146Let jobs
$1,090,234,830Total low bids
$1,083,578,873Total estimates
+0.6%Low bids vs estimates
Aug 2018 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 29, 2018 | 6331-45-001RMC - 633145001 | Shelby Lufkin |
DITCH AND CULVERT CLEANINGSH 87 · | $239,500 | $169,450 | TEXAS DRAINAGE INC. | -29.2% | 2 |
| Aug 28, 2018 | 6335-25-001RMC - 633525001 | Angelina Lufkin |
TREE REMOVAL AND TREE AND BRUSH TRIMMINGUS 59 · | $279,500 | $247,536 | C.E.S. CONTRACTOR | -11.4% | 6 |
| Aug 28, 2018 | 6330-31-001RMC - 633031001 | Trinity Lufkin |
TREE REMOVAL AND TREE AND BRUSH TRIMMINGFM 357 · | $187,500 | $138,490 | FLORES TREE SERVICE LLC | -26.1% | 8 |
| Aug 23, 2018 | 6334-18-001RMC - 633418001 | Hudspeth El Paso |
CRACK SEALINGIH 10 · | $207,600 | $148,110 | D & M CONTRACTORS, LLC | -28.7% | 2 |
| Aug 23, 2018 | 6334-19-001RMC - 633419001 | El Paso El Paso |
CRACK SEALINGIH 10 · | $167,825 | $135,010 | D & M CONTRACTORS, LLC | -19.6% | 3 |
| Aug 23, 2018 | 6327-23-001RMC - 632723001 | De Witt Yoakum |
DISTRICT OFFICE COMPLEX JANITORIAL SERVICESBU 77Q · | $43,730 | $42,981 | ACE GLOBAL | -1.7% | 2 |
| Aug 22, 2018 | 6331-46-001RMC - 633146001 | Houston Lufkin |
HIGH EDGE REMOVALUS 287 · | $181,750 | $151,106 | L & M MOWING CONTRACTORS, LLC | -16.9% | 4 |
| Aug 22, 2018 | 6333-52-001RMC - 633352001 | Wichita Wichita Falls |
BRIDGE RAIL REPAIRUS 287 · | $91,810 | $92,400 | DRS CONSTRUCTION, INC. | +0.6% | 6 |
| Aug 16, 2018 | 6332-92-001RMC - 633292001 | Hunt Paris |
CRACK SEALUS 69 · | $190,184 | $141,766 | JOHN & DENISE WILLIAMS CONSTRUCTION COMPANY LLC | -25.5% | 8 |
| Aug 14, 2018 | 6331-34-001RMC - 633134001 | Brazoria Houston |
REPAIR OF FLEXIBLE PAVEMENTSH 288 · | $263,050 | $236,830 | MAIN LANE INDUSTRIES LTD. | -10.0% | 3 |
| Aug 14, 2018 | 6334-10-001RMC - 633410001 | Crane Odessa |
ROADSIDE MOWINGUS 385 · | $161,472 | $154,744 | ABESCAPE GROUP LLC | -4.2% | 4 |
| Aug 14, 2018 | 6327-49-001RMC - 632749001 | Kaufman Dallas |
TREE TRIMMING & BRUSH REMOVALIH 20 · | $189,104 | $134,550 | AZA CONSTRUCTION INC | -28.8% | 9 |
| Aug 14, 2018 | 6333-21-001RMC - 633321001 | Midland Odessa |
CLEANING AND SEALING JOINTS AND CRACKSSH 158 · | $241,557 | $116,235 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | -51.9% | 3 |
| Aug 14, 2018 | 6334-05-001RMC - 633405001 | Ector Odessa |
CLEANING AND SEALING CRACKSSH 158 · | $227,501 | $92,955 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | -59.1% | 3 |
| Aug 9, 2018 | 6332-93-001RMC - 633293001 | Hidalgo Pharr |
ON CALL PAVEMENT MARKINGS AND PAVEMENT MIH 2 · | $292,883 | $285,928 | PAVEMENT MARKINGS INC. | -2.4% | 2 |
| Aug 8, 2018 | 0271-02-055NH 1802(497) | Austin Yoakum |
PVT,GRDING,STRS,BASE,SIGNING,ITSIH 10 · | $303,003,725 | $317,508,659 | WEBBER, LLC | +4.8% | 5 |
| Aug 8, 2018 | 0158-02-084NH 1802(735) | Tom Green San Angelo |
CONSTRUCT INTERCHANGESUS 67 · | $36,118,504 | $37,993,285 | REECE ALBERT, INC. | +5.2% | 2 |
| Aug 8, 2018 | 0034-01-126NH 1802(506) | Taylor Abilene |
EMB, FL BS, STRS, AND ACPUS 83 · | $32,078,115 | $27,993,542 | ALLEN BUTLER CONSTRUCTION, INC. | -12.7% | 7 |
| Aug 8, 2018 | 0517-01-043STP 1802(616) | Atascosa San Antonio |
REHAB & WIDEN TO PROVIDE OPERATIONAL IMPRVMNTSSH 16 · | $21,116,426 | $22,041,915 | ANGEL BROTHERS HOLDINGS CORP. | +4.4% | 4 |
| Aug 8, 2018 | 0270-03-075STP 1802(559) | Karnes Corpus Christi |
REHABILITATE ROADWAY AND ADD PASSING LANESSH 72 · | $19,433,999 | $18,309,294 | HUNTER INDUSTRIES, LTD. | -5.8% | 4 |
| Aug 8, 2018 | 2230-01-013STP 1802(618) | Bexar San Antonio |
GRAD, STR, BASE, SURFFM 1560 · | $16,562,969 | $17,810,211 | DAN WILLIAMS COMPANY | +7.5% | 8 |
| Aug 8, 2018 | 0191-01-063NH 2013(216) | Smith Tyler |
GR,STRS,ACP BS&SURF,MBGF,SIGNALS,PV MKUS 69 · | $16,519,021 | $16,738,120 | LONGVIEW BRIDGE AND ROAD, LTD. | +1.3% | 4 |
| Aug 8, 2018 | 0237-07-015STP 2018(946) | Dimmit Laredo |
BASE,ACP,GRAD,STR,PAV MRKFM 133 · | $18,004,309 | $16,183,209 | ANGEL BROTHERS HOLDINGS CORP. | -10.1% | 4 |
| Aug 8, 2018 | 0101-03-088STP 1802(556)HES | San Patricio Corpus Christi |
CONSTRUCT GRADE SEPARATIONUS 181 · | $13,898,551 | $15,437,893 | HAAS-ANDERSON CONSTRUCTION, LTD. | +11.1% | 4 |
| Aug 8, 2018 | 0327-10-062NH 1802(561) | Willacy Pharr |
CONSTRUCT MAINLANES & OVERPASSESUS 77 · | $14,830,225 | $15,409,268 | FOREMOST PAVING, INC. | +3.9% | 3 |
| Aug 8, 2018 | 0380-07-026NH 1802(582) | Martin Odessa |
ARMORING WITH OVERLAYSH 349 · | $17,598,197 | $15,052,677 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | -14.5% | 4 |
| Aug 8, 2018 | 0116-01-039C 116-1-39 | Lee Austin |
LEVEL-UP, FULL DEPTH REPAIR & TOMSH 21 · | $11,614,965 | $12,787,554 | BIG CREEK CONSTRUCTION, LTD. | +10.1% | 7 |
| Aug 8, 2018 | 0270-10-013BR 1802(496) | De Witt Yoakum |
REPLACE BRIDGE AND APPROACHESSH 72 · | $15,099,265 | $12,717,082 | SB CONTRACTORS LLC | -15.8% | 3 |
| Aug 8, 2018 | 3621-01-014STP 1802(541) | Val Verde Laredo |
BASE,GRADE,ACP,PAVMRK,ILLUMINATIONSL 79 · | $14,331,589 | $11,318,353 | HUNTER INDUSTRIES, LTD. | -21.0% | 4 |
| Aug 8, 2018 | 2121-03-160STP 1802(574)MM | El Paso El Paso |
RAMP AND INTERSECTION IMPROVEMENTSIH 10 · | $9,183,649 | $9,358,403 | J.D. ABRAMS, L.P. | +1.9% | 4 |
| Aug 8, 2018 | 3158-01-032STP 1802(609) | Montgomery Houston |
WIDEN TO 4-LANE DIVIDED URBANFM 3083 · | $8,363,456 | $9,047,341 | SMITH & COMPANY | +8.2% | 3 |
| Aug 8, 2018 | 0765-02-021C 765-2-21 | Fannin Paris |
REHABILITATION OF EXISTING ROADFM 1753 · | $10,731,067 | $8,647,080 | D. L. LENNON INCORPORATED - CONTRACTOR | -19.4% | 4 |
| Aug 8, 2018 | 0666-01-027STP 1802(492) | Grayson Paris |
WIDEN NON-FREEWAYFM 691 · | $7,755,455 | $8,294,048 | JAGOE-PUBLIC COMPANY | +6.9% | 4 |
| Aug 8, 2018 | 0002-07-049BR 1802(572) | Hudspeth El Paso |
REPLACE BRIDGES AND APPROACHESIH 10 · | $5,721,389 | $7,766,379 | DAN WILLIAMS COMPANY | +35.7% | 1 |
| Aug 8, 2018 | 0592-02-015STP 1802(562)HES | Rusk Tyler |
PL,BS,SURF TRT,ACP,STRS,MBGF,SIGNS,PV MKFM 840 · | $8,332,689 | $7,676,967 | PINTO CONSTRUCTION CO., INC. | -7.9% | 7 |
| Aug 8, 2018 | 0264-04-052C 264-4-52 | Coke San Angelo |
RESTORATION OF EXISTING ROADUS 277 · | $6,066,480 | $7,015,129 | REECE ALBERT, INC. | +15.6% | 2 |
| Aug 8, 2018 | 0153-02-040NH 1802(495) | Gonzales Yoakum |
PAVEMENT REPAIR AND RESURFACING; MILLED R. STRIPSUS 183 · | $7,207,873 | $6,756,349 | HUNTER INDUSTRIES, LTD. | -6.3% | 5 |
| Aug 8, 2018 | 1349-03-013C 1349-3-13 | Burnet Austin |
PROVIDE ADDITIONAL PAVED SURFACERM 1174 · | $5,695,841 | $6,179,469 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | +8.5% | 6 |
| Aug 8, 2018 | 0681-04-041STP 1802(253)HES | Wichita Wichita Falls |
SAFETY TREAT FIXED OBBJECTS, PROVIDE ADDL WIDTHFM 367 · | $4,269,955 | $5,646,362 | A. L. HELMCAMP, INC. | +32.2% | 3 |
| Aug 8, 2018 | 0083-03-055C 83-3-55 | Hopkins Paris |
OVERLAYSH 154 · | $5,571,893 | $5,289,098 | RK HALL, LLC | -5.1% | 4 |
| Aug 8, 2018 | 0135-03-050STP 1802(749)HES | Collin Dallas |
INSTALL RAISED MEDIANUS 380 · | $5,352,580 | $5,260,480 | ALTUS CONSTRUCTION LLC | -1.7% | 7 |
| Aug 8, 2018 | 1503-02-011STP 1802(505)HES | Howard Abilene |
PAVEMENT WIDENINGFM 1584 · | $3,142,591 | $3,443,262 | DELHUR INDUSTRIES, INC. | +9.6% | 6 |
| Aug 8, 2018 | 0523-08-014C 523-8-14 | Montgomery Houston |
BASE REPAIR, OCST, LEVEL UP, OVFM 1488 · | $3,876,245 | $3,164,973 | ANGEL BROTHERS HOLDINGS CORP. | -18.3% | 6 |
| Aug 8, 2018 | 3417-01-029C 3417-1-29 | Travis Austin |
PAVEMENT REPAIR, UNDERSEAL & OVERLAYFM 734 · | $2,741,778 | $2,822,373 | AUSTIN MATERIALS, LLC | +2.9% | 6 |
| Aug 8, 2018 | 6334-99-001RMC - 633499001 | Knox Childress |
REMOVAL AND CONSTRUCTION OF SRA FOR KNOXUS 82 · | $1,585,111 | $2,450,000 | DCI CONTRACTING, INC. | +54.6% | 1 |
| Aug 8, 2018 | 0146-01-051BR 1802(481) | Motley Childress |
REPLACEMENT OF EXISTING BRIDGE FACILITYUS 62 · | $2,189,851 | $2,119,656 | HODGES AND SON CONSTRUCTION COMPANY, INC. | -3.2% | 5 |
| Aug 8, 2018 | 6330-46-001RMC - 633046001 | Dallas Dallas |
SWEEPING & DEBRIS REMOVALSH 78 · | $2,674,985 | $2,006,001 | BAYOU DRAGON TRANSPORT LLC | -25.0% | 3 |
| Aug 8, 2018 | 0902-00-213C 902-00-213 | Tarrant Fort Worth |
CONCRETE PAVEMENT REPAIRVA · | $1,705,070 | $1,777,800 | O. TREVINO CONSTRUCTION, LLC | +4.3% | 5 |
| Aug 8, 2018 | 6329-77-001RMC - 632977001 | Dallas Dallas |
SWEEPING & DEBRIS REMOVALUS 67 · | $2,071,107 | $1,553,475 | BAYOU DRAGON TRANSPORT LLC | -25.0% | 4 |
| Aug 8, 2018 | 0912-73-195BR 1502(357) | Galveston Houston |
REPLACE BRIDGE AND APPROACHESCR · | $1,519,233 | $1,514,087 | JOHN REED AND COMPANY, LLC | -0.3% | 2 |
| Aug 8, 2018 | 6333-83-001RMC - 633383001 | Gonzales Yoakum |
ON CALL LUMINAIRE/TRAFFIC SIGNAL/GUIDE SIGN REPAIRIH 10 · | $860,929 | $1,221,521 | THIRD COAST SERVICES LLC | +41.9% | 1 |
| Aug 8, 2018 | 0015-17-028STP 1802(542)HES | Williamson Austin |
IMPROVE GUARDRAIL TO DESIGN STANDARDSSS 158 · | $951,493 | $1,181,685 | CHAMPION INFRASTRUCTURE, LLC | +24.2% | 3 |
| Aug 8, 2018 | 0050-06-090NH 1802(600) | Harris Houston |
LANDSCAPE ENHANCEMENTSUS 290 · | $1,393,781 | $1,140,000 | APEX LANDSCAPE & IRRIGATION, LLC | -18.2% | 6 |
| Aug 8, 2018 | 0322-01-049C 322-1-49 | Bastrop Austin |
MILL, SEAL & TOM OVERLAYSH 95 · | $1,206,218 | $1,130,212 | LONE STAR PAVING COMPANY | -6.3% | 5 |
| Aug 8, 2018 | 0901-29-082BR 1402(211) | Lamar Paris |
BRIDGE REPLACEMENTCR · | $1,053,658 | $1,097,244 | STATELINE CONSTRUCTION, LLC | +4.1% | 7 |
| Aug 8, 2018 | 1939-01-059STP 1802(567)HES | Hidalgo Pharr |
INSTALL TRAFFIC SIGNALSFM 2061 · | $1,113,892 | $1,064,871 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | -4.4% | 3 |
| Aug 8, 2018 | 0049-01-094STP 1802(508)HES | McLennan Waco |
IMPROVE TRAFFIC SIGNALSSH 6 · | $970,438 | $1,026,074 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | +5.7% | 3 |
| Aug 8, 2018 | 0017-01-024STP 1802(612)HES | Bexar San Antonio |
PROFILE EDGELINE/CENTERLINE MARKINGS, ETC.SL 353 · | $2,419,475 | $1,022,882 | INTERSTATE BARRICADES & MARKINGS, INC. | -57.7% | 5 |
| Aug 8, 2018 | 0902-00-209STP 1802(554) | Tarrant Fort Worth |
BRIDGE MAINTENANCEVA · | $918,561 | $984,722 | GIBSON & ASSOCIATES, INC. | +7.2% | 3 |
| Aug 8, 2018 | 6332-47-001RMC - 633247001 | Brazos Bryan |
METAL BEAM GUARD FENCE REPAIRSH 6 · | $724,355 | $747,333 | T&L CLEANING SERVICES LLC | +3.2% | 3 |
| Aug 8, 2018 | 6332-59-001RMC - 633259001 | Hidalgo Pharr |
FM MOWINGFM 490 · | $568,764 | $726,084 | R&M INCORPORATED | +27.7% | 2 |
| Aug 8, 2018 | 0271-16-144NH 1802(607) | Harris Houston |
LANDSCAPE ENHANCEMENTSIH 610 · | $495,517 | $614,672 | CHAMPION INFRASTRUCTURE, LLC | +24.0% | 3 |
| Aug 8, 2018 | 0920-03-034BR 93(356) | Hardin Beaumont |
REPLACE BRIDGECR · | $710,136 | $586,642 | STATELINE CONSTRUCTION, LLC | -17.4% | 4 |
| Aug 8, 2018 | 0138-06-045STP 1802(576)HES | Nacogdoches Lufkin |
SAFETY LIGHTINGUS 259 · | $637,755 | $574,813 | VACA UNDERGROUND UTILITIES INC | -9.9% | 5 |
| Aug 8, 2018 | 0271-14-236NH 1802(605) | Harris Houston |
LANDSCAPE ENHANCEMENTSIH 610 · | $572,928 | $566,853 | CROSBY RD CONSTRUCTION INC | -1.1% | 5 |
| Aug 8, 2018 | 0902-20-099BR 2009(900) | Wise Fort Worth |
REPLACE BRIDGE AND APPROACHESCR · | $635,829 | $529,964 | HODGES AND SON CONSTRUCTION COMPANY, INC. | -16.7% | 7 |
| Aug 8, 2018 | 0005-01-109STP 1802(579)HES | Ector Odessa |
FLASHING BEACONS, WARNING SIGNAL & SIGNSBI 20-E · | $482,111 | $518,770 | WILLIS ELECTRIC CO., LP | +7.6% | 1 |
| Aug 8, 2018 | 6334-78-001RMC - 633478001 | Swisher Lubbock |
MOWINGIH 27 · | $386,080 | $451,571 | CROSS PLUS CONSTRUCTION, LLC | +17.0% | 3 |
| Aug 8, 2018 | 6331-14-001RMC - 633114001 | Parker Fort Worth |
TREE TRIMMING AND BRUSH AND TREE REMOVALIH 20 · | $445,148 | $440,095 | C.E.S. CONTRACTOR | -1.1% | 5 |
| Aug 8, 2018 | 6327-17-001RMC - 632717001 | Travis Austin |
SLOPE REPAIRSH 45 · | $439,302 | $423,495 | RELMCO, INC. | -3.6% | 5 |
| Aug 8, 2018 | 2293-01-030C 2293-1-030 | Hays Austin |
TOM OVERLAYFM 2439 · | $524,410 | $409,850 | LONE STAR PAVING COMPANY | -21.8% | 7 |
| Aug 8, 2018 | 0049-09-079STP 1802(486)HESG | Brazos Bryan |
INSTALL TRAFFIC SIGNALUS 190 · | $421,116 | $388,060 | BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. | -7.8% | 4 |
| Aug 8, 2018 | 0002-01-095STP 1802(571) | El Paso El Paso |
PEDESTRIAN IMPROVEMENTSSH 20 · | $383,320 | $349,909 | MARIL ENTERPRISES LLC | -8.7% | 6 |
| Aug 8, 2018 | 6330-43-001RMC - 633043001 | Harris Houston |
STORM SEWER SYSTEM CLEANINGIH 10 · | $329,107 | $344,188 | AIMS COMPANIES | +4.6% | 1 |
| Aug 8, 2018 | 0110-05-128BR 1802(417) | Harris Houston |
REPLACE/RESET BEARING PADSIH 45 · | $354,229 | $309,370 | CHAMPION INFRASTRUCTURE, LLC | -12.7% | 4 |
| Aug 8, 2018 | 0909-38-078BR 2017(203) | Falls Waco |
REPL BR & APPRSCS · | $249,884 | $279,404 | KNIFE RIVER CORPORATION - SOUTH | +11.8% | 7 |
| Aug 8, 2018 | 6333-01-001RMC - 633301001 | Lamar Paris |
CRACK SEALUS 82 · | $326,530 | $219,140 | D & M CONTRACTORS, LLC | -32.9% | 3 |
| Aug 8, 2018 | 0080-07-097C 80-7-97 | Tarrant Fort Worth |
INSTALLATION OF TRAFFIC SIGNALUS 377 · | $178,842 | $188,385 | NEW WORLD CONTRACTING, LLC | +5.3% | 4 |
| Aug 8, 2018 | 0145-01-031STP 1802(533)HES | Bailey Lubbock |
TREE REMOVAL IN CLEAR ZONEUS 70 · | $248,400 | $125,595 | SPARTAN DIRECT SOLUTIONS LLC | -49.4% | 6 |
| Aug 7, 2018 | 0080-11-001NH 1802(546) | Hood Fort Worth |
GR, DR, STR, BS AND PAVEMENTUS 377 · | $55,348,715 | $60,713,830 | ZACHRY CONSTRUCTION CORPORATION | +9.7% | 9 |
| Aug 7, 2018 | 0718-02-045STP 1802(552)MM | Tarrant Fort Worth |
GRADING, STRUCTURES, PAVEMENT & STRFM 156 · | $51,717,780 | $48,586,586 | WEBBER, LLC | -6.1% | 9 |
| Aug 7, 2018 | 0101-04-097NH 1702(490) | San Patricio Corpus Christi |
GRAD,STRS,BASE & SURFACINGUS 181 · | $39,815,128 | $43,149,146 | BAY LTD. | +8.4% | 3 |
| Aug 7, 2018 | 0016-03-103NH 1802(535) | Hays Austin |
REPLACE BRIDGE & APPROACHESIH 35 · | $33,976,081 | $31,736,977 | WEBBER, LLC | -6.6% | 6 |
| Aug 7, 2018 | 0433-02-052C 433-2-52 | Willacy Pharr |
REHABILITATE ROADWAY (SUPER 2)SH 186 · | $22,069,391 | $20,899,928 | ASAGO, LLC | -5.3% | 3 |
| Aug 7, 2018 | 0493-02-015STP 2018(931) | Loving |
ROADWAY RESTORATIONRM 652 · | $17,560,799 | $19,243,862 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY | +9.6% | 4 |
| Aug 7, 2018 | 0177-14-010STP 1802(602) | Montgomery Houston |
RECONSTRUCT AND WIDEN TO A 4 LANESL 494 · | $14,791,057 | $14,347,429 | ISI CONTRACTING, INC. | -3.0% | 9 |
| Aug 7, 2018 | 0484-01-023STP 1802(504)HES | Jones Abilene |
WIDEN ROADWAYFM 707 · | $15,249,965 | $13,833,694 | J. H. STRAIN & SONS, INC. | -9.3% | 3 |
| Aug 7, 2018 | 1046-01-030NH 1802(573) | El Paso El Paso |
OPERATIONAL IMPROVEMENTSFM 659 · | $10,688,776 | $12,904,066 | LESNA CONSTRUCTION, INC. | +20.7% | 4 |
| Aug 7, 2018 | 0301-04-020C 301-4-20 | Dimmit Laredo |
BASE, ACP, GRAD, STR, PAV MRKFM 186 · | $13,823,743 | $12,607,041 | J. CARROLL WEAVER, INC. | -8.8% | 5 |
| Aug 7, 2018 | 1566-02-019C 1566-2-19 | Williamson Austin |
REHAB RDWYFM 1660 · | $8,857,967 | $8,947,810 | JORDAN FOSTER CONSTRUCTION, LLC | +1.0% | 7 |
| Aug 7, 2018 | 0252-02-054NH 1802(537) | Burnet Austin |
ADD CENTER LEFT TURN LANE AND SHOULDERSUS 281 · | $7,417,179 | $7,365,015 | JORDAN FOSTER CONSTRUCTION, LLC | -0.7% | 4 |
| Aug 7, 2018 | 0089-06-090C 89-6-90 | Wharton Yoakum |
ACP OVERLAYUS 59 · | $7,505,321 | $7,009,734 | JAMES CONSTRUCTION GROUP, L.L.C. | -6.6% | 4 |
| Aug 7, 2018 | 0068-08-065BR 1802(503) | Howard Abilene |
BRIDGE REHABUS 87 · | $6,834,229 | $6,661,051 | DCI CONTRACTING, INC. | -2.5% | 4 |
| Aug 7, 2018 | 6327-47-001RMC - 632747001 | Denton Dallas |
GUARDRAIL REPAIRIH 35W · | $3,089,735 | $5,738,770 | K-BAR SERVICES, INC. | +85.7% | 2 |
| Aug 7, 2018 | 0286-03-017C 286-3-17 | Caldwell Austin |
LEVEL-UP, FULL DEPTH REPAIR AND TOMSH 80 · | $5,590,086 | $5,221,959 | ANGEL BROTHERS HOLDINGS CORP. | -6.6% | 6 |
| Aug 7, 2018 | 0212-03-062STP 1802(487) | Brazos Bryan |
MILL AND INLAYFM 158 · | $4,929,740 | $4,710,744 | ANGEL BROTHERS HOLDINGS CORP. | -4.4% | 3 |
| Aug 7, 2018 | 0112-03-035STP 1802(536)HES | Gillespie Austin |
UPGRADE GUARDRAILUS 290 · | $4,245,876 | $4,681,678 | ALLEN KELLER COMPANY | +10.3% | 5 |
| Aug 7, 2018 | 0912-73-204BR 1702(557) | Galveston Houston |
REHABILITATE BRIDGECR · | $3,598,660 | $4,488,672 | TEXAS GULF CONSTRUCTION COMPANY, INC. | +24.7% | 2 |
| Aug 7, 2018 | 0113-13-175C 113-13-175 | Travis Austin |
MILL & INLAYSH 71 · | $4,521,576 | $3,958,942 | LONE STAR PAVING COMPANY | -12.4% | 6 |
| Aug 7, 2018 | 0140-11-045C 140-11-45 | Crockett San Angelo |
RELOCATE EXIT RAMP, BUILD FRONTAGE ROAD AND BRIDGEIH 10 · | $3,674,637 | $3,784,610 | ALLEN KELLER COMPANY | +3.0% | 2 |
1–100 of 146Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.