.00 | $38.00 | |
| 28 | 44000159 | HMA SURF REM 2 1/2 | 7,320 | SQ YD | $3.40 | $3.50 | $3.45 | $3.05 | |
| 29 | 44000164 | HMA SURF REM 3 3/4 | 64,271 | SQ YD | $4.00 | $3.00 | $5.00 | $4.50 | |
| 30 | 44000200 | DRIVE PAVEMENT REM | 49 | SQ YD | $27.00 | $25.00 | $25.00 | $25.00 | |
| 31 | 44000600 | SIDEWALK REM | 2,335 | SQ FT | $4.00 | $5.00 | $3.50 | $3.50 | |
| 32 | 44201741 | CL D PATCH T2 8 | 611 | SQ YD | $83.50 | $60.00 | $21.00 | $80.00 | |
| 33 | 44201745 | CL D PATCH T3 8 | 408 | SQ YD | $80.50 | $50.00 | $21.00 | $75.00 | |
| 34 | 44201747 | CL D PATCH T4 8 | 340 | SQ YD | $72.50 | $50.00 | $21.00 | $70.00 | |
| 35 | 44201753 | CL D PATCH T2 9 | 907 | SQ YD | $92.50 | $70.00 | $24.00 | $85.00 | |
| 36 | 44201757 | CL D PATCH T3 9 | 604 | SQ YD | $87.00 | $60.00 | $24.00 | $80.00 | |
| 37 | 44201759 | CL D PATCH T4 9 | 504 | SQ YD | $80.00 | $60.00 | $24.00 | $75.00 | |
| 38 | 60251740 | CB ADJ NEW T24F&G | 15 | EACH | $800.00 | $890.00 | $890.00 | $710.00 | |
| 39 | 60255410 | CB CLEANED | 45 | EACH | $335.00 | $315.00 | $335.00 | $300.00 | |
| 40 | 60300105 | FR & GRATES ADJUST | 12 | EACH | $500.00 | $495.00 | $495.00 | $480.00 | |
| 41 | 60300305 | FR & LIDS ADJUST | 4 | EACH | $600.00 | $685.00 | $685.00 | $520.00 | |
| 42 | 60406100 | FR & LIDS T1 CL | 15 | EACH | $425.00 | $500.00 | $500.00 | $300.00 | |
| 43 | 66900200 | NON SPL WASTE DISPOSL | 54 | CU YD | $150.00 | $110.00 | $135.00 | $195.00 | |
| 44 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,750.00 | $1,200.00 | $1,450.00 | $1,800.00 | |
| 45 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,500.00 | $2,200.00 | $2,000.00 | $3,300.00 | |
| 46 | 66901002 | ON-SITE MON REG SUB | 15 | CAL DA | $600.00 | $100.00 | $700.00 | $680.00 | |
| 47 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,000.00 | $1,800.00 | $1,000.00 | $900.00 | |
| 48 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,500.00 | $3,500.00 | $2,500.00 | $2,750.00 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $157,265.58 | $163,000.00 | $168,000.00 | $208,615.00 | |
| 50 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1.00 | $1.00 | $252,000.00 | $1.00 | |
| 51 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $40,000.00 | $416,800.00 | $1.00 | $67,150.00 | |
| 52 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 53 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $15,000.00 | $10,000.00 | $2,500.00 | $1.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 22,560 | FOOT | $1.10 | $0.0100 | $0.3500 | $0.3000 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 7,520 | SQ FT | $1.15 | $0.0100 | $0.9000 | $0.0100 | |
| 56 | 70300210 | TEMP PVT MK LTR & SYM | 1,513.2 | SQ FT | $1.25 | $0.9500 | $0.0100 | $1.00 | |
| 57 | 70300220 | TEMP PVT MK LINE 4 | 30,742 | FOOT | $0.2800 | $0.2500 | $0.0100 | $0.2200 | |
| 58 | 70300240 | TEMP PVT MK LINE 6 | 3,688 | FOOT | $0.3500 | $0.4000 | $0.0100 | $0.2500 | |
| 59 | 70300250 | TEMP PVT MK LINE 8 | 573 | FOOT | $0.6000 | $0.8500 | $0.0100 | $0.6000 | |
| 60 | 70300260 | TEMP PVT MK LINE 12 | 1,614 | FOOT | $0.9000 | $0.7500 | $0.0100 | $0.7000 | |
| 61 | 70300280 | TEMP PVT MK LINE 24 | 795 | FOOT | $1.25 | $1.10 | $0.0100 | $1.00 | |
| 62 | 70300520 | PAVT MARK TAPE T3 4 | 5,600 | FOOT | $1.25 | $0.0100 | $0.8000 | $1.95 | |
| 63 | 72400710 | RELOC SIGN PANEL T1 | 12.5 | SQ FT | $25.00 | $75.00 | $30.00 | $16.00 | |
| 64 | 78000100 | THPL PVT MK LTR & SYM | 1,513.2 | SQ FT | $4.55 | $4.00 | $3.75 | $3.75 | |
| 65 | 78000200 | THPL PVT MK LINE 4 | 30,742 | FOOT | $0.6200 | $0.5000 | $0.5800 | $0.5800 | |
| 66 | 78000400 | THPL PVT MK LINE 6 | 3,688 | FOOT | $1.05 | $0.7000 | $0.7500 | $0.7500 | |
| 67 | 78000500 | THPL PVT MK LINE 8 | 573 | FOOT | $1.25 | $1.00 | $1.00 | $1.00 | |
| 68 | 78000600 | THPL PVT MK LINE 12 | 1,614 | FOOT | $2.15 | $1.40 | $1.50 | $1.50 | |
| 69 | 78000650 | THPL PVT MK LINE 24 | 795 | FOOT | $4.75 | $4.00 | $3.75 | $3.75 | |
| 70 | 78100100 | RAISED REFL PAVT MKR | 1,381 | EACH | $29.00 | $20.00 | $24.00 | $24.00 | |
| 71 | 78300200 | RAISED REF PVT MK REM | 1,030 | EACH | $12.00 | $14.00 | $4.50 | $10.00 | |
| 72 | 85000200 | MAIN EX TR SIG INSTAL | 3 | EACH | $1,500.00 | $5,000.00 | $2,400.00 | $2,400.00 | |
| 73 | 88600600 | DET LOOP REPL | 2,261 | FOOT | $15.90 | $17.00 | $17.00 | $17.00 | |
| 74 | 89502376 | REBUILD EX HANDHOLE | 4 | EACH | $2,364.00 | $2,200.00 | $2,200.00 | $2,200.00 |