Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jun 12, 2019 | 6343-81-001RMC - 634381001 | Houston Lufkin |
GUARD FENCE, ATTENUATOR & METAL RAIL RPRUS 287 · | $237,050 | $283,356 | CATOCON, INC. | +19.5% | 1 |
| Jun 12, 2019 | 6325-80-001RMC - 632580001 | Tarrant Fort Worth |
CALL-OUT STRIPINGIH 820 · | $213,964 | $220,890 | STRIPING TECHNOLOGY, L.P. | +3.2% | 4 |
| Jun 11, 2019 | 6342-55-001RMC - 634255001 | Kaufman Dallas |
MISCELLANEOUS CONCRETE REPAIRUS 80 · | $263,590 | $274,720 | GIBSON & ASSOCIATES, INC. | +4.2% | 4 |
| Jun 5, 2019 | 0200-03-021NH 2014(444) | Angelina Lufkin |
GRADING, STRUCTURES, BASE & SURFACEUS 69 · | $32,534,931 | $37,447,955 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | +15.1% | 4 |
| Jun 5, 2019 | 0461-05-011STP 2019(753) | Yoakum |
SUPER 2 PASSING LANESSH 214 · | $21,661,892 | $24,052,608 | DUININCK, INC. | +11.0% | 4 |
| Jun 5, 2019 | 0048-03-050BR 2019(856) | Ellis Dallas |
REPLACE BRG & APPR,GR,STORM SEWER,BASE, SURFUS 77 · | $21,858,750 | $23,695,771 | FLUOR HEAVY CIVIL, LLC | +8.4% | 7 |
| Jun 5, 2019 | 0301-06-018STP 1902(059) | Frio San Antonio |
REHAB & WIDEN TO PROVIDE PASS LNS & OP IMPROVSH 85 · | $19,884,678 | $22,794,970 | ANDERSON COLUMBIA CO., INC. | +14.6% | 3 |
| Jun 5, 2019 | 0301-03-027STP 1902(058) | Frio San Antonio |
GRD, BSE, SURF, PAV'T MRKSH 85 · | $17,932,619 | $18,027,138 | ANDERSON COLUMBIA CO., INC. | +0.5% | 3 |
| Jun 5, 2019 | 0280-02-040STP 2019(862) | Collin Dallas |
WIDEN SHLDRS & REPLACE BR RAIL & APPROACH RAILINGSH 78 · | $13,471,009 | $15,143,488 | D. L. LENNON INCORPORATED - CONTRACTOR | +12.4% | 7 |
| Jun 5, 2019 | 0470-01-028STP 1902(061) | Comal San Antonio |
OVERLAYFM 1863 · | $13,961,724 | $13,058,153 | CLARK CONSTRUCTION OF TEXAS, INC. | -6.5% | 5 |
| Jun 5, 2019 | 0092-14-096BR 1902(250) | Dallas Dallas |
REHABILITATE BRIDGEIH 45 · | $5,431,593 | $8,251,403 | GIBSON & ASSOCIATES, INC. | +51.9% | 1 |
| Jun 5, 2019 | 0291-07-034STP 1902(064)HES | Bandera San Antonio |
INST PROTECTION, WIDEN SHLDRS & PAV MARKSSH 16 · | $5,081,810 | $4,979,184 | HUNTER INDUSTRIES, LTD. | -2.0% | 6 |
| Jun 5, 2019 | 6341-21-001RMC - 634121001 | Dallas Dallas |
GUARD FENCE & CABLE REPAIRSL 12 · | $5,270,095 | $4,890,506 | FIREMAN EXCAVATING, INC. | -7.2% | 3 |
| Jun 5, 2019 | 6342-80-001RMC - 634280001 | Smith Tyler |
IH-20 TOTAL MAINTENANCEIH 20 · | $4,924,948 | $4,687,552 | FIREMAN EXCAVATING, INC. | -4.8% | 1 |
| Jun 5, 2019 | 2706-01-008STP 1902(037)HES | Montague Wichita Falls |
SAFETY TRT FXD OBJ, ADDL SURF WIDTH, RUMBLE STRIPSFM 2634 · | $3,903,626 | $4,677,007 | EUROVIA ATLANTIC COAST LLC | +19.8% | 3 |
| Jun 5, 2019 | 0092-14-092C 92-14-92 | Dallas Dallas |
FULL DEPTH CONCRETE REPAIR ON FRONTAGE ROADSIH 345 · | $4,091,632 | $3,979,914 | RAGLE CONSTRUCTION, INC. | -2.7% | 5 |
| Jun 5, 2019 | 0009-09-106STP 1902(034)HES | Hopkins Paris |
SAFETY IMPROVEMENT PROJECTSIH 30 · | $3,988,122 | $3,952,539 | DBI SERVICES, LLC | -0.9% | 6 |
| Jun 5, 2019 | 0158-01-083STP 1902(010)HES | Runnels San Angelo |
INSTALL CABLE BARRIERUS 67 · | $4,143,679 | $3,312,755 | GRATIOT CONSTRUCTION, LTD. | -20.1% | 7 |
| Jun 5, 2019 | 0905-00-105STP 2019(998) | Lubbock Lubbock |
PEDESTRIAN, SIDEWALKS, & CURB RAMPSVA · | $2,713,037 | $3,291,800 | TI-ZACK CONCRETE, INC. | +21.3% | 2 |
| Jun 5, 2019 | 0197-02-126NH 2019(861) | Dallas Dallas |
MILL, FDR AND ACP OVERLAY ON FRONTAGE ROADSUS 175 · | $2,782,809 | $3,063,098 | O. TREVINO CONSTRUCTION, LLC | +10.1% | 5 |
| Jun 5, 2019 | 6342-47-001RMC - 634247001 | Dallas Dallas |
MANAGED LANE IN DALLAS & DENTON COUNTYIH 35E · | $2,533,193 | $2,940,588 | ROY JORGENSEN ASSOCIATES, INC. | +16.1% | 3 |
| Jun 5, 2019 | 6338-53-001RMC - 633853001 | Jefferson Beaumont |
HIGH VOLUME SWEEPINGIH 10 · | $3,791,620 | $2,886,280 | SWEEPING SERVICES OF TEXAS - OPERATING, L.P. | -23.9% | 1 |
| Jun 5, 2019 | 1198-03-010SSW 1198-3-10 | Bell Waco |
PROVIDE ADD'L PAVED SURFACE WID, ADD RUMBLE STRIPSFM 2670 · | $2,256,306 | $2,672,894 | TEXAS MATERIALS GROUP, INC. | +18.5% | 2 |
| Jun 5, 2019 | 1615-02-016STP 1902(043)HES | Clay Wichita Falls |
SAFETY TRT FXD OBJ, ADDL SURF WIDTH, RUMBLE STRIPSFM 1740 · | $1,837,035 | $2,420,442 | A. L. HELMCAMP, INC. | +31.8% | 1 |
| Jun 5, 2019 | 0430-01-060STP 2019(866)HES | Dallas Dallas |
IMPROVEMENT OF TRAFFIC SIGNALSSH 352 · | $2,631,669 | $2,199,905 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | -16.4% | 4 |
| Jun 5, 2019 | 0908-19-025BR 2018(378) | Scurry Abilene |
REMOVE AND REPLACE EXISTING BRIDGE AND APPROACHESCR · | $2,201,960 | $2,153,443 | HODGES AND SON CONSTRUCTION COMPANY, INC. | -2.2% | 6 |
| Jun 5, 2019 | 3256-02-095NH 2018(461) | Harris Houston |
FRNTG RD PAV RPR W/ 2.5"TBCO,MRK & LP DETECTSL 8 · | $1,722,587 | $2,046,085 | ANGEL BROTHERS HOLDINGS CORP. | +18.8% | 2 |
| Jun 5, 2019 | 1145-01-044BR 1902(019) | Leon Bryan |
BRIDGE REPLACEMENTFM 1511 · | $2,034,217 | $2,035,078 | PIERCE R & B LLC | +0.0% | 6 |
| Jun 5, 2019 | 6343-32-001RMC - 634332001 | Navarro Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRIH 45 · | $1,521,940 | $1,923,119 | KNIFE RIVER CORPORATION - SOUTH | +26.4% | 3 |
| Jun 5, 2019 | 6341-82-001RMC - 634182001 | Harris Houston |
MNT OF TRAFFIC SIGNLSIH 610 · | $1,873,815 | $1,803,182 | THIRD COAST SERVICES LLC | -3.8% | 4 |
| Jun 5, 2019 | 0913-09-088BR 1702(586) | Wharton Yoakum |
REPLACE BRIDGE AND APPROACHESCR · | $1,254,158 | $1,639,006 | REXCO CONSTRUCTION SERVICES, INC. | +30.7% | 3 |
| Jun 5, 2019 | 1068-01-221NH 2019(885) | Tarrant Fort Worth |
GR, BS, DR, PAVIH 30 · | $1,550,610 | $1,477,580 | PEACHTREE CONSTRUCTION, LTD. | -4.7% | 2 |
| Jun 5, 2019 | 6343-28-001RMC - 634328001 | Collin Dallas |
REFLECTORIZED PAVEMENT MARKINGS& MARKERSUS 75 · | $1,478,169 | $1,432,339 | STRIPING TECHNOLOGY, L.P. | -3.1% | 3 |
| Jun 5, 2019 | 0905-00-095STP 2019(997) | Lubbock Lubbock |
REHABILITATE EXISTING ROADWAYVA · | $1,494,203 | $1,274,329 | WINDING ROAD CONSTRUCTION, INC. | -14.7% | 2 |
| Jun 5, 2019 | 0346-02-016STP 1902(023)HES | Jackson Yoakum |
INCREASE SUPERELEVATIONSH 111 · | $1,212,241 | $1,235,556 | HUNTER INDUSTRIES, LTD. | +1.9% | 3 |
| Jun 5, 2019 | 6343-93-001RMC - 634393001 | Harris Houston |
MNT OF ILLUM SYSTEMSIH 610 · | $1,633,907 | $1,234,412 | VACA UNDERGROUND UTILITIES INC | -24.5% | 5 |
| Jun 5, 2019 | 0021-06-027STP 1902(011)HES | Pecos Odessa |
PROFILE EDGELINE CENTERLINE MARKINGUS 90 · | $1,821,917 | $1,150,725 | TOTAL HIGHWAY MAINTENANCE, LLC | -36.8% | 6 |
| Jun 5, 2019 | 6341-27-001RMC - 634127001 | Walker Bryan |
HMA MILL AND INLAYSH 30 · | $1,028,005 | $1,137,392 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | +10.6% | 3 |
| Jun 5, 2019 | 0027-13-234BR 1902(309) | Harris Houston |
REPLACE BEARING PADSIH 69 · | $1,000,721 | $1,045,020 | RAGLE CONSTRUCTION, INC. | +4.4% | 5 |
| Jun 5, 2019 | 0320-04-027NH 2019(993) | Williamson Austin |
LANDSCAPE DEVELOPMENTUS 79 · | $1,284,714 | $1,038,569 | APEX LANDSCAPE & IRRIGATION, LLC | -19.2% | 5 |
| Jun 5, 2019 | 0374-02-107CM 2019(991) | El Paso El Paso |
OPERATIONAL IMPROVEMENTSUS 62 · | $850,074 | $1,033,028 | INTERNATIONAL EAGLE ENTERPRISES, INC. | +21.5% | 3 |
| Jun 5, 2019 | 1498-01-008BR 1902(021) | Fayette Yoakum |
REPLACE BRIDGE AND APPROACHESFM 1579 · | $1,089,257 | $1,026,049 | SB CONTRACTORS LLC | -5.8% | 10 |
| Jun 5, 2019 | 6340-59-001RMC - 634059001 | Walker Bryan |
SPOT BASE REPAIRSH 30 · | $1,128,597 | $1,020,358 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | -9.6% | 3 |
| Jun 5, 2019 | 1567-02-035NH 1902(198) | Denton Dallas |
PLANTING AND IRRIGATIONFM 423 · | $1,071,656 | $958,664 | CENTRAL NORTH CONSTRUCTION, LLC | -10.5% | 4 |
| Jun 5, 2019 | 0909-38-082BR 2018(296) | Falls Waco |
REPL BR & APPRSCR · | $936,885 | $887,644 | ELLIS-MCGINNIS CONSTRUCTION CO. | -5.3% | 6 |
| Jun 5, 2019 | 6341-28-001RMC - 634128001 | Washington Bryan |
HMA MILL AND INLAYUS 290 · | $882,355 | $885,498 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | +0.4% | 3 |
| Jun 5, 2019 | 0007-06-264STP 2019(986)HES | Eastland Brownwood |
INSTALL MEDIAN BARRIERIH 20 · | $1,146,561 | $848,830 | GRATIOT CONSTRUCTION, LTD. | -26.0% | 6 |
| Jun 5, 2019 | 0906-32-057STP 2019(481)TAPS | Midland Odessa |
BICYCLE AND PEDESTRIAN IMPROVEMENTSCS · | $767,308 | $834,327 | ENCINO LANDSCAPE, INC. | +8.7% | 3 |
| Jun 5, 2019 | 6342-44-001RMC - 634244001 | Dallas Dallas |
REPAIR/REPLACE CONCRETE BARRIERSL 12 · | $968,950 | $773,540 | GIBSON & ASSOCIATES, INC. | -20.2% | 5 |
| Jun 5, 2019 | 6340-60-001RMC - 634060001 | Washington Bryan |
SPOT BASE REPAIRUS 290 · | $806,412 | $769,528 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | -4.6% | 3 |
| Jun 5, 2019 | 0910-00-126C 910-00-126 | Smith Tyler |
THERMOPLASTIC & PROFILE PAVEMENT MARKINGSVA · | $892,205 | $738,214 | TOTAL HIGHWAY MAINTENANCE, LLC | -17.3% | 4 |
| Jun 5, 2019 | 0249-08-044STP 2019(414) | Palo Pinto Fort Worth |
PEDESTRIAN & ADA IMPROVEMENTSUS 281 · | $562,566 | $732,353 | ENCINO LANDSCAPE, INC. | +30.2% | 3 |
| Jun 5, 2019 | 6340-58-001RMC - 634058001 | Brazos Bryan |
SPOT BASE REPAIRSH 6 · | $719,876 | $713,352 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | -0.9% | 3 |
| Jun 5, 2019 | 6288-86-001RMC - 628886001 | Bowie Atlanta |
INSTALLATION OF PAVEMENT MARKINGSUS 82 · | $631,901 | $671,714 | STRIPING TECHNOLOGY, L.P. | +6.3% | 4 |
| Jun 5, 2019 | 3115-01-011STP 1902(007)HES | Bastrop Austin |
IMPROVE GUARDRAIL, SAFETY TREAT FIXED OBJECTSFM 3000 · | $422,791 | $628,355 | RELMCO, INC. | +48.6% | 5 |
| Jun 5, 2019 | 6343-40-001RMC - 634340001 | Denton Dallas |
FULL DEPTH CONCRETE REPAIRSL 288 · | $539,086 | $626,903 | SILVER CREEK CONSTRUCTION, INC. | +16.3% | 4 |
| Jun 5, 2019 | 0271-14-237BR 1902(003) | Harris Houston |
REPLACE BEARING PADSIH 610 · | $736,095 | $578,700 | FORDE CONSTRUCTION COMPANY, INC. | -21.4% | 3 |
| Jun 5, 2019 | 6344-70-001RMC - 634470001 | Harris Houston |
SMALL SIGN INSTALLATIONFM 521 · | $705,434 | $578,300 | VACA UNDERGROUND UTILITIES INC | -18.0% | 3 |
| Jun 5, 2019 | 0252-01-085STP 1902(237)HES | Burnet Austin |
SAFETYUS 281 · | $471,248 | $562,105 | LONE STAR PAVING COMPANY | +19.3% | 1 |
| Jun 5, 2019 | 6341-26-001RMC - 634126001 | Brazos Bryan |
HMA MILL AND INLAYBS 6R · | $547,402 | $546,196 | KNIFE RIVER CORPORATION - SOUTH | -0.2% | 3 |
| Jun 5, 2019 | 0901-19-180BR 2018(617) | Grayson Paris |
BRIDGE REPLACEMENTCR · | $469,142 | $475,467 | HIGHWAY 19 CONSTRUCTION LLC | +1.3% | 8 |
| Jun 5, 2019 | 0915-00-211STP 2019(796)MM | Bexar San Antonio |
SIGNAL UPGRADESVA · | $466,337 | $409,939 | THE LEVY COMPANY, INC. | -12.1% | 3 |
| Jun 5, 2019 | 0057-03-043STP 1902(028)HES | Freestone Bryan |
INSTALL MEDIAN BARRIERUS 84 · | $345,949 | $340,990 | CROSS PLUS CONSTRUCTION, LLC | -1.4% | 5 |
| Jun 5, 2019 | 6342-10-001RMC - 634210001 | Jefferson Beaumont |
DW CABLE BARRIER REPAIRIH 10 · | $332,150 | $310,900 | ELITE CASTLE RESOURCES LLC | -6.4% | 1 |
| Jun 5, 2019 | 3417-01-030STP 2019(995)HES | Travis Austin |
INFRASTRUCTURE IMPROVEMENTSFM 734 · | $131,964 | $279,705 | AARON CONCRETE CONTRACTORS, L.P. | +112.0% | 1 |
| Jun 5, 2019 | 2311-01-041STP 1902(016)HES | McLennan Waco |
PROVIDE ADDL PAV WIDTSL 340 · | $201,314 | $243,475 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | +20.9% | 1 |
| Jun 5, 2019 | 0124-03-062STP 1902(047) | Wilbarger Wichita Falls |
LANDSCAPINGUS 183 · | $77,546 | $98,020 | SJ&J CONSTRUCTION, LLC | +26.4% | 1 |
| Jun 5, 2019 | 0222-05-048STP 1902(048)HES | Marion Atlanta |
SAFETY LIGHTING AT INTERSECTIONSH 49 · | $98,582 | $95,254 | TEXAS TRAFFIC CONTROL SYSTEMS, INC. | -3.4% | 5 |
| Jun 4, 2019 | 0016-04-117NH 1902(057) | Comal San Antonio |
FREEWAY OPERATIONAL IMPROVEMENTSIH 35 · | $80,245,982 | $73,245,147 | WEBBER, LLC | -8.7% | 7 |
| Jun 4, 2019 | 0475-01-056STP 1902(024) | Brazos Bryan |
REHABILITATION OF EXISTING ROADSH OSR · | $55,205,435 | $64,767,701 | BIG CREEK CONSTRUCTION, LTD. | +17.3% | 3 |
| Jun 4, 2019 | 0231-03-145NH 2019(651) | Bell Waco |
WDN, BS, STR, SURFUS 190 · | $42,581,073 | $44,733,666 | J.D. ABRAMS, L.P. | +5.1% | 4 |
| Jun 4, 2019 | 0301-07-013STP 1902(060) | Frio San Antonio |
REHAB & WIDEN TO PROVIDE PASS LNS & OP IMPROVEMENTSH 85 · | $30,085,513 | $35,430,891 | ANGEL BROTHERS HOLDINGS CORP. | +17.8% | 3 |
| Jun 4, 2019 | 0366-03-068NH 1902(063) | Guadalupe San Antonio |
REHABILITATE AND WIDEN TO ADD SHOULDERSSH 123 · | $24,136,511 | $24,608,309 | HUNTER INDUSTRIES, LTD. | +2.0% | 6 |
| Jun 4, 2019 | 0016-04-116NH 2019(775) | Comal San Antonio |
GRADE, STR, BASE & SURF, ETC.IH 35 · | $18,176,785 | $19,093,979 | HUNTER INDUSTRIES, LTD. | +5.0% | 3 |
| Jun 4, 2019 | 0317-01-037STP 2019(985) | Fisher Abilene |
WIDEN NON-FREEWAY & REPLACE BRIDGE AND APROACHESFM 57 · | $15,042,021 | $18,577,371 | FNF CONSTRUCTION, INC. | +23.5% | 3 |
| Jun 4, 2019 | 0100-06-065NH 2019(989) | Karnes Corpus Christi |
PAVEMENT REPAIR AND STRUCTURAL OVERLAYUS 181 · | $15,175,932 | $15,738,942 | HUNTER INDUSTRIES, LTD. | +3.7% | 3 |
| Jun 4, 2019 | 0102-07-045STP 1902(052) | Brooks Maintenance Division |
OVERLAYSH 285 · | $9,481,408 | $11,330,611 | FOREMOST PAVING, INC. | +19.5% | 1 |
| Jun 4, 2019 | 0516-02-030C 516-2-30 | Goliad Corpus Christi |
REHAB ROADWAY AND WIDENSH 239 · | $10,428,571 | $11,249,526 | RAY FARIS, INC. | +7.9% | 3 |
| Jun 4, 2019 | 0380-01-092NH 2019(994) | Lubbock Lubbock |
SURFACING ROADWAY / RECONSTRUCTIONUS 62 · | $9,907,151 | $10,343,903 | ALLEN BUTLER CONSTRUCTION, INC. | +4.4% | 3 |
| Jun 4, 2019 | 0262-07-041C 262-7-41 | Milam Bryan |
REHABILITATION OF EXISTING ROADFM 1915 · | $7,683,326 | $8,638,532 | BIG CREEK CONSTRUCTION, LTD. | +12.4% | 2 |
| Jun 4, 2019 | 6340-31-001RMC - 634031001 | Travis Austin |
CONCRETE REPAIR_AND OVERLAYSH 130 · | $6,822,812 | $8,481,875 | ANGEL BROTHERS HOLDINGS CORP. | +24.3% | 4 |
| Jun 4, 2019 | 1682-01-015STP 1902(029)HES | Shelby Lufkin |
HIGHWAY IMPROVEMENTFM 1645 · | $5,795,189 | $5,760,486 | LONGVIEW BRIDGE AND ROAD, LTD. | -0.6% | 6 |
| Jun 4, 2019 | 0171-01-034NH 2019(872) | Jack Fort Worth |
GR, BS, DR, PAVSH 199 · | $4,899,872 | $5,282,832 | JAGOE-PUBLIC COMPANY | +7.8% | 5 |
| Jun 4, 2019 | 1744-02-013STP 1902(027) | Jackson Yoakum |
REHABILITATE EXISTING ROADWAYFM 1862 · | $4,813,356 | $5,207,582 | REXCO CONSTRUCTION SERVICES, INC. | +8.2% | 2 |
| Jun 4, 2019 | 6341-20-001RMC - 634120001 | Dallas Dallas |
GUARD FENCE & CABLE REPAIRSH 78 · | $5,725,798 | $5,134,013 | FIREMAN EXCAVATING, INC. | -10.3% | 3 |
| Jun 4, 2019 | 0353-05-121STP 2019(865)HES | Dallas Dallas |
SIGS, CHEV, BR RAIL, GRDRL, MRKSSL 12 · | $4,252,870 | $4,663,153 | GHB EQUIPMENT COMPANY, L.L.C. | +9.6% | 4 |
| Jun 4, 2019 | 0034-01-137STP 2019(984) | Taylor Abilene |
PLAN, SEAL, SPOT REPAIR OVERLAYUS 83 · | $4,633,807 | $4,451,082 | J. H. STRAIN & SONS, INC. | -3.9% | 3 |
| Jun 4, 2019 | 0845-03-064STP 1902(068)HES | Cooke Wichita Falls |
SAFETY TRT FXD OBJ, ADDL SURF WIDTH, RUMBLE STRIPSFM 922 · | $4,197,267 | $4,439,662 | JAGOE-PUBLIC COMPANY | +5.8% | 2 |
| Jun 4, 2019 | 0095-05-059STP 2019(860)HES | Kaufman Dallas |
INSTALL MEDIAN CABLE AND CONCRETE BARRIERUS 80 · | $3,411,159 | $4,110,940 | ALTUS CONSTRUCTION LLC | +20.5% | 4 |
| Jun 4, 2019 | 0902-00-218NH 2019(876) | Tarrant Fort Worth |
REPLACE GUARDRAILVA · | $5,146,706 | $4,081,763 | SCR CIVIL CONSTRUCTION, LLC | -20.7% | 6 |
| Jun 4, 2019 | 0220-04-055STP 1902(053) | Cameron Pharr |
OVERLAYUS 281 · | $3,019,767 | $3,773,984 | FOREMOST PAVING, INC. | +25.0% | 2 |
| Jun 4, 2019 | 1767-03-018STP 1902(041)HES | Montague Wichita Falls |
SAFETY TRT FXD OBJ, ADDL SURF WIDTH, RUMBLE STRIPSFM 1816 · | $2,940,969 | $3,337,757 | JAGOE-PUBLIC COMPANY | +13.5% | 4 |
| Jun 4, 2019 | 0008-04-050NH 2019(871) | Tarrant Fort Worth |
MILL AND OVERLAYUS 377 · | $1,740,095 | $3,321,023 | PEACHTREE CONSTRUCTION, LTD. | +90.9% | 1 |
| Jun 4, 2019 | 0314-02-052NH 2019(874) | Palo Pinto Fort Worth |
OVERLAYIH 20 · | $2,595,950 | $3,283,419 | JAY MILLS CONTRACTING, INCORPORATED | +26.5% | 3 |
| Jun 4, 2019 | 0027-13-222NH 2019(965) | Harris Houston |
UPGRADE HIGH MAST ILLUMINATIONIH 69 · | $3,752,176 | $3,258,511 | MICA CORPORATION | -13.2% | 7 |
| Jun 4, 2019 | 6338-97-001RMC - 633897001 | Ellis Dallas |
FLEXIBLE PAVEMENT STRUCTURE REPAIRUS 287 · | $2,752,515 | $2,987,208 | BIG CREEK CONSTRUCTION, LTD. | +8.5% | 3 |
| Jun 4, 2019 | 2279-02-019STP 1902(009) | Crockett San Angelo |
REPLACE BRIDGE AND APPROACHESUS 190 · | $2,500,862 | $2,965,511 | STATELINE CONSTRUCTION, LLC | +18.6% | 4 |
| Jun 4, 2019 | 1601-01-034STP 2019(886) | Parker Fort Worth |
OVERLAYFM 730 · | $2,972,678 | $2,799,919 | NORTHEASTERN PAVERS, LLC | -5.8% | 5 |
| Jun 4, 2019 | 0915-00-220STP 1902(062) | Bexar San Antonio |
CONSTRUCT PEDESTRIAN INFRASTRUCTUREVA · | $1,907,006 | $2,393,564 | TI-ZACK CONCRETE, INC. | +25.5% | 3 |
| Jun 4, 2019 | 0715-01-019BR 1902(020) | Gonzales Yoakum |
REPLACE BRIDGE AND APPROACHESFM 108 · | $2,818,930 | $2,235,432 | HILL COUNTRY BRIDGE, INC. | -20.7% | 7 |
1–100 of 128Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.