509BidsNov 3, 2016 to Nov 17, 2026
140Wins (low bidder)
27.5%Win rate
$507,601,279Total won
Competitor scorecard
Last 5 years in Texas28.4%Win rate74 of 261 bids
+5.5%Average bid vs estimate
-9.1%Winning bids vs estimate
+18.4%Over the low bid when they loseAverage field: 4.4 bidders
| Head to head | Times met | Beat them | Lost to them | Record |
|---|---|---|---|---|
| TEXAS MATERIALS GROUP, INC. | 232 | 119 | 113 | 51% |
| HUNTER INDUSTRIES, LTD. | 138 | 91 | 47 | 66% |
| CLARK CONSTRUCTION OF TEXAS, INC. | 87 | 46 | 41 | 53% |
| BIG CREEK CONSTRUCTION, LTD. | 51 | 22 | 29 | 43% |
| COLORADO MATERIALS, LTD. | 45 | 14 | 31 | 31% |
| BRAUNTEX MATERIALS, INC. | 42 | 5 | 37 | 12% |
| ALLEN KELLER COMPANY | 38 | 25 | 13 | 66% |
| DEAN WORD COMPANY, LTD. | 33 | 19 | 14 | 58% |
| KNIFE RIVER CORPORATION - SOUTH | 27 | 18 | 9 | 67% |
| CK NEWBERRY, LLC | 26 | 20 | 6 | 77% |
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Nov 17, 2026 | 6506-95-001 | FY 2027 HOTMIX COLD-LAID-MATERIAL ONLYBell · Waco | 1 of 3 | $467,875 | $467,875 | Won |
| Nov 4, 2026 | 0923-06-068 | PW within Lake Brownwood SPBrown · Brownwood | 2 of 6 | $1,683,823 | $1,561,729JAY MILLS CONTRACTING, INCO… | +7.8% |
| Nov 4, 2026 | 0016-03-125 | IH 35 from Comal C/L to Marshall St.Hays · Austin | 5 of 6 | $3,801,261 | $2,797,454BOBCAT SERVICES, INC. | +35.9% |
| Nov 4, 2026 | 0157-04-058 | SB US 277 S Y IN HASKELL TO JONES COUNTYHaskell · Abilene | 1 of 9 | $6,732,215 | $6,732,215 | Won |
| Nov 4, 2026 | 6510-39-001 | BELL - FY27 BASE FAILURE REPAIRBell · Waco | 3 of 3 | $1,876,700 | $1,470,225TEXAS MATERIALS GROUP, INC. | +27.6% |
| Nov 3, 2026 | 6510-37-001 | MCLENNAN - FY27 BASE FAILURE REPAIRMcLennan · Waco | 4 of 4 | $3,542,100 | $2,172,910TEXAS MATERIALS GROUP, INC. | +63.0% |
| Nov 3, 2026 | 6510-38-001 | GATESVILLE AO - FY27 BASE FAILURE REPAIRCoryell · Waco | 4 of 4 | $2,005,650 | $1,146,275BIG CREEK CONSTRUCTION, LTD. | +75.0% |
| Sep 22, 2026 | 6494-48-001 | Hot Mix CL - DeWitt Co. (Materials Only)De Witt · Yoakum | 3 of 3 | $597,000 | $510,000BRAUNTEX MATERIALS, INC. | +17.1% |
| Sep 2, 2026 | 0337-03-020 | FM 1331 - W of FM 619 to Milam C/LWilliamson · Austin | 1 of 4 | $2,174,856 | $2,174,856 | Won |
| Sep 2, 2026 | 6496-52-001 | FY 27 West Hot Mix Cold-LaidBlanco · Austin | 2 of 4 | $3,005,750 | $2,803,000BRAUNTEX MATERIALS, INC. | +7.2% |
| Sep 2, 2026 | 6496-53-001 | FY 27 East Hot Mix Cold-LaidHays · Austin | 2 of 4 | $2,290,500 | $2,219,000BRAUNTEX MATERIALS, INC. | +3.2% |
| Aug 5, 2026 | 0276-07-035 | US 57:0276-07-035; OVFrio · San Antonio | 4 of 6 | $8,989,700 | $7,430,847CLARK CONSTRUCTION OF TEXAS… | +21.0% |
| Jul 15, 2026 | 6505-27-001 | HOT-MIX (MAT ONLY) SAN SABA COUNTYSan Saba · Brownwood | 2 of 4 | $218,000 | $178,980BIG CREEK CONSTRUCTION, LTD. | +21.8% |
| Jul 14, 2026 | 6503-82-001 | FY26 Milam HMA - 07Milam · Bryan | 1 of 3 | $372,300 | $372,300 | Won |
| Jul 1, 2026 | 0143-01-068 | US 87: 0143-01-068; OVBexar · San Antonio | 8 of 8 | $3,556,084 | $2,314,232TEXAS MATERIALS GROUP, INC. | +53.7% |
| Jul 1, 2026 | 0088-02-063 | US 59 Goliad Fort St to SH 239 RehabGoliad · Corpus Christi | 4 of 7 | $2,473,962 | $2,132,369HUNTER INDUSTRIES, LTD. | +16.0% |
| Jul 1, 2026 | 6498-75-001 | Hot Mix - Bell and FallsBell · Waco | 3 of 4 | $1,381,000 | $1,302,581TEXAS MATERIALS GROUP, INC. | +6.0% |
| Jul 1, 2026 | 6498-77-001 | Hot Mix - Coryell and HamiltonCoryell · Waco | 2 of 4 | $1,247,925 | $1,194,788BIG CREEK CONSTRUCTION, LTD. | +4.4% |
| Jun 10, 2026 | 6502-36-001 | FY26 Robertson Hot Mix - 06Robertson · Bryan | 3 of 5 | $384,125 | $330,664BIG CREEK CONSTRUCTION, LTD. | +16.2% |
| May 13, 2026 | 6495-92-001 | Asphalt Repair FY 26-2Hays · Austin | 1 of 3 | $890,314 | $890,314 | Won |
| May 7, 2026 | 6488-81-001 | FY26 - Calvert Mill & InlayRobertson · Bryan | 1 of 5 | $2,266,508 | $2,266,508 | Won |
| May 7, 2026 | 0073-02-092 | SS 536: 0073-02-092: OVBexar · San Antonio | 5 of 7 | $1,459,001 | $1,105,677H. L. ZUMWALT CONSTRUCTION,… | +32.0% |
| May 6, 2026 | 0209-01-076 | OV | US 77 | FM 3148 | LP 340McLennan · Waco | 4 of 4 | $8,080,110 | $5,957,588BIG CREEK CONSTRUCTION, LTD. | +35.6% |
| May 6, 2026 | 0915-00-313 | VA: 0915-00-313: SC PrepBexar · San Antonio | 5 of 5 | $6,147,288 | $4,426,974CLARK CONSTRUCTION OF TEXAS… | +38.9% |
| Apr 7, 2026 | 0986-03-015 | FM 619 from FM 1331 to US 79Williamson · Austin | 1 of 4 | $1,567,487 | $1,567,487 | Won |
| Apr 7, 2026 | 0337-02-054 | SH 29 - FM 1660 to SH 95Williamson · Austin | 1 of 4 | $2,388,456 | $2,388,456 | Won |
| Apr 7, 2026 | 0016-08-049 | SL 368: 0016-08-049; OVBexar · San Antonio | 3 of 6 | $4,957,515 | $3,947,711CLARK CONSTRUCTION OF TEXAS… | +25.6% |
| Mar 24, 2026 | 6494-74-001 | Hot Mix - Fayette (Materials Only)Fayette · Yoakum | 4 of 5 | $1,228,500 | $1,036,750TEXAS MATERIALS GROUP, INC. | +18.5% |
| Mar 24, 2026 | 6494-75-001 | Hot Mix CL - Fayette (Materials Only)Fayette · Yoakum | 4 of 5 | $485,000 | $436,250TEXAS MATERIALS GROUP, INC. | +11.2% |
| Mar 24, 2026 | 6498-46-001 | HOT-MIX (MAT ONLY) LAMP COUNTYLampasas · Brownwood | 2 of 3 | $213,625 | $193,750BIG CREEK CONSTRUCTION, LTD. | +10.3% |
| Mar 24, 2026 | 6494-68-001 | Hot Mix - DeWitt (Materials Only)De Witt · Yoakum | 4 of 4 | $1,074,000 | $936,000BRAUNTEX MATERIALS, INC. | +14.7% |
| Mar 24, 2026 | 6494-69-001 | Hot Mix - Lavaca (Materials Only)Lavaca · Yoakum | 3 of 5 | $1,058,000 | $943,000BRAUNTEX MATERIALS, INC. | +12.2% |
| Mar 24, 2026 | 6494-71-001 | Hot Mix CL - Lavaca (Materials Only)Lavaca · Yoakum | 4 of 5 | $478,750 | $430,000TEXAS MATERIALS GROUP, INC. | +11.3% |
| Mar 24, 2026 | 6494-72-001 | Hot Mix - Gonzales (Materials Only)Gonzales · Yoakum | 4 of 4 | $983,250 | $862,500BRAUNTEX MATERIALS, INC. | +14.0% |
| Mar 24, 2026 | 6494-73-001 | Hot Mix CL - Gonzales (Materials Only)Gonzales · Yoakum | 4 of 4 | $452,500 | $405,000BRAUNTEX MATERIALS, INC. | +11.7% |
| Mar 5, 2026 | 3544-04-011 | SH 211: 3544-04-011: OVBexar · San Antonio | 5 of 8 | $2,858,516 | $2,498,078BOBCAT SERVICES, INC. | +14.4% |
| Mar 5, 2026 | 3545-02-013 | FM 110 - IH 35 to SH 123Hays · Austin | 6 of 7 | $1,961,143 | $1,570,963DEAN WORD COMPANY, LTD. | +24.8% |
| Mar 5, 2026 | 6491-05-001 | FY26 - Robertson SH 6 Mill & InlayRobertson · Bryan | 6 of 7 | $2,926,779 | $2,329,117TEXAS MATERIALS GROUP, INC. | +25.7% |
| Mar 4, 2026 | 0253-03-078 | US 281:0253-03-078; OVComal · San Antonio | 2 of 6 | $6,264,913 | $5,825,981TEXAS MATERIALS GROUP, INC. | +7.5% |
| Mar 4, 2026 | 0542-06-053 | US59LiveOakFM1359-McMullenOVLive Oak · Corpus Christi | 3 of 5 | $5,810,892 | $5,311,274HUNTER INDUSTRIES, LTD. | +9.4% |
| Mar 4, 2026 | 1776-02-021 | FM 2001 - Satterwhite Rd to SH 21Hays · Austin | 1 of 7 | $1,788,338 | $1,788,338 | Won |
| Mar 4, 2026 | 0421-02-034 | SH 173: 0421-02-034; OVMedina · San Antonio | 7 of 11 | $1,927,520 | $1,524,647CLARK CONSTRUCTION OF TEXAS… | +26.4% |
| Feb 17, 2026 | 6494-52-001 | Hot Mix CL-Colorado Co. (Materials Only)Colorado · Yoakum | 4 of 5 | $471,875 | $417,500BRAUNTEX MATERIALS, INC. | +13.0% |
| Feb 5, 2026 | 0366-02-096 | SH 123: 0366-02-096: RERGuadalupe · San Antonio | 3 of 7 | $4,536,034 | $4,323,419CLARK CONSTRUCTION OF TEXAS… | +4.9% |
| Feb 5, 2026 | 6494-87-001 | MILL AND INLAY (SOUTH)Brown · Brownwood | 5 of 6 | $1,300,120 | $1,025,505ALLEN KELLER COMPANY | +26.8% |
| Feb 4, 2026 | 0015-11-075 | SL 275 - Braker Ln to Morrow StTravis · Austin | 2 of 5 | $2,253,646 | $2,185,903ALLEN KELLER COMPANY | +3.1% |
| Feb 4, 2026 | 0017-09-106 | IH 35: 0017-09-106; OVBexar · San Antonio | 1 of 4 | $15,028,560 | $15,028,560 | Won |
| Feb 4, 2026 | 0150-05-051 | SH 29 - E of PR 4 to W of RM 3509Burnet · Austin | 1 of 6 | $2,897,632 | $2,897,632 | Won |
| Jan 14, 2026 | 6493-72-001 | Hot Mix - Bell and CoryellBell · Waco | 2 of 4 | $762,975 | $761,450BIG CREEK CONSTRUCTION, LTD. | +0.2% |
| Jan 7, 2026 | 6494-27-001 | FY26 BASE REPAIR KERRVILLE AOKerr · San Antonio | 3 of 4 | $2,149,990 | $1,989,197CLARK CONSTRUCTION OF TEXAS… | +8.1% |
| Jan 7, 2026 | 6494-40-001 | FY2026 BASE REPAIR FOR BEXAR METRO AOBexar · San Antonio | 2 of 5 | $1,641,568 | $1,555,323CLARK CONSTRUCTION OF TEXAS… | +5.5% |
| Jan 7, 2026 | 6494-43-001 | FY2026 BASE REPAIR FOR HONDO AOFrio · San Antonio | 4 of 6 | $2,157,818 | $1,957,502CLARK CONSTRUCTION OF TEXAS… | +10.2% |
| Jan 6, 2026 | 6494-41-001 | FY2026 BASE REPAIR FOR NORTH BEXAR AOBexar · San Antonio | 3 of 4 | $1,846,726 | $1,616,344TEXAS MATERIALS GROUP, INC. | +14.3% |
| Jan 6, 2026 | 6494-42-001 | FY2026 BASE REPAIR FOR NEW BRAUNFELS AOWilson · San Antonio | 2 of 5 | $2,221,441 | $1,893,846TEXAS MATERIALS GROUP, INC. | +17.3% |
| Jan 6, 2026 | 0054-06-114 | US 67/377 Overlay From FM2524 to US 377Brown · Brownwood | 4 of 6 | $2,558,289 | $1,931,829BIG CREEK CONSTRUCTION, LTD. | +32.4% |
| Dec 3, 2025 | 0322-01-052 | SH 95 - US 290 to S of FM 2336Bastrop · Austin | 1 of 6 | $2,047,396 | $2,047,396 | Won |
| Nov 12, 2025 | 6488-06-001 | HOT-MIX COLD-LAID-MATERIAL ONLYBell · Waco | 2 of 3 | $644,500 | $642,838TEXAS MATERIALS GROUP, INC. | +0.3% |
| Oct 15, 2025 | 6487-58-001 | HOT-MIX COLD-LAID BROWN 2025 (MAT ONLY)Brown · Brownwood | 3 of 4 | $256,000 | $220,220VULCAN CONSTRUCTION MATERIA… | +16.2% |
| Oct 9, 2025 | 6482-90-001 | FY 26 East Hot Mix Cold-LaidHays · Austin | 1 of 4 | $2,040,450 | $2,040,450 | Won |
| Oct 9, 2025 | 0252-01-087 | US 281 - PR 4 to RM 1855Burnet · Austin | 2 of 6 | $1,582,616 | $1,537,148TEXAS MATERIALS GROUP, INC. | +3.0% |
| Oct 9, 2025 | 0017-09-114 | IH 35:0017-09-114:OVBexar · San Antonio | 4 of 5 | $3,464,165 | $2,846,602TEXAS MATERIALS GROUP, INC. | +21.7% |
| Sep 22, 2025 | 6486-98-001 | Hot Mix CL-DeWitt Co. (Materials Only)De Witt · Yoakum | 4 of 4 | $560,250 | $504,000BRAUNTEX MATERIALS, INC. | +11.2% |
| Sep 5, 2025 | 1534-01-021 | RM 1623Blanco · Austin | 3 of 8 | $549,658 | $507,633HUNTER INDUSTRIES, LTD. | +8.3% |
| Sep 5, 2025 | 1500-01-028 | FM 1582:1500-01-028; OVFrio · San Antonio | 2 of 8 | $2,944,130 | $2,460,101HUNTER INDUSTRIES, LTD. | +19.7% |
| Sep 5, 2025 | 0380-09-104 | OVERLAY_0380-09Midland · Odessa | 4 of 5 | $6,438,789 | $5,391,295JONES BROS. DIRT & PAVING C… | +19.4% |
| Sep 5, 2025 | 0073-10-053 | IH 37: 0073-10-053; OVAtascosa · San Antonio | 1 of 5 | $17,520,874 | $17,520,874 | Won |
| Sep 4, 2025 | 6482-89-001 | FY 26 Hot Mix Cold-LaidBlanco · Austin | 3 of 5 | $2,657,950 | $2,556,200BRAUNTEX MATERIALS, INC. | +4.0% |
| Sep 4, 2025 | 0805-03-022 | FM 713 - FM 20 to FM 86Caldwell · Austin | 1 of 6 | $2,233,729 | $2,233,729 | Won |
| Aug 8, 2025 | 6482-34-001 | SH130 Frontage Road Mill & InlayWilliamson · Austin | 3 of 5 | $15,280,361 | $13,801,280ALLEN KELLER COMPANY | +10.7% |
| Aug 7, 2025 | 6482-35-001 | SH130 & SH45 Frontage Road Mill & InlayTravis · Austin | 1 of 4 | $12,111,218 | $12,111,218 | Won |
| Jul 24, 2025 | 6487-58-001 | HOT-MIX COLD-LAID BROWN 2025 (MAT ONLY)Brown · Brownwood | 3 of 5 | $269,500 | $240,000VALUE DRILLING COMPANY INC | +12.3% |
| Jul 15, 2025 | 6485-79-001 | 6485-79-001 HMCL Karnes Maint.Karnes · Corpus Christi | 3 of 3 | $312,650 | $279,000BRAUNTEX MATERIALS, INC. | +12.1% |
| Jul 9, 2025 | 6486-09-001 | FY25 Robertson HMA - 07Robertson · Bryan | 4 of 4 | $522,750 | $411,000BIG CREEK CONSTRUCTION, LTD. | +27.2% |
| Jul 8, 2025 | 6486-12-001 | FY25 Burleson HMA - 07Burleson · Bryan | 3 of 3 | $391,500 | $292,200BRAZOS PAVING, INC. | +34.0% |
| Jul 2, 2025 | 6479-85-001 | HOT MIX - CORYELL AND HAMILTON (FY 25)Coryell · Waco | 3 of 4 | $1,274,288 | $1,227,192TEXAS MATERIALS GROUP, INC. | +3.8% |
| Jul 2, 2025 | 0216-03-037 | FM 466: 0216-03-037: OVGuadalupe · San Antonio | 5 of 5 | $910,961 | $643,755DEAN WORD COMPANY, LTD. | +41.5% |
| Jul 1, 2025 | 0521-01-057 | SL 13: 0521-01-057: OVBexar · San Antonio | 2 of 6 | $6,351,538 | $5,240,622CLARK CONSTRUCTION OF TEXAS… | +21.2% |
| Jul 1, 2025 | 0017-01-025 | SL 353: 0017-01-025; OVBexar · San Antonio | 3 of 7 | $4,064,197 | $3,232,999CLARK CONSTRUCTION OF TEXAS… | +25.7% |
| Jul 1, 2025 | 6479-84-001 | HOT MIX - BELL & FALLS COUNTYBell · Waco | 3 of 4 | $1,408,938 | $1,367,899TEXAS MATERIALS GROUP, INC. | +3.0% |
| May 2, 2025 | 0542-06-050 | US 59 LiveOak lagarto-FM 1359 OVLive Oak · Corpus Christi | 1 of 5 | $8,329,533 | $8,329,533 | Won |
| May 1, 2025 | 0521-05-151 | IH 410: 0521-05-151; OVBexar · San Antonio | 3 of 6 | $9,993,793 | $9,693,874TEXAS MATERIALS GROUP, INC. | +3.1% |
| Apr 4, 2025 | 0029-03-055 | US 90-S. of Mesquite to 0.20 W OF PLUM CCaldwell · Austin | 2 of 6 | $4,371,612 | $4,315,552HUNTER INDUSTRIES, LTD. | +1.3% |
| Mar 27, 2025 | 6481-97-001 | HOT-MIX (MATERIALS ONLY) SANSABA COUNTYSan Saba · Brownwood | 1 of 2 | $208,000 | $208,000 | Won |
| Mar 24, 2025 | 6476-89-001 | Hot Mix-DeWitt County (Materials Only)De Witt · Yoakum | 4 of 4 | $1,110,000 | $957,000TEXAS MATERIALS GROUP, INC. | +16.0% |
| Mar 24, 2025 | 6476-86-001 | Hot Mix-Fayette Co. (Materials Only)Fayette · Yoakum | 4 of 4 | $1,053,250 | $877,250TEXAS MATERIALS GROUP, INC. | +20.1% |
| Mar 24, 2025 | 6476-87-001 | Hot Mix-Gonzales Co. (Materials Only)Gonzales · Yoakum | 4 of 4 | $1,008,000 | $886,200TEXAS MATERIALS GROUP, INC. | +13.7% |
| Mar 24, 2025 | 6476-88-001 | Hot Mix-Lavaca County (Materials Only)Lavaca · Yoakum | 5 of 5 | $1,242,000 | $977,500TEXAS MATERIALS GROUP, INC. | +27.1% |
| Mar 24, 2025 | 6476-90-001 | Hot Mix CL-Fayette Co (Materials Only)Fayette · Yoakum | 4 of 4 | $615,750 | $531,000BRAUNTEX MATERIALS, INC. | +16.0% |
| Mar 24, 2025 | 6476-91-001 | Hot Mix CL-Gonzales (Materials Only)Gonzales · Yoakum | 3 of 4 | $528,000 | $474,000TEXAS MATERIALS GROUP, INC. | +11.4% |
| Mar 24, 2025 | 6476-92-001 | Hot Mix CL-Lavaca Co. (Materials Only)Lavaca · Yoakum | 4 of 4 | $620,250 | $516,000TEXAS MATERIALS GROUP, INC. | +20.2% |
| Mar 5, 2025 | 1566-02-028 | FM 1660 - King Ln to FM 973Williamson · Austin | 1 of 5 | $3,853,030 | $3,853,030 | Won |
| Mar 4, 2025 | 7774-01-006 | PA 1502: 7774-01-006: OVBexar · San Antonio | 3 of 4 | $1,709,157 | $1,579,728HUNTER INDUSTRIES, LTD. | +8.2% |
| Feb 18, 2025 | 6476-65-001 | Hot Mix CL-Austin Co. (Materials Only)Austin · Yoakum | 5 of 5 | $298,125 | $225,000BRAUNTEX MATERIALS, INC. | +32.5% |
| Feb 18, 2025 | 6476-62-001 | Hot Mix CL-Colorado (Materials Only)Colorado · Yoakum | 4 of 4 | $298,125 | $217,500BRAUNTEX MATERIALS, INC. | +37.1% |
| Feb 18, 2025 | 6476-64-001 | Hot Mix CL-Matagorda (Materials Only)Matagorda · Yoakum | 5 of 5 | $311,250 | $246,250QUALITY HOT MIX, INC. | +26.4% |
| Feb 18, 2025 | 6476-63-001 | Hot Mix CL-Wharton (Materials Only)Wharton · Yoakum | 5 of 5 | $298,125 | $227,500BRAUNTEX MATERIALS, INC. | +31.0% |
| Feb 12, 2025 | 6479-31-001 | FY25 - Milam HMA -02Milam · Bryan | 1 of 4 | $390,150 | $390,150 | Won |
| Feb 7, 2025 | 0915-15-101 | VA: 0915-15-101; TPWKerr · San Antonio | 1 of 7 | $908,186 | $908,186 | Won |
| Feb 7, 2025 | 0151-09-149 | US 183 from IH 135 to US290Travis · Austin | 1 of 3 | $1,181,539 | $1,181,539 | Won |
| Feb 7, 2025 | 0072-12-201 | IH 10: 0072-12-201: OVBexar · San Antonio | 1 of 5 | $6,824,351 | $6,824,351 | Won |
| Feb 6, 2025 | 0025-02-226 | IH10: 0025-02-226; FR OVBexar · San Antonio | 2 of 6 | $8,221,539 | $7,922,686DEAN WORD COMPANY, LTD. | +3.8% |
| Feb 6, 2025 | 0025-09-081 | FM 78; 0025-09-081; OVBexar · San Antonio | 4 of 4 | $23,496,212 | $21,789,871TEXAS MATERIALS GROUP, INC. | +7.8% |
| Feb 4, 2025 | 6478-97-001 | 2025 East Bexar HMABexar · San Antonio | 2 of 5 | $638,365 | $580,720TEXAS MATERIALS GROUP, INC. | +9.9% |
| Feb 4, 2025 | 6478-98-001 | 2025 Comal HMAComal · San Antonio | 4 of 5 | $902,000 | $781,000TEXAS MATERIALS GROUP, INC. | +15.5% |
| Jan 14, 2025 | 6477-81-001 | 2025 Medina HMAMedina · San Antonio | 1 of 6 | $224,850 | $224,850 | Won |
| Jan 14, 2025 | 6477-78-001 | 2025 Bexar HMCLBexar · San Antonio | 3 of 4 | $67,025 | $64,800TEXAS MATERIALS GROUP, INC. | +3.4% |
| Jan 8, 2025 | 0251-06-041 | US183 AVE E TO NINTH ST MILL&OVERLAYLampasas · Brownwood | 1 of 6 | $1,066,350 | $1,066,350 | Won |
| Jan 8, 2025 | 0337-01-051 | SH 29 from US 183 to Jack NicklausWilliamson · Austin | 1 of 3 | $9,163,865 | $9,163,865 | Won |
| Jan 8, 2025 | 6473-58-001 | HOT MIX - BELL & CORYELLBell · Waco | 2 of 4 | $1,316,813 | $1,283,290TEXAS MATERIALS GROUP, INC. | +2.6% |
| Jan 8, 2025 | 0114-04-078 | US 290 from SH 95 to FM 696 OverlayBastrop · Austin | 3 of 6 | $4,615,004 | $4,270,055TEXAS MATERIALS GROUP, INC. | +8.1% |
| Jan 8, 2025 | 0150-03-021 | Sh 29 From Autumn Ave to Wells AveLlano · Austin | 2 of 6 | $1,567,173 | $1,386,823TEXAS MATERIALS GROUP, INC. | +13.0% |
| Jan 7, 2025 | 0320-03-102 | SH 95 from Bell C/L to FM 971Williamson · Austin | 1 of 3 | $3,483,608 | $3,483,608 | Won |
| Jan 7, 2025 | 0683-03-047 | RM - Wimberley CL to Old Kyle RdHays · Austin | 3 of 4 | $650,084 | $581,999DEAN WORD COMPANY, LTD. | +11.7% |
| Dec 4, 2024 | 6473-56-001 | BASE FAILURE PAVEMENT REPAIR-CORYELLCoryell · Waco | 3 of 4 | $2,356,575 | $1,449,375BIG CREEK CONSTRUCTION, LTD. | +62.6% |
| Dec 4, 2024 | 6473-41-001 | Base Repair - McLennanMcLennan · Waco | 3 of 3 | $2,118,825 | $1,423,275BIG CREEK CONSTRUCTION, LTD. | +48.9% |
| Dec 3, 2024 | 1533-01-022 | FM 1704 from Lower Elgin Rd to FM 969Bastrop · Austin | 1 of 6 | $2,843,419 | $2,843,419 | Won |
| Dec 3, 2024 | 6473-55-001 | BASE FAILURE PAVEMENT REPAIRBell · Waco | 3 of 3 | $1,786,475 | $1,547,097TEXAS MATERIALS GROUP, INC. | +15.5% |
| Nov 13, 2024 | 6473-54-001 | HOT-MIX COLD-LAID - MATERIAL ONLYBell · Waco | 1 of 3 | $651,375 | $651,375 | Won |
| Nov 7, 2024 | 3136-01-190 | SL 1 from Barton Springs Road to SL 360Travis · Austin | 2 of 4 | $3,633,072 | $3,314,600HUNTER INDUSTRIES, LTD. | +9.6% |
| Nov 7, 2024 | 1378-02-059 | RM 1431 From Travis C/L to US 183AWilliamson · Austin | 1 of 2 | $2,125,759 | $2,125,759 | Won |
| Nov 6, 2024 | 0535-07-053 | IH 10 PFC 2511Fayette · Yoakum | 3 of 4 | $11,514,582 | $10,827,270HUNTER INDUSTRIES, LTD. | +6.3% |
| Nov 6, 2024 | 6474-45-001 | FY25 BASE REPAIR NORTH BEXAR AOBexar · San Antonio | 2 of 6 | $1,703,328 | $1,592,374TEXAS MATERIALS GROUP, INC. | +7.0% |
| Aug 2, 2024 | 0074-01-062 | RESURFACE ROADWAYLive Oak · Corpus Christi | 2 of 3 | $14,709,305 | $14,385,828TEXAS MATERIALS GROUP, INC. | +2.2% |
| Aug 2, 2024 | 6470-42-001 | MILL AND INLAYBandera · San Antonio | 4 of 6 | $1,768,871 | $1,543,147TEXAS MATERIALS GROUP, INC. | +14.6% |
| Aug 2, 2024 | 6467-53-001 | HOT MIXBell · Waco | 4 of 4 | $1,684,900 | $1,496,929TEXAS MATERIALS GROUP, INC. | +12.6% |
| Aug 1, 2024 | 6467-54-001 | HOT MIXCoryell · Waco | 4 of 4 | $2,113,375 | $1,892,350BIG CREEK CONSTRUCTION, LTD. | +11.7% |
| Aug 1, 2024 | 6470-28-001 | MILL AND INLAYComal · San Antonio | 5 of 7 | $2,884,159 | $2,292,837CLARK CONSTRUCTION OF TEXAS… | +25.8% |
| Jul 25, 2024 | 6395-83-001 | HOT-MIX_(MATERIALS ONLY)Lampasas · Brownwood | 1 of 2 | $240,500 | $240,500 | Won |
| Jun 6, 2024 | 0265-04-075 | PREVENTIVE MAINTENANCEBastrop · Austin | 1 of 4 | $4,578,078 | $4,578,078 | Won |
| Jun 6, 2024 | 6467-43-001 | BASE FAILURE PAVEMENT REPAIRMcLennan · Waco | 4 of 4 | $3,124,170 | $2,169,039BIG CREEK CONSTRUCTION, LTD. | +44.0% |
| Jun 5, 2024 | 0285-02-015 | RESURFACE ROADWAYHays · Austin | 3 of 5 | $4,619,442 | $4,429,880DEAN WORD COMPANY, LTD. | +4.3% |
| Jun 5, 2024 | 2057-01-010 | SURFACING/ROADWAY RESTORATIONBell · Waco | 1 of 3 | $1,357,784 | $1,357,784 | Won |
| Jun 5, 2024 | 6467-38-001 | BASE FAILURE PAVEMENT REPAIRBell · Waco | 2 of 3 | $1,031,776 | $875,096TEXAS MATERIALS GROUP, INC. | +17.9% |
| May 3, 2024 | 2102-01-078 | PREVENTIVE MAINTENANCETravis · Austin | 1 of 4 | $5,079,255 | $5,079,255 | Won |
| May 3, 2024 | 3417-03-033 | PREVENTIVE MAINTENANCETravis · Austin | 2 of 5 | $3,807,797 | $3,643,668TEXAS MATERIALS GROUP, INC. | +4.5% |
| May 2, 2024 | 0074-02-082 | RESURFACE ROADWAYLive Oak · Corpus Christi | 2 of 2 | $15,076,811 | $13,060,729HUNTER INDUSTRIES, LTD. | +15.4% |
| Apr 5, 2024 | 0073-07-071 | RESURFACE ROADWAYLive Oak · Corpus Christi | 1 of 2 | $6,063,315 | $6,063,315 | Won |
| Apr 5, 2024 | 6463-41-001 | MILL AND INLAYBexar · San Antonio | 2 of 5 | $1,215,228 | $1,088,978CLARK CONSTRUCTION OF TEXAS… | +11.6% |
| Apr 4, 2024 | 6463-42-001 | MILL AND INLAYBexar · San Antonio | 3 of 4 | $1,377,502 | $1,086,329CLARK CONSTRUCTION OF TEXAS… | +26.8% |
| Feb 2, 2024 | 0204-02-036 | RESURFACE ROADWAYWilliamson · Austin | 1 of 2 | $3,840,828 | $3,840,828 | Won |
| Feb 2, 2024 | 2103-01-044 | RESURFACE ROADWAYWilliamson · Austin | 2 of 2 | $2,035,554 | $1,696,964TEXAS MATERIALS GROUP, INC. | +20.0% |
| Feb 2, 2024 | 0114-20-014 | PREVENTIVE MAINTENANCETravis · Austin | 2 of 2 | $1,086,299 | $799,754TEXAS MATERIALS GROUP, INC. | +35.8% |
| Feb 2, 2024 | 0286-01-065 | PREVENTIVE MAINTENANCEHays · Austin | 2 of 5 | $1,066,165 | $1,035,073DEAN WORD COMPANY, LTD. | +3.0% |
| Feb 1, 2024 | 0252-02-064 | RESURFACE ROADWAYBurnet · Austin | 2 of 4 | $5,862,489 | $5,701,426CLARK CONSTRUCTION OF TEXAS… | +2.8% |
| Feb 1, 2024 | 0914-00-512 | HIGHWAY IMPROVEMENTTravis · Austin | 2 of 2 | $9,381,480 | $7,676,625TEXAS MATERIALS GROUP, INC. | +22.2% |
| Feb 1, 2024 | 2295-01-019 | RESURFACE ROADWAYWilliamson · Austin | 1 of 2 | $885,043 | $885,043 | Won |
| Feb 1, 2024 | 6422-12-001 | ASPHALT PAVEMENT REPAIRDe Witt · Yoakum | 4 of 5 | $1,963,869 | $1,882,668HUNTER INDUSTRIES, LTD. | +4.3% |
| Jan 5, 2024 | 0017-06-086 | RESURFACE ROADWAYFrio · San Antonio | 2 of 7 | $11,941,602 | $11,872,495ANDERSON COLUMBIA CO., INC. | +0.6% |
| Jan 5, 2024 | 0265-03-053 | RESURFACE ROADWAYBastrop · Austin | 1 of 5 | $6,520,251 | $6,520,251 | Won |
| Jan 5, 2024 | 3210-01-020 | RESURFACE ROADWAYHays · Austin | 2 of 3 | $346,206 | $294,472DEAN WORD COMPANY, LTD. | +17.6% |
| Jan 4, 2024 | 0015-08-431 | RESURFACE ROADWAYWilliamson · Austin | 1 of 3 | $5,399,229 | $5,399,229 | Won |
| Jan 4, 2024 | 0142-06-029 | REPAIR ROADWAYKendall · San Antonio | 2 of 6 | $3,991,116 | $3,751,988CLARK CONSTRUCTION OF TEXAS… | +6.4% |
| Jan 4, 2024 | 2718-01-015 | RESURFACE ROADWAYTravis · Austin | 2 of 3 | $3,837,138 | $2,979,803TEXAS MATERIALS GROUP, INC. | +28.8% |
| Jan 4, 2024 | 0113-13-184 | RESURFACE ROADWAYTravis · Austin | 1 of 3 | $2,026,821 | $2,026,821 | Won |
| Jan 4, 2024 | 1197-01-025 | PREVENTIVE MAINTENANCEHays · Austin | 2 of 4 | $1,172,650 | $1,083,996CLARK CONSTRUCTION OF TEXAS… | +8.2% |
| Dec 6, 2023 | 0700-04-053 | PREVENTIVE MAINTENANCELlano · Austin | 1 of 6 | $3,798,988 | $3,798,988 | Won |
| Dec 5, 2023 | 0471-04-035 | PREVENTIVE MAINTENANCECaldwell · Austin | 1 of 4 | $9,312,832 | $9,312,832 | Won |
| Dec 5, 2023 | 1378-04-056 | RESURFACE ROADWAYBurnet · Austin | 1 of 6 | $7,574,977 | $7,574,977 | Won |
| Dec 5, 2023 | 0015-11-074 | PREVENTIVE MAINTENANCETravis · Austin | 2 of 3 | $3,426,674 | $3,285,366HUNTER INDUSTRIES, LTD. | +4.3% |
| Dec 5, 2023 | 6340-47-001 | ACP OVERLAYTravis · Austin | 1 of 3 | $40,923,831 | $40,923,831 | Won |
| Nov 2, 2023 | 0071-04-057 | SEAL COATMason · Austin | 2 of 6 | $7,918,520 | $6,987,837ALLEN KELLER COMPANY | +13.3% |
| Nov 2, 2023 | 1378-03-039 | SEAL COATBurnet · Austin | 1 of 6 | $6,275,058 | $6,275,058 | Won |
| Nov 2, 2023 | 0112-02-036 | SEAL COATGillespie · Austin | 3 of 5 | $4,869,598 | $3,888,101ALLEN KELLER COMPANY | +25.2% |
| Nov 1, 2023 | 0384-04-034 | SEAL COATCaldwell · Austin | 1 of 3 | $8,806,087 | $8,806,087 | Won |
| Nov 1, 2023 | 0700-04-054 | SEAL COATLlano · Austin | 2 of 7 | $7,450,265 | $6,207,912ALLEN KELLER COMPANY | +20.0% |
| Nov 1, 2023 | 3351-02-006 | SEAL COATBlanco · Austin | 4 of 5 | $6,288,774 | $4,405,351ALLEN KELLER COMPANY | +42.8% |
| Nov 1, 2023 | 6442-78-001 | ASPHALT PAVEMENT REPAIRTravis · Austin | 2 of 2 | $6,551,435 | $6,010,997TEXAS MATERIALS GROUP, INC. | +9.0% |
| Oct 6, 2023 | 2293-01-032 | PREVENTIVE MAINTENANCEHays · Austin | 2 of 4 | $1,035,883 | $958,354HUNTER INDUSTRIES, LTD. | +8.1% |
| Oct 6, 2023 | 0016-02-169 | PREVENTIVE MAINTENANCEHays · Austin | 1 of 4 | $915,989 | $915,989 | Won |
| Oct 5, 2023 | 3534-02-007 | SURFACING/ROADWAY RESTORATIONBell · Waco | 3 of 3 | $6,665,484 | $5,861,342TEXAS MATERIALS GROUP, INC. | +13.7% |
| Oct 5, 2023 | 0071-06-062 | SURFACING/ROADWAY RESTORATIONGillespie · Austin | 3 of 5 | $7,444,872 | $6,082,477CLARK CONSTRUCTION OF TEXAS… | +22.4% |
| Sep 7, 2023 | 0072-05-089 | RESURFACE ROADWAYKendall · San Antonio | 2 of 6 | $27,410,575 | $26,085,495TEXAS MATERIALS GROUP, INC. | +5.1% |
| Sep 7, 2023 | 0112-03-036 | SEAL COATGillespie · Austin | 4 of 4 | $3,842,461 | $3,070,930ALLEN KELLER COMPANY | +25.1% |
| Sep 7, 2023 | 0334-05-035 | SEAL COATLee · Austin | 3 of 3 | $4,021,857 | $3,387,874TEXAS MATERIALS GROUP, INC. | +18.7% |
| Sep 7, 2023 | 2210-01-008 | SEAL COATTravis · Austin | 3 of 3 | $1,706,843 | $1,340,429TEXAS MATERIALS GROUP, INC. | +27.3% |
| Sep 7, 2023 | 0914-04-288 | STATE PARK IMPROVEMENTSTravis · Austin | 2 of 2 | $972,342 | $971,504FNH CONSTRUCTION, LLC | +0.1% |
| Aug 2, 2023 | 0914-21-032 | PREVENTIVE MAINTENANCELee · Austin | 1 of 3 | $1,068,092 | $1,068,092 | Won |
| Jun 27, 2023 | 0015-11-073 | PREVENTIVE MAINTENANCETravis · Austin | 1 of 4 | $1,029,125 | $1,029,125 | Won |
| Jun 27, 2023 | 6443-58-001 | REHABILITATION OF EXISTING ROADWAYBexar · San Antonio | 2 of 3 | $460,589 | $364,201TEXAS MATERIALS GROUP, INC. | +26.5% |
| May 5, 2023 | 0142-01-076 | PREVENTIVE MAINTENANCEKimble · San Angelo | 1 of 3 | $20,144,525 | $20,144,525 | Won |
| May 5, 2023 | 1754-01-020 | PREVENTIVE MAINTENANCETravis · Austin | 1 of 4 | $1,225,398 | $1,225,398 | Won |
| May 5, 2023 | 0683-03-044 | RESURFACE ROADWAYHays · Austin | 1 of 3 | $5,424,333 | $5,424,333 | Won |
| May 4, 2023 | 0015-13-417 | RESURFACE ROADWAYTravis · Austin | 3 of 3 | $10,316,512 | $7,604,085HUNTER INDUSTRIES, LTD. | +35.7% |
| Apr 5, 2023 | 6340-46-001 | ACP OVERLAYTravis · Austin | 1 of 3 | $34,906,067 | $34,906,067 | Won |
| Feb 2, 2023 | 0016-02-170 | RESURFACE ROADWAYHays · Austin | 3 of 4 | $4,589,202 | $4,186,522HUNTER INDUSTRIES, LTD. | +9.6% |
| Feb 2, 2023 | 1167-01-011 | RESURFACE ROADWAYUvalde · San Antonio | 1 of 3 | $1,021,333 | $1,021,333 | Won |
| Feb 2, 2023 | 6431-30-001 | HOT MIXBell · Waco | 2 of 4 | $827,750 | $820,000BIG CREEK CONSTRUCTION, LTD. | +0.9% |
| Feb 1, 2023 | 0231-02-066 | MILL AND INLAYCoryell · Waco | 3 of 3 | $9,884,850 | $9,294,253TEXAS MATERIALS GROUP, INC. | +6.4% |
| Feb 1, 2023 | 0535-05-037 | SURFACING/ROADWAY RESTORATIONGonzales · Yoakum | 2 of 3 | $12,905,847 | $12,470,411HUNTER INDUSTRIES, LTD. | +3.5% |
| Feb 1, 2023 | 0366-02-094 | RESURFACE ROADWAYGuadalupe · San Antonio | 2 of 4 | $7,607,493 | $7,325,978HUNTER INDUSTRIES, LTD. | +3.8% |
| Feb 1, 2023 | 0320-04-029 | PREVENTIVE MAINTENANCEWilliamson · Austin | 2 of 3 | $5,737,070 | $5,596,125HUNTER INDUSTRIES, LTD. | +2.5% |
| Feb 1, 2023 | 0265-02-045 | RESURFACE ROADWAYTravis · Austin | 1 of 4 | $2,068,354 | $2,068,354 | Won |
| Jan 6, 2023 | 6406-73-001 | HOT MIXComal · San Antonio | 3 of 6 | $958,375 | $854,150TEXAS MATERIALS GROUP, INC. | +12.2% |
| Jan 6, 2023 | 6428-74-001 | SPOT BASE REPAIRGonzales · Yoakum | 3 of 4 | $1,569,500 | $985,800CORNERSTONE PAVING AND CONS… | +59.2% |
| Jan 6, 2023 | 0072-08-143 | RESURFACE ROADWAYBexar · San Antonio | 2 of 5 | $6,970,441 | $6,416,002CLARK CONSTRUCTION OF TEXAS… | +8.6% |
| Jan 6, 2023 | 0016-02-171 | RESURFACE ROADWAYHays · Austin | 3 of 3 | $7,577,283 | $6,782,284TEXAS MATERIALS GROUP, INC. | +11.7% |
| Jan 6, 2023 | 1902-01-031 | PREVENTIVE MAINTENANCETravis · Austin | 1 of 3 | $2,118,243 | $2,118,243 | Won |
| Jan 6, 2023 | 2786-01-018 | RESURFACE ROADWAYLampasas · Brownwood | 1 of 2 | $2,365,647 | $2,365,647 | Won |
| Jan 6, 2023 | 0286-01-061 | PREVENTIVE MAINTENANCEHays · Austin | 3 of 4 | $1,329,394 | $1,208,196HUNTER INDUSTRIES, LTD. | +10.0% |
| Jan 5, 2023 | 6427-94-001 | HOT MIXMilam · Bryan | 5 of 5 | $510,000 | $381,000KNIFE RIVER CORPORATION - S… | +33.9% |
| Jan 5, 2023 | 0700-04-051 | RESURFACE ROADWAYLlano · Austin | 1 of 4 | $2,134,104 | $2,134,104 | Won |
| Jan 5, 2023 | 6406-69-001 | HOT MIXBexar · San Antonio | 3 of 5 | $845,800 | $693,913TEXAS MATERIALS GROUP, INC. | +21.9% |
| Jan 5, 2023 | 6428-58-001 | HOT MIXGuadalupe · San Antonio | 4 of 5 | $361,000 | $325,250TEXAS MATERIALS GROUP, INC. | +11.0% |
| Dec 15, 2022 | 6428-68-001 | HOT-MIX (MATERIALS ONLY)Lampasas · Brownwood | 2 of 2 | $280,200 | $233,260TEXAS MATERIALS GROUP, INC. | +20.1% |
| Dec 14, 2022 | 6428-50-001 | HOT-MIX COLD-LAIDBexar · San Antonio | 3 of 5 | $72,750 | $65,700BRAUNTEX MATERIALS, INC. | +10.7% |
| Dec 2, 2022 | 6405-26-001 | ASPHALT PAVEMENT REPAIRTravis · Austin | 3 of 3 | $6,659,370 | $5,562,208HUNTER INDUSTRIES, LTD. | +19.7% |
| Dec 2, 2022 | 6418-47-001 | HOT-MIX COLD-LAIDBell · Waco | 1 of 4 | $420,000 | $420,000 | Won |
| Dec 1, 2022 | 6425-60-001 | HOT MIXBell · Waco | 2 of 4 | $824,500 | $779,000BIG CREEK CONSTRUCTION, LTD. | +5.8% |
| Nov 2, 2022 | 0141-08-050 | PREVENTIVE MAINTENANCEKimble · San Angelo | 3 of 4 | $10,318,837 | $9,718,660ALLEN KELLER COMPANY | +6.2% |
| Nov 2, 2022 | 0471-02-079 | PREVENTIVE MAINTENANCEHays · Austin | 1 of 4 | $2,808,196 | $2,808,196 | Won |
| Nov 2, 2022 | 0016-02-168 | PREVENTIVE MAINTENANCEHays · Austin | 1 of 4 | $1,151,607 | $1,151,607 | Won |
| Nov 2, 2022 | 1200-05-018 | RESURFACE ROADWAYTravis · Austin | 1 of 4 | $791,290 | $791,290 | Won |
| Nov 2, 2022 | 0805-04-035 | PREVENTIVE MAINTENANCEHays · Austin | 1 of 3 | $482,720 | $482,720 | Won |
| Oct 27, 2022 | 6423-88-001 | HOT-MIX COLD-LAID (MATERIALS ONLY)Brown · Brownwood | 3 of 4 | $236,500 | $205,000MALBEC MATERIALS LLC | +15.4% |
| Oct 27, 2022 | 6423-90-001 | HOT-MIX COLD-LAID (MATERIALS ONLY)Coleman · Brownwood | 3 of 4 | $247,000 | $211,000MALBEC MATERIALS LLC | +17.1% |
| Oct 27, 2022 | 6423-92-001 | HOT-MIX COLD-LAID (MATERIALS ONLY)McCulloch · Brownwood | 3 of 4 | $242,000 | $194,000MALBEC MATERIALS LLC | +24.7% |
| Oct 7, 2022 | 1234-02-013 | RESURFACE ROADWAYBastrop · Austin | 2 of 3 | $474,660 | $468,555HUNTER INDUSTRIES, LTD. | +1.3% |
| Oct 6, 2022 | 6417-81-001 | SEAL COATMedina · San Antonio | 5 of 5 | $1,533,991 | $1,273,725RONALD R. WAGNER & CO., LP | +20.4% |
| Sep 8, 2022 | 6410-37-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRKerr · San Antonio | 4 of 5 | $1,718,843 | $1,410,326TEXAS MATERIALS GROUP, INC. | +21.9% |
| Sep 8, 2022 | 6411-43-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRBexar · San Antonio | 3 of 5 | $1,463,489 | $1,270,874TEXAS MATERIALS GROUP, INC. | +15.2% |
| Sep 8, 2022 | 0113-05-049 | SEAL COATBlanco · Austin | 2 of 4 | $13,294,729 | $13,188,476HUNTER INDUSTRIES, LTD. | +0.8% |
| Sep 8, 2022 | 1201-02-025 | SEAL COATWilliamson · Austin | 1 of 2 | $2,349,410 | $2,349,410 | Won |
| Sep 8, 2022 | 0807-01-032 | RESURFACE ROADWAYBastrop · Austin | 2 of 5 | $1,655,946 | $1,577,805HUNTER INDUSTRIES, LTD. | +5.0% |
| Sep 8, 2022 | 1535-01-015 | RESURFACE ROADWAYTravis · Austin | 1 of 2 | $755,872 | $755,872 | Won |
| Sep 8, 2022 | 1754-02-029 | PREVENTIVE MAINTENANCEHays · Austin | 1 of 4 | $1,052,439 | $1,052,439 | Won |
| Sep 8, 2022 | 0396-02-029 | PREVENTIVE MAINTENANCEMason · Austin | 4 of 4 | $6,778,139 | $6,087,040BIG CREEK CONSTRUCTION, LTD. | +11.4% |
| Sep 8, 2022 | 0152-03-061 | PREVENTIVE MAINTENANCECaldwell · Austin | 1 of 3 | $5,467,487 | $5,467,487 | Won |
| Sep 8, 2022 | 0024-08-141 | RESURFACE ROADWAYBexar · San Antonio | 2 of 5 | $29,992,012 | $28,447,459AUSTIN BRIDGE & ROAD SERVIC… | +5.4% |
| Sep 7, 2022 | 6404-60-001 | HOT-MIX COLD-LAID (MATERIAL ONLY)Hays · Austin | 1 of 4 | $1,969,300 | $1,969,300 | Won |
| Sep 7, 2022 | 3136-01-196 | PREVENTIVE MAINTENANCETravis · Austin | 2 of 3 | $1,612,554 | $1,239,173HUNTER INDUSTRIES, LTD. | +30.1% |
| Sep 7, 2022 | 0291-02-038 | RESURFACE ROADWAYKerr · San Antonio | 4 of 4 | $4,783,119 | $4,178,288AUSTIN BRIDGE & ROAD SERVIC… | +14.5% |
| Sep 7, 2022 | 6404-64-001 | HOT-MIX COLD-LAID (MATERIAL ONLY)Blanco · Austin | 4 of 5 | $2,155,750 | $1,932,500MALBEC MATERIALS LLC | +11.6% |
| Sep 7, 2022 | 6410-63-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRMedina · San Antonio | 6 of 7 | $3,365,210 | $2,351,122CLARK CONSTRUCTION OF TEXAS… | +43.1% |
| Sep 7, 2022 | 6410-67-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRComal · San Antonio | 4 of 5 | $3,115,212 | $2,637,043TEXAS MATERIALS GROUP, INC. | +18.1% |
| Sep 7, 2022 | 6411-41-001 | FLEXIBLE PAVEMENT STRUCTURE REPAIRBexar · San Antonio | 4 of 5 | $1,738,488 | $1,289,459TEXAS MATERIALS GROUP, INC. | +34.8% |
| Jul 29, 2022 | 6402-61-001 | HOT-MIX COLD-LAIDLavaca · Yoakum | 5 of 5 | $501,600 | $357,200BRAUNTEX MATERIALS, INC. | +40.4% |
| Jul 21, 2022 | 6406-38-001 | HOT-MIX COLD-LAIDBexar · San Antonio | 6 of 6 | $481,000 | $281,834VULCAN CONSTRUCTION MATERIA… | +70.7% |
| May 4, 2022 | 6374-41-001 | METAL BEAM GUARDFENCE UPGRADEGuadalupe · San Antonio | 4 of 4 | $1,423,016 | $711,961ABOVE ALL CONSTRUCTION | +99.9% |
| Apr 26, 2022 | 6401-38-001 | HOT MIXFayette · Yoakum | 3 of 5 | $358,530 | $296,000BRAUNTEX MATERIALS, INC. | +21.1% |
| Apr 19, 2022 | 6399-07-001 | HOT-MIX COLD-LAIDKarnes · Corpus Christi | 5 of 5 | $346,750 | $270,000BRAUNTEX MATERIALS, INC. | +28.4% |
| Apr 19, 2022 | 6399-08-001 | HOT-MIX COLD-LAIDLive Oak · Corpus Christi | 4 of 5 | $365,250 | $309,000BRAUNTEX MATERIALS, INC. | +18.2% |
| Apr 7, 2022 | 6386-75-001 | MILL, TOM INLAY, AND FULL DEPTH RECONSTRUCTIONTravis · Austin | 1 of 3 | $1,011,169 | $1,011,169 | Won |
| Apr 7, 2022 | 6386-73-001 | MILL AND INLAY, BONDING COURSE, FDR, AND TOMWilliamson · Austin | 1 of 3 | $7,085,849 | $7,085,849 | Won |
| Mar 17, 2022 | 6398-39-001 | HOT-MIX COLD-LAIDBexar · San Antonio | 5 of 5 | $437,600 | $272,400BRAUNTEX MATERIALS, INC. | +60.6% |
| Mar 17, 2022 | 6398-42-001 | DENSE GRADED HOT MIXComal · San Antonio | 4 of 5 | $373,388 | $279,025TEXAS MATERIALS GROUP, INC. | +33.8% |
| Mar 16, 2022 | 6397-45-001 | DENSE GRADED HOT MIXBexar · San Antonio | 3 of 3 | $394,350 | $332,800VULCAN CONSTRUCTION MATERIA… | +18.5% |
| Mar 16, 2022 | 6397-46-001 | DENSE GRADED HOT MIXBexar · San Antonio | 3 of 3 | $394,350 | $332,800VULCAN CONSTRUCTION MATERIA… | +18.5% |
| Mar 15, 2022 | 6398-54-001 | HOT MIXBell · Waco | 1 of 3 | $328,375 | $328,375 | Won |
| Mar 4, 2022 | 6394-34-001 | ASPHALT PAVEMENT REPAIRVictoria · Yoakum | 2 of 2 | $2,025,997 | $1,747,618HUNTER INDUSTRIES, LTD. | +15.9% |
| Mar 3, 2022 | 6394-32-001 | ASPHALT PAVEMENT REPAIRGonzales · Yoakum | 4 of 5 | $772,290 | $704,757HUNTER INDUSTRIES, LTD. | +9.6% |
| Feb 4, 2022 | 0521-02-042 | RESURFACE ROADWAYBexar · San Antonio | 5 of 6 | $9,667,503 | $6,683,654CLARK CONSTRUCTION OF TEXAS… | +44.6% |
| Jan 31, 2022 | 6396-24-001 | HOT-MIX COLD-LAID (MATERIALS ONLY)Lampasas · Brownwood | 4 of 4 | $92,200 | $66,955TEXAS MATERIALS GROUP, INC. | +37.7% |
| Jan 7, 2022 | 3417-02-024 | DEPTH REPAIR, UNDERSEAL & OVWilliamson · Austin | 1 of 2 | $1,965,252 | $1,965,252 | Won |
| Jan 7, 2022 | 0915-11-032 | STATE PARK IMPROVEMENTSKendall · San Antonio | 3 of 3 | $1,001,364 | $723,891LCR TOTAL TRANSPORT LLC | +38.3% |
| Jan 7, 2022 | 0015-09-203 | PREVENTIVE MAINTENANCEWilliamson · Austin | 2 of 2 | $428,388 | $399,183TEXAS MATERIALS GROUP, INC. | +7.3% |
| Jan 6, 2022 | 0530-01-008 | REHABILITATE EXISTING ROADWAYBastrop · Austin | 1 of 3 | $547,399 | $547,399 | Won |
| Dec 2, 2021 | 0535-08-089 | SURFACING/ROADWAY RESTORATIONColorado · Yoakum | 3 of 4 | $5,007,823 | $4,831,460HUNTER INDUSTRIES, LTD. | +3.7% |
| Dec 2, 2021 | 0265-10-032 | PREVENTIVE MAINTENANCEBastrop · Austin | 3 of 3 | $1,238,485 | $1,115,938TEXAS MATERIALS GROUP, INC. | +11.0% |
| Dec 1, 2021 | 0071-03-042 | RESURFACE ROADWAYMason · Austin | 2 of 5 | $4,335,226 | $3,962,336TEXAS MATERIALS GROUP, INC. | +9.4% |
| Dec 1, 2021 | 0143-08-099 | SURFACING/ROADWAY RESTORATIONDe Witt · Yoakum | 4 of 4 | $2,137,763 | $1,692,979HUNTER INDUSTRIES, LTD. | +26.3% |
| Dec 1, 2021 | 1149-01-030 | HIGHWAY IMPROVEMENTTravis · Austin | 1 of 4 | $1,170,307 | $1,170,307 | Won |
| Nov 23, 2021 | 6391-80-001 | HOT-MIX COLD-LAIDBexar · San Antonio | 3 of 4 | $328,850 | $298,000TEXAS MATERIALS GROUP, INC. | +10.4% |
| Nov 3, 2021 | 0252-01-079 | PREVENTIVE MAINTENANCEBurnet · Austin | 2 of 4 | $5,680,605 | $5,323,846TEXAS MATERIALS GROUP, INC. | +6.7% |
| Nov 3, 2021 | 6383-67-001 | LEVEL UP, FULL DEPTH REPAIR, AND SEAL COATCaldwell · Austin | 4 of 4 | $2,078,151 | $1,830,718TEXAS MATERIALS GROUP, INC. | +13.5% |
| Nov 3, 2021 | 6373-27-001 | MILL, SEAL, AND OVERLAYTravis · Austin | 1 of 3 | $2,526,954 | $2,526,954 | Won |
| Nov 3, 2021 | 0291-01-052 | SURFACING/ROADWAY RESTORATIONGillespie · Austin | 2 of 3 | $1,044,529 | $920,831TEXAS MATERIALS GROUP, INC. | +13.4% |
| Nov 3, 2021 | 0089-07-159 | SURFACING/ROADWAY RESTORATIONWharton · Yoakum | 3 of 4 | $9,108,602 | $8,528,161JAMES CONSTRUCTION GROUP, L… | +6.8% |
| Oct 20, 2021 | 6391-04-001 | DENSE GRADED HOT MIXBexar · San Antonio | 3 of 4 | $322,400 | $261,800TEXAS MATERIALS GROUP, INC. | +23.1% |
| Oct 20, 2021 | 6391-05-001 | DENSE GRADED HOT MIXBexar · San Antonio | 3 of 4 | $322,400 | $261,800TEXAS MATERIALS GROUP, INC. | +23.1% |
| Oct 20, 2021 | 6391-06-001 | ENSE GRADED HOT MIXComal · San Antonio | 2 of 3 | $341,600 | $314,245COLORADO MATERIALS, LTD. | +8.7% |
| Oct 20, 2021 | 6391-07-001 | DENSE GRADED HOT MIXComal · San Antonio | 1 of 3 | $323,850 | $323,850 | Won |
| Oct 19, 2021 | 6390-40-001 | HOT MIXKarnes · Corpus Christi | 3 of 3 | $295,100 | $258,760COLORADO MATERIALS, LTD. | +14.0% |
| Oct 8, 2021 | 0571-02-037 | RESURFACE ROADWAYCaldwell · Austin | 1 of 4 | $4,566,557 | $4,566,557 | Won |
| Oct 8, 2021 | 6383-60-001 | MATERIAL ONLY - HOT MIX COLD-LAID ASPHALT CONCRETEBastrop · Austin | 2 of 3 | $1,446,985 | $1,441,215TEXAS MATERIALS GROUP, INC. | +0.4% |
| Oct 8, 2021 | 6383-61-001 | MATERIAL ONLY - HOT-MIX COLD-LAID ASPHALT CONCRETEBlanco · Austin | 2 of 4 | $1,232,675 | $1,150,625TEXAS MATERIALS GROUP, INC. | +7.1% |
| Oct 8, 2021 | 6385-42-001 | SPOT BASE REPAIRKerr · San Antonio | 2 of 3 | $1,180,185 | $1,092,062TEXAS MATERIALS GROUP, INC. | +8.1% |
| Oct 7, 2021 | 0265-04-069 | PREVENTIVE MAINTENANCEBastrop · Austin | 2 of 4 | $2,119,600 | $1,972,087TEXAS MATERIALS GROUP, INC. | +7.5% |
| Oct 7, 2021 | 6386-31-001 | MILL AND INLAYBrown · Brownwood | 2 of 5 | $721,480 | $576,345FOUTSCO PAVING COMPANY, LLC | +25.2% |
| Oct 7, 2021 | 6377-63-001 | MILL AND INLAYEastland · Brownwood | 5 of 6 | $1,658,053 | $1,442,403FOUTSCO PAVING COMPANY, LLC | +15.0% |
| Sep 2, 2021 | 0149-04-018 | RESURFACE ROADWAYMason · Austin | 1 of 3 | $1,661,834 | $1,661,834 | Won |
| Sep 2, 2021 | 6385-41-001 | SPOT BASE REPAIRMedina · San Antonio | 5 of 6 | $2,397,542 | $1,820,224CLARK CONSTRUCTION OF TEXAS… | +31.7% |
| Sep 2, 2021 | 6385-43-001 | SPOT BASE REPAIRComal · San Antonio | 2 of 6 | $2,146,589 | $1,943,944CLARK CONSTRUCTION OF TEXAS… | +10.4% |
| Sep 2, 2021 | 6387-67-001 | HOT-MIX COLD-LAIDBell · Waco | 3 of 3 | $360,688 | $323,000KNIFE RIVER CORPORATION - S… | +11.7% |
| Sep 1, 2021 | 6385-40-001 | SPOT BASE REPAIRBexar · San Antonio | 6 of 6 | $3,498,679 | $1,998,721TEXAS MATERIALS GROUP, INC. | +75.0% |
| Aug 5, 2021 | 0472-01-044 | PREVENTIVE MAINTENANCEBastrop · Austin | 4 of 4 | $10,856,419 | $8,458,636BIG CREEK CONSTRUCTION, LTD. | +28.3% |
| Aug 5, 2021 | 0015-13-419 | PREVENTIVE MAINTENANCETravis · Austin | 3 of 3 | $10,721,437 | $8,677,684TEXAS MATERIALS GROUP, INC. | +23.6% |
| Jul 1, 2021 | 0127-02-148 | RESURFACE ROADWAYEastland · Brownwood | 8 of 9 | $1,767,989 | $1,372,072BIG CREEK CONSTRUCTION, LTD. | +28.9% |
| Jun 16, 2021 | 6377-95-001 | ASPHALTTravis · Austin | 1 of 2 | $129,850 | $129,850 | Won |
| Jun 14, 2021 | 6381-89-001 | HOT-MIX COLD-LAIDGonzales · Yoakum | 1 of 5 | $270,600 | $270,600 | Won |
| Jun 14, 2021 | 6381-87-001 | HOT-MIX COLD-LAIDColorado · Yoakum | 2 of 4 | $299,200 | $294,800QUALITY HOT MIX, INC. | +1.5% |
| Jun 9, 2021 | 6381-88-001 | HOT-MIX COLD-LAIDJackson · Yoakum | 2 of 4 | $321,200 | $316,800QUALITY HOT MIX, INC. | +1.4% |
| Jun 8, 2021 | 6381-97-001 | HOT-MIX COLD-LAIDAustin · Yoakum | 2 of 4 | $306,600 | $285,600QUALITY HOT MIX, INC. | +7.4% |
| Jun 8, 2021 | 6381-93-001 | HOT-MIX COLD-LAIDCalhoun · Yoakum | 2 of 4 | $323,400 | $294,000QUALITY HOT MIX, INC. | +10.0% |
| Jun 8, 2021 | 6381-90-001 | HOT-MIX COLD-LAIDLavaca · Yoakum | 3 of 5 | $299,200 | $294,800BRAUNTEX MATERIALS, INC. | +1.5% |
| Jun 8, 2021 | 6381-92-001 | HOT-MIX COLD-LAIDFayette · Yoakum | 2 of 6 | $299,200 | $290,400QUALITY HOT MIX, INC. | +3.0% |
| Jun 8, 2021 | 6381-95-001 | HOT-MIX COLD-LAIDWharton · Yoakum | 2 of 4 | $338,800 | $297,000QUALITY HOT MIX, INC. | +14.1% |
| Jun 8, 2021 | 6381-96-001 | HOT-MIX COLD-LAIDMatagorda · Yoakum | 2 of 4 | $340,200 | $302,400QUALITY HOT MIX, INC. | +12.5% |
| Jun 8, 2021 | 6381-94-001 | HOT-MIX COLD-LAIDVictoria · Yoakum | 2 of 4 | $306,600 | $285,600QUALITY HOT MIX, INC. | +7.4% |
| Jun 7, 2021 | 6381-79-001 | HOT MIXDe Witt · Yoakum | 5 of 5 | $324,000 | $265,500BRAUNTEX MATERIALS, INC. | +22.0% |
| Jun 7, 2021 | 6381-81-001 | HOT MIXGonzales · Yoakum | 3 of 5 | $294,400 | $253,000CENTURY ASPHALT, LTD. | +16.4% |
Active prime contracts 10
| CCSJ | Where | Work | Contract | Complete | Report |
|---|---|---|---|---|---|
| 0157-04-058Let Nov 4, 2026 | HaskellAbilene · US 277 | $6,732,215 | |||
| 0337-03-020Let Sep 2, 2026 | WilliamsonAustin · FM 1331 | $2,174,856 | |||
| 1776-02-021Let Mar 4, 2026 | HaysAustin · FM 2001 | OVERLAY | $1,851,224 | 13% | |
| 0150-05-051Let Feb 4, 2026 | BurnetAustin · SH 29 | MAINTENANCE | $2,963,449 | 103% | |
| 6482-90-001Let Oct 9, 2025 | HaysAustin · SH0021 | MATERIALS-ONLY CONTRACT | $2,059,249 | 120% | |
| 0073-10-053Let Sep 5, 2025 | AtascosaSan Antonio · IH 37 | RESTORATION | $17,668,156 | 101% | |
| 0805-03-022Let Sep 4, 2025 | CaldwellAustin · FM 713 | SEAL COAT | $2,297,164 | 121% | |
| 6482-35-001Let Aug 7, 2025 | TravisAustin · SH0130 | MAINTENANCE | $11,632,301 | 90% | |
| 6481-97-001Let Mar 27, 2025 | San SabaBrownwood · US0190 | MAINTENANCE | $208,000 | 13% | |
| 6477-81-001Let Jan 14, 2025 | MedinaSan Antonio · US0090 | MATERIALS-ONLY CONTRACT | $816,080 | 168% |
Subcontracts on active jobs 52
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 1201-02-026Let Feb 5, 2026 | Rucoba & Maya Construction, LLC | WilliamsonAustin | REHABILITATION OF EXISTING ROAD | 8.04% | $304,278 |
| 1755-03-010Let Feb 5, 2026 | AARON CONCRETE CONTRACTORS, LLC | WilliamsonAustin | HAZARD ELIMINATION & SAFETY | 32.93% | $983,324 |
| 0178-02-090Let Jan 6, 2026 | DURWOOD GREENE CONSTRUCTION CO. | BrazoriaHouston | OVERLAY | 8.34% | $767,585 |
| 0906-00-256Let Dec 3, 2025 | SCOUT 5 CONSTRUCTION LLC | EctorOdessa | MISCELLANEOUS CONSTRUCTION | 33.61% | $2,115,298 |
| 0348-04-055Let Dec 2, 2025 | RELMCO, INC. | KarnesCorpus Christi | MISCELLANEOUS CONSTRUCTION | 9.89% | $1,188,983 |
| 0913-29-061Let Nov 6, 2025 | CEKRA INC. | LavacaYoakum | BRIDGE WIDENING OR REHABILITATION | 2.01% | $15,395 |
| 0113-13-168Let Nov 6, 2025 | WEBBER, LLC | TravisAustin | MISCELLANEOUS CONSTRUCTION | 6.2% | $4,303,497 |
| 0913-27-092Let Nov 6, 2025 | PRESIDIO CONTRACTING, LLC | VictoriaYoakum | BRIDGE REPLACEMENT | 2.98% | $86,691 |
| 0334-01-048Let Nov 5, 2025 | POSILLICO CIVIL, INC. | WilliamsonAustin | WIDEN NON-FREEWAY | 22.92% | $1,049,106 |
| 0273-04-045Let Nov 5, 2025 | JOE BLAND CONSTRUCTION LLC | WilliamsonAustin | REHABILITATION OF EXISTING ROAD | 41.91% | $6,236,909 |
| 0034-01-130Let Oct 8, 2025 | JAMES CONSTRUCTION GROUP, LLC | TaylorAbilene | MISCELLANEOUS CONSTRUCTION | 15.79% | $11,688,376 |
| 0916-35-253Let Sep 4, 2025 | PRESIDIO CONTRACTING, LLC | NuecesCorpus Christi | BRIDGE REPLACEMENT | 4.53% | $64,753 |
| 0323-01-028Let Aug 8, 2025 | C. E. BARKER, LTD. | BastropAustin | MISCELLANEOUS CONSTRUCTION | 14.19% | $2,765,096 |
| 0211-07-046Let Aug 7, 2025 | ACME BRIDGE COMPANY, INC. | LeeAustin | BRIDGE REPLACEMENT | 3.58% | $483,715 |
| 0913-29-062Let Jul 2, 2025 | 3LW CIVIL LLC | LavacaYoakum | BRIDGE REPLACEMENT | 4.7% | $73,307 |
| 0267-02-043Let Jul 1, 2025 | ACME BRIDGE COMPANY, INC. | FayetteYoakum | BRIDGE REPLACEMENT | 10.71% | $466,205 |
| 0024-07-059Let Jun 5, 2025 | JORDAN FOSTER CONSTRUCTION, LLC | BexarSan Antonio | CONVERT NON-FREEWAY TO FREEWAY | 16.37% | $20,436,001 |
| 0909-36-198Let Jun 4, 2025 | TTG UTILITIES, INC. | CoryellWaco | REHABILITATION OF EXISTING ROAD | 12.11% | $700,809 |
| 1149-02-033Let Jun 4, 2025 | DAN WILLIAMS COMPANY | BastropAustin | UPGRADE TO STANDARDS FREEWAY | 30.75% | $2,372,909 |
| 0403-01-050Let May 2, 2025 | SKYLINE BRIDGE LLC | San JacintoLufkin | BRIDGE REPLACEMENT | 12.29% | $534,539 |
| 0398-01-045Let Mar 5, 2025 | ORION CONSTRUCTION, LLC | BosqueWaco | BRIDGE REPLACEMENT | 4.87% | $326,055 |
| 0521-04-293Let Mar 5, 2025 | E-Z BEL CONSTRUCTION, LLC | BexarSan Antonio | REHABILITATION OF EXISTING ROAD | 2.54% | $75,218 |
| 0258-09-147Let Jan 8, 2025 | ORION CONSTRUCTION, LLC | MclennanWaco | BRIDGE REPLACEMENT | 1.34% | $1,520,743 |
| 0151-10-001Let Jan 7, 2025 | WEBBER, LLC | WilliamsonAustin | MISCELLANEOUS CONSTRUCTION | 5.04% | $7,119,979 |
| 0015-13-433Let Dec 4, 2024 | SAK CONSTRUCTION, LLC | TravisAustin | MISCELLANEOUS CONSTRUCTION | 0% | $0 |
| 0913-22-055Let Dec 4, 2024 | TREVWAY, INC. | GonzalesYoakum | BRIDGE REPLACEMENT | 2.09% | $67,397 |
| 0923-08-030Let Oct 1, 2024 | SKYLINE BRIDGE LLC | ColemanBrownwood | BRIDGE REPLACEMENT | 9.36% | $167,404 |
| 0015-13-428Let Sep 6, 2024 | BALFOUR BEATTY INFRASTRUCTURE, INC. | TravisAustin | WIDEN FREEWAY | 2.06% | $15,523,221 |
| 6467-47-001Let Sep 5, 2024 | GARRET SHIELDS INFRASTRUCTURE | MclennanWaco | MAINTENANCE | 2.41% | $41,668 |
| 0521-06-155Let Aug 2, 2024 | ZACHRY CONSTRUCTION CORPORATION | BexarSan Antonio | WIDEN FREEWAY | 5.33% | $4,512,045 |
| 2452-03-087Let Jun 6, 2024 | WEBBER, LLC | BexarSan Antonio | WIDEN FREEWAY | 14.23% | $22,235,363 |
| 0915-00-270Let Jun 6, 2024 | RELMCO, INC. | BexarSan Antonio | BRIDGE WIDENING OR REHABILITATION | 4.5% | $430,299 |
| 0027-01-042Let Jun 5, 2024 | CEKRA INC. | ColoradoYoakum | BRIDGE WIDENING OR REHABILITATION | 1.65% | $125,233 |
| 0005-14-094Let Mar 6, 2024 | SUNDT CONSTRUCTION, INC. | MidlandOdessa | WIDEN FREEWAY | 10.5% | $17,361,789 |
| 0320-06-008Let Feb 2, 2024 | JAMES CONSTRUCTION GROUP, LLC | BellWaco | WIDEN NON-FREEWAY | 3.8% | $2,102,832 |
| 3212-05-013Let Feb 2, 2024 | DAN WILLIAMS COMPANY | ComalSan Antonio | BRIDGE REPLACEMENT | 10% | $1,270,438 |
| 0914-00-524Let Feb 2, 2024 | ROY JORGENSEN ASSOCIATES, INC. | TravisAustin | REHABILITATION OF EXISTING ROAD | 4.66% | $130,972 |
| 0005-13-064Let Nov 2, 2023 | SUNDT CONSTRUCTION, INC. | EctorOdessa | WIDEN FREEWAY | 11.02% | $26,645,162 |
| 2452-02-130Let Oct 6, 2023 | PULICE CONSTRUCTION, INC. | BexarSan Antonio | WIDEN FREEWAY | 11.3% | $21,919,893 |
| 0271-01-066Let Jun 28, 2023 | WEBBER, LLC | ColoradoYoakum | WIDEN FREEWAY | 0% | $0 |
| 0004-02-063Let Jun 27, 2023 | JAMES CONSTRUCTION GROUP, LLC | WardOdessa | BRIDGE REPLACEMENT | 10.67% | $3,122,008 |
| 0535-01-074Let Jun 1, 2023 | WEBBER, LLC | GuadalupeSan Antonio | WIDEN FREEWAY | 12.09% | $30,716,942 |
| 0251-06-036Let May 5, 2023 | JAY MILLS CONTRACTING, INCORPORATED | LampasasBrownwood | WIDEN NON-FREEWAY | 26.78% | $6,953,623 |
| 1433-02-044Let May 4, 2023 | HARPER BROTHERS CONSTRUCTION LLC | ComalSan Antonio | WIDEN NON-FREEWAY | 13.24% | $6,421,915 |
| 0215-01-044Let Jun 30, 2022 | WEBBER, LLC | ComalSan Antonio | WIDEN NON-FREEWAY | 19.19% | $11,809,764 |
| 1799-02-017Let Jun 2, 2022 | ATLANTIC SPECIALTY INSURANCE COMPANY | DimmitLaredo | REHABILITATION OF EXISTING ROAD | 0% | $0 |
| 0015-13-077Let May 5, 2022 | FLUOR HEAVY CIVIL, LLC | TravisAustin | WIDEN FREEWAY | 12.15% | $73,859,511 |
| 0113-13-166Let Dec 1, 2021 | COPASA INC | TravisAustin | INTERCHANGE (NEW OR RECONSTRUCTED) | 5.62% | $4,554,718 |
| 0025-03-097Let Nov 3, 2021 | WEBBER, LLC | GuadalupeSan Antonio | WIDEN FREEWAY | 15.65% | $21,576,273 |
| 0025-02-215Let Jul 9, 2020 | ZACHRY CONSTRUCTION CORPORATION | BexarSan Antonio | WIDEN FREEWAY | 10.01% | $18,998,514 |
| 0113-08-060Let Apr 30, 2020 | COLORADO RIVER CONSTRUCTORS, OHP | TravisAustin | REHABILITATION OF EXISTING ROAD | 3.61% | $24,601,564 |
| 0185-01-030Let Nov 6, 2019 | CONTINENTAL INSURANCE COMPANY (THE) | BellWaco | WIDEN NON-FREEWAY | 0% | $0 |