(17,18)RS-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curran Contracting Company Low bidder | $2,407,407 | ||
| 2 | Advanced Asphalt Company | $2,463,612 | +2.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curran Contract… | #2 Advanced Asphal… |
|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 28,166 | SQ FT | $0.1000 | $0.6000 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 2,490 | SQ YD | $11.00 | $3.00 | |
| 3 | Z0004556 | HMA SURFACE RM (DECK) | 1,210 | SQ YD | $10.15 | $3.00 | |
| 4 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $35.00 | $46.00 | |
| 5 | Z0033700 | LONG JOINT SEALANT | 33,031 | FOOT | $2.15 | $1.90 | |
| 6 | Z0034105 | MATL TRANSFER DEVICE | 20,580 | TON | $2.10 | $2.25 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,500.00 | $3,000.00 | |
| 8 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | |
| 10 | 20400800 | FURNISHED EXCAVATION | 40 | CU YD | $150.00 | $100.00 | |
| 11 | 40200800 | AGG SURF CSE B | 115 | TON | $62.00 | $40.00 | |
| 12 | 40600290 | BIT MATLS TACK CT | 66,153 | POUND | $0.0100 | $0.6000 | |
| 13 | 40600400 | MIX CR JTS FLANGEWYS | 29 | TON | $185.00 | $125.00 | |
| 14 | 40600525 | LEV BIND HM N50 | 49 | TON | $185.00 | $125.00 | |
| 15 | 40600625 | LEV BIND MM N50 | 10,976 | TON | $58.50 | $72.00 | |
| 16 | 40600990 | TEMPORARY RAMP | 381 | SQ YD | $20.00 | $15.00 | |
| 17 | 40603310 | HMA SC "C" N50 | 9,672 | TON | $60.00 | $72.00 | |
| 18 | 40800050 | INCIDENTAL HMA SURF | 516 | TON | $165.00 | $135.00 | |
| 19 | 44000155 | HMA SURF REM 1 1/2 | 3,656 | SQ YD | $5.50 | $3.00 | |
| 20 | 44000164 | HMA SURF REM 3 3/4 | 98,004 | SQ YD | $2.70 | $3.00 | |
| 21 | 48102100 | AGG WEDGE SHLD TYPE B | 7,079 | TON | $21.25 | $21.25 | |
| 22 | 66700205 | PERM SURV MKRS T1 | 3 | EACH | $2,200.00 | $180.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $269,230.78 | $145,000.00 | |
| 24 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $78,804.40 | $14,800.00 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 11,093 | FOOT | $0.3000 | $0.4500 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 2,440 | SQ FT | $1.50 | $1.15 | |
| 27 | 70300210 | TEMP PVT MK LTR & SYM | 61 | SQ FT | $2.50 | $2.50 | |
| 28 | 70300220 | TEMP PVT MK LINE 4 | 71,335 | FOOT | $0.1000 | $0.1000 | |
| 29 | 70300240 | TEMP PVT MK LINE 6 | 7,936 | FOOT | $0.1200 | $0.1400 | |
| 30 | 70300280 | TEMP PVT MK LINE 24 | 298 | FOOT | $2.00 | $2.25 | |
| 31 | 78000100 | THPL PVT MK LTR & SYM | 61 | SQ FT | $6.00 | $15.00 | |
| 32 | 78000200 | THPL PVT MK LINE 4 | 713 | FOOT | $3.25 | $2.61 | |
| 33 | 78000400 | THPL PVT MK LINE 6 | 21 | FOOT | $5.00 | $3.92 | |
| 34 | 78000650 | THPL PVT MK LINE 24 | 298 | FOOT | $6.00 | $14.50 | |
| 35 | 78001110 | PAINT PVT MK LINE 4 | 141,444 | FOOT | $0.1800 | $0.0900 | |
| 36 | 78001130 | PAINT PVT MK LINE 6 | 15,830 | FOOT | $0.3200 | $0.1400 | |
| 37 | 78100100 | RAISED REFL PAVT MKR | 414 | EACH | $35.00 | $27.45 | |
| 38 | 78300200 | RAISED REF PVT MK REM | 384 | EACH | $30.00 | $10.00 |