MILL AND INLAY
- Let date
- Thursday, October 7, 2021
- CCSJ
- 6386-31-001
- District
- Brownwood
- County
- Brown
- Highway
- US 67
- Limits
- VARIOUS to VARIOUS
- Classification
- Maintenance
- Project number
- RMC - 638631001
- Working days
- 22
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $426,254 | ||
| 1 | FOUTSCO PAVING COMPANY, LLC Low bidder | $576,345 | +35.2% | |
| 2 | LONE STAR PAVING COMPANY | $721,480 | +69.3% | +25.2% |
| 3 | PEACHTREE CONSTRUCTION, LTD. | $776,154 | +82.1% | +34.7% |
| 4 | RK HALL, LLC | $839,943 | +97.1% | +45.7% |
| 5 | TEXAS MATERIALS GROUP, INC. | $896,603 | +110.3% | +55.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 FOUTSCO PAVING … | #2 LONE STAR PAVIN… | #3 PEACHTREE CONST… | #4 RK HALL, LLC | #5 TEXAS MATERIALS… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 354-6011 | PLAN & TEXT ASPH CONC PAV(0" TO 8") | 11,421 | SY | $3.89 | $7.00 | $7.25 | $8.25 | $13.05 | $11.80 |
| 2 | 500-6001 | MOBILIZATION | 1 | LS | $39,983.87 | $1,000.00 | $50,000.00 | $40,000.00 | $105,542.62 | $81,200.00 |
| 3 | 500-6033 | MOBILIZATION (CALLOUT) | 1 | EA | $2,000.00 | $1,000.00 | $25,000.00 | $16,000.00 | $32,520.21 | $25,100.00 |
| 4 | 662-6109 | WK ZN PAV MRK SHT TERM (TAB)TY W | 1,071 | EA | $1.34 | $1.00 | $1.00 | $2.00 | $4.35 | $0.9000 |
| 5 | 662-6111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 857 | EA | $0.8600 | $1.00 | $1.00 | $2.00 | $4.35 | $0.9000 |
| 6 | 3076-6001 | D-GR HMA TY-B PG64-22 | 5,025 | TON | $66.81 | $98.00 | $110.00 | $123.00 | $106.79 | $128.00 |
| 7 | 6185-6002 | TMA (STATIONARY) | 20 | DAY | $97.50 | $1.00 | $450.00 | $200.00 | $391.48 | $530.00 |