51BidsMay 6, 2026 to Nov 18, 2026
30Wins (low bidder)
58.8%Win rate
$89,548,911Total won
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Nov 18, 2026 | 6511-07-001 | FY27 - Leon HMA - 11Leon · Bryan | 1 of 3 | $283,600 | $283,600 | Won |
| Nov 18, 2026 | 6511-08-001 | FY27 - Madison HMA - 11Madison · Bryan | 2 of 3 | $271,300 | $270,750KNIFE RIVER CORPORATION - S… | +0.2% |
| Nov 17, 2026 | 6511-06-001 | FY27 - Freestone HMA - 11Freestone · Bryan | 1 of 3 | $444,000 | $444,000 | Won |
| Nov 4, 2026 | 0923-06-068 | PW within Lake Brownwood SPBrown · Brownwood | 4 of 6 | $1,774,687 | $1,561,729JAY MILLS CONTRACTING, INCO… | +13.6% |
| Nov 4, 2026 | 0212-03-058 | SH 30 NAVASOTA RIVER RELIEF #1 - BRBrazos · Bryan | 2 of 12 | $33,187,594 | $30,209,876FLUOR ENTERPRISES, INC. | +9.9% |
| Nov 4, 2026 | 0262-01-034 | FM 485 - W and E of FM 979 - FY 27Milam · Bryan | 1 of 7 | $9,787,627 | $9,787,627 | Won |
| Nov 4, 2026 | 6502-80-001 | Flexible Pvmt. Structure Repair 09 1026Ellis · Dallas | 3 of 7 | $1,359,695 | $1,246,988AUSTIN BRIDGE & ROAD SERVIC… | +9.0% |
| Nov 4, 2026 | 6510-36-001 | HILLSBORO AO - FY27 BASE FAILURE REPAIRHill · Waco | 1 of 3 | $1,603,275 | $1,603,275 | Won |
| Nov 4, 2026 | 6510-39-001 | BELL - FY27 BASE FAILURE REPAIRBell · Waco | 2 of 3 | $1,769,425 | $1,470,225TEXAS MATERIALS GROUP, INC. | +20.4% |
| Nov 3, 2026 | 6510-37-001 | MCLENNAN - FY27 BASE FAILURE REPAIRMcLennan · Waco | 2 of 4 | $2,221,050 | $2,172,910TEXAS MATERIALS GROUP, INC. | +2.2% |
| Nov 3, 2026 | 6510-38-001 | GATESVILLE AO - FY27 BASE FAILURE REPAIRCoryell · Waco | 1 of 4 | $1,146,275 | $1,146,275 | Won |
| Oct 22, 2026 | 6510-97-001 | HMA COMANCHE 2026Comanche · Brownwood | 1 of 3 | $410,000 | $410,000 | Won |
| Oct 7, 2026 | 0014-23-041 | RER | IH 35W | IH 35E | Johnson CL SBHill · Waco | 3 of 5 | $11,361,815 | $10,903,496NORTHEASTERN PAVERS, LLC | +4.2% |
| Oct 6, 2026 | 2502-01-024 | WNF | IH 14 | IH 35Bell · Waco | 1 of 6 | $22,052,184 | $22,052,184 | Won |
| Aug 12, 2026 | 6496-74-001 | Flexible Pavement Str Repair 0826Navarro · Dallas | 2 of 4 | $978,709 | $955,633TEXAS MATERIALS GROUP, INC. | +2.4% |
| Aug 11, 2026 | 6505-00-001 | FY26 Walker HMA - 08Walker · Bryan | 1 of 3 | $636,380 | $636,380 | Won |
| Aug 6, 2026 | 0114-10-102 | US 290WB F: FM 1155 T: Waller CL -RER 26Washington · Bryan | 1 of 6 | $4,287,440 | $4,287,440 | Won |
| Aug 6, 2026 | 6503-26-001 | FY27 - Bryan AO Mill & Inlay - 08Brazos · Bryan | 1 of 4 | $987,331 | $987,331 | Won |
| Aug 5, 2026 | 0173-04-059 | SH 34 IH 20 EB to N of SH 243Kaufman · Dallas | 1 of 7 | $6,242,701 | $6,242,701 | Won |
| Aug 5, 2026 | 6505-22-001 | OVERLAY EASTLAND COUNTYEastland · Brownwood | 7 of 9 | $3,419,570 | $2,982,235BLACKSMITH VENTURES LLC | +14.7% |
| Aug 5, 2026 | 0186-03-071 | SH 36 F: S of SH 21 T: CR 122 -IOI FY 26Burleson · Bryan | 1 of 6 | $4,987,865 | $4,987,865 | Won |
| Aug 5, 2026 | 0150-02-043 | SH 29 from SH 71 to Zula Rd.Llano · Austin | 1 of 6 | $2,462,865 | $2,462,865 | Won |
| Jul 15, 2026 | 6505-27-001 | HOT-MIX (MAT ONLY) SAN SABA COUNTYSan Saba · Brownwood | 1 of 4 | $178,980 | $178,980 | Won |
| Jul 14, 2026 | 6503-82-001 | FY26 Milam HMA - 07Milam · Bryan | 2 of 3 | $399,000 | $372,300LONE STAR PAVING COMPANY | +7.2% |
| Jul 2, 2026 | 0492-04-034 | FM756,CR1167-FM346,WDNSmith · Tyler | 9 of 9 | $75,487,342 | $58,705,654BAKER & COMPANY CONSTRUCTIO… | +28.6% |
| Jul 2, 2026 | 0625-01-001 | Rehab EX RD | FT PARKER STATE PARK |Limestone · Waco | 1 of 6 | $1,849,328 | $1,849,328 | Won |
| Jul 2, 2026 | 6498-12-001 | Hot Mix - Hill and BosqueHill · Waco | 1 of 3 | $1,864,225 | $1,864,225 | Won |
| Jul 2, 2026 | 6498-13-001 | Hot Mix - McLennan and LimestoneMcLennan · Waco | 1 of 3 | $1,955,438 | $1,955,438 | Won |
| Jul 2, 2026 | 6503-27-001 | FY26 - Huntsville AO Mill & Inlay - 07Walker · Bryan | 1 of 4 | $1,433,238 | $1,433,238 | Won |
| Jul 1, 2026 | 3110-01-003 | FM3016_FROM FM 228 TO CR 1685Houston · Lufkin | 3 of 5 | $3,925,688 | $3,814,102L. S. EQUIPMENT CO., INC. | +2.9% |
| Jul 1, 2026 | 0199-01-090 | US 69 - SUPERELEVATIONCherokee · Tyler | 2 of 3 | $1,234,087 | $1,093,712REYNOLDS & KAY, LTD. | +12.8% |
| Jul 1, 2026 | 0540-03-039 | FM 974 F: FM 2776 T: south - FY 27Brazos · Bryan | 1 of 8 | $3,771,592 | $3,771,592 | Won |
| Jul 1, 2026 | 6498-75-001 | Hot Mix - Bell and FallsBell · Waco | 2 of 4 | $1,369,220 | $1,302,581TEXAS MATERIALS GROUP, INC. | +5.1% |
| Jul 1, 2026 | 6498-77-001 | Hot Mix - Coryell and HamiltonCoryell · Waco | 1 of 4 | $1,194,788 | $1,194,788 | Won |
| Jul 1, 2026 | 6503-24-001 | FY27 - Brenham AO Mill & Inlay - 07Washington · Bryan | 2 of 5 | $1,135,210 | $1,091,717BRAZOS PAVING, INC. | +4.0% |
| Jun 10, 2026 | 6500-04-001 | Hot Mix Material 09 0426Ellis · Dallas | 1 of 2 | $550,000 | $550,000 | Won |
| Jun 10, 2026 | 6502-36-001 | FY26 Robertson Hot Mix - 06Robertson · Bryan | 1 of 5 | $330,664 | $330,664 | Won |
| Jun 9, 2026 | 6502-35-001 | FY26 Burleson Hot Mix - 06Burleson · Bryan | 1 of 5 | $212,600 | $212,600 | Won |
| Jun 3, 2026 | 0937-01-027 | FM 227_FROM FM 2544 TO 3.3 MI EASTHouston · Lufkin | 2 of 9 | $4,876,249 | $4,462,648PINTO CONSTRUCTION CO., INC. | +9.3% |
| Jun 2, 2026 | 0274-02-032 | US 183 MILLS C/L TO LOMETALampasas · Brownwood | 1 of 9 | $4,510,688 | $4,510,688 | Won |
| Jun 2, 2026 | 0315-03-070 | SH 90 at FM 244 - Turn Lane FY 26Grimes · Bryan | 3 of 7 | $1,279,779 | $1,241,183LARRY YOUNG PAVING, INC. | +3.1% |
| Jun 2, 2026 | 0190-05-078 | US 69, N of IH 20 & S of IH 20 FRTGSmith · Tyler | 4 of 5 | $2,698,880 | $2,362,671ICOS MANAGEMENT, LLC | +14.2% |
| Jun 2, 2026 | 6500-39-001 | MILL & INLAY SOUTH FY 27Henderson · Tyler | 1 of 5 | $977,218 | $977,218 | Won |
| Jun 2, 2026 | 6500-40-001 | SMITH COUNTY SMA FY 27Smith · Tyler | 4 of 6 | $5,649,110 | $5,091,894TEXAS MATERIALS GROUP, INC. | +10.9% |
| May 7, 2026 | 6488-81-001 | FY26 - Calvert Mill & InlayRobertson · Bryan | 2 of 5 | $2,287,353 | $2,266,508LONE STAR PAVING COMPANY | +0.9% |
| May 7, 2026 | 0110-01-052 | SH 75 at FM 2296 - FY 25Walker · Bryan | 1 of 5 | $2,980,129 | $2,980,129 | Won |
| May 6, 2026 | 6500-76-001 | MMC HMA Rusk CountyRusk · Tyler | 1 of 2 | $2,302,000 | $2,302,000 | Won |
| May 6, 2026 | 6500-78-001 | MMC HMA Henderson CoHenderson · Tyler | 1 of 2 | $1,561,000 | $1,561,000 | Won |
| May 6, 2026 | 1186-02-028 | FM 969 from Utley Rd to Howard LnBastrop · Austin | 2 of 8 | $3,287,461 | $3,189,429HUNTER INDUSTRIES, LTD. | +3.1% |
| May 6, 2026 | 0209-01-076 | OV | US 77 | FM 3148 | LP 340McLennan · Waco | 1 of 4 | $5,957,588 | $5,957,588 | Won |
| May 6, 2026 | 1410-01-026 | FM 1456 REHABILITATE ROADWAY HSIP 2605Austin · Yoakum | 1 of 8 | $2,587,895 | $2,587,895 | Won |
Subcontracts on active jobs 0