SPOT BASE REPAIR
- Let date
- Friday, January 6, 2023
- CCSJ
- 6428-74-001
- District
- Yoakum
- County
- Gonzales
- Highway
- UA 90
- Limits
- VARIOUS to VARIOUS
- Classification
- Maintenance
- Project number
- RMC - 642874001
- Working days
- 365
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $987,500 | ||
| 1 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. Low bidder | $985,800 | -0.2% | |
| 2 | HUNTER INDUSTRIES, LTD. | $1,028,902 | +4.2% | +4.4% |
| 3 | LONE STAR PAVING COMPANY | $1,569,500 | +58.9% | +59.2% |
| 4 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | $2,659,021 | +169.3% | +169.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CORNERSTONE PAV… | #2 HUNTER INDUSTRI… | #3 LONE STAR PAVIN… | #4 SALINAS CONSTRU… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 351-6002 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 3,500 | SY | $55.00 | $70.05 | $50.29 | $99.00 | |
| 2 | 351-6004 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 5,000 | SY | $70.00 | $85.85 | $69.20 | $115.00 | |
| 3 | 351-6008 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 2,500 | SY | $110.00 | $117.10 | $100.29 | $148.00 | |
| 4 | 500-6033 | MOBILIZATION (CALLOUT) | 3 | EA | $25,000.00 | $2,500.00 | $50,778.88 | $15,000.00 | |
| 5 | 6185-6002 | TMA (STATIONARY) | 60 | DAY | $200.00 | $150.00 | $407.16 | $550.00 | |
| 6 | 7022-6001 | 1 LANE CLOSURE-2 LANE ROAD, NO SHLDR | 25 | EA | $1,000.00 | $25.00 | $872.48 | $2,500.00 | |
| 7 | 7022-6002 | 1 LANE CLOSURE-2 LANE ROAD, PAVED SHLDR | 35 | EA | $1,000.00 | $25.00 | $988.81 | $2,500.00 | |
| 8 | 7022-6003 | 1 LANE CLOSURE-4 LANE ROAD | 15 | EA | $1,200.00 | $25.00 | $1,105.14 | $2,000.00 | |
| 9 | 7022-6016 | WORK AREA ON SHOULDER | 10 | EA | $500.00 | $25.00 | $639.82 | $2,000.00 |