FY25 Robertson HMA - 07
- Let date
- Wednesday, July 9, 2025
- CCSJ
- 6486-09-001
- District
- Bryan
- County
- Robertson
- Highway
- SH0006
- Limits
- Various to Various
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00216197
- Working days
- 180
- DBE goal
- 0%
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $435,000 | ||
| 1 | BIG CREEK CONSTRUCTION, LTD. Low bidder | $411,000 | -5.5% | |
| 2 | BRAZOS PAVING, INC. | $423,000 | -2.8% | +2.9% |
| 3 | TEXAS MATERIALS GROUP, INC. | $502,940 | +15.6% | +22.4% |
| 4 | LONE STAR PAVING COMPANY | $522,750 | +20.2% | +27.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BIG CREEK CONST… | #2 BRAZOS PAVING, … | #3 TEXAS MATERIALS… | #4 LONE STAR PAVIN… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 8011-7055 | D-GR HMA TY D PG 64-22 (PICKUP) | 500 | TON | $85.00 | $69.00 | $83.00 | $81.67 | $82.00 |
| 2 | 8011-7056 | D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 1,500 | TON | $100.00 | $97.00 | $95.00 | $113.72 | $114.50 |
| 3 | 8011-7091 | D-GR HMA TY F PG 64-22 (PICKUP) | 500 | TON | $85.00 | $70.00 | $86.00 | $90.97 | $98.00 |
| 4 | 8011-7092 | D-GR HMA TY F PG 64-22 (DEL) SITE 1 | 2,000 | TON | $100.00 | $98.00 | $98.00 | $123.02 | $130.50 |