Win Price

Know the low bid before bid day Sign up free

Win Price · Texas

Know the low bid before bid day.

On a TxDOT letting the lowest bid wins. Win Price predicts that low bid for every advertised job, from thousands of past Texas lettings, the plan holders on the job and how each of them bids. Put in your number and see your odds of coming in lowest.

88%typical accuracy on the low bidHalf of our predictions land within 12.2% of the real low bid. The engineer's estimate: 13.4%.
41%within 10% of the low bidThe engineer's estimate: 40%.
47%inside our likely rangeThe middle-half range is built to catch the low bid half the time.
2,041Texas lettings testedEach predicted only from jobs let before it. How we score this

1. The low bid

The most likely low bid and the range it should land in, against the engineer's estimate, before anyone opens a bid.

2. The field

Which plan holders are likely to turn in a bid, how many to expect, and how far under the estimate each one usually goes.

3. Your odds

Enter your total or upload your priced items. See your chance of being lowest, and the lines that cost you the job.

Upcoming TxDOT jobs

LetsCCSJWhereWorkEstimatePredicted lowLikely rangeBidders
Nov 29, 2026 6513-67-001 ZavalaLaredo · US0083 Routine Maintenance Project - Sealed $296,881 $266,565-10.2% vs est. $230,793 – $296,881 3.8 Check my bid
Dec 1, 2026 0092-03-053 EllisDallas · FM 664, IH 45 Interchange (New or Reconstructed) $116,656,531 $108,646,063-6.9% vs est. $99,567,726 – $116,059,716 10.017 plan holders Check my bid
Dec 1, 2026 6482-46-001 TarrantFort Worth · IH0035W Routine Maintenance Project - Sealed $27,875,745 $24,216,843-13.1% vs est. $21,884,870 – $26,906,156 3.48 plan holders Check my bid
Dec 1, 2026 0354-04-043 WinklerOdessa · SH 115 Super-2 Highway $25,229,401 $21,638,244-14.2% vs est. $19,528,605 – $23,880,125 4.17 plan holders Check my bid
Dec 1, 2026 0528-01-113 HidalgoPharr · SH 107 Widen Non-Freeway $24,134,502 $20,938,672-13.2% vs est. $18,811,518 – $23,058,066 3.66 plan holders Check my bid
Dec 1, 2026 0095-07-062 Anderson, Cherokee, Gregg, Henderson, Rusk, Smith, Van Zandt, WoodTyler · FM 16, FM 17, FM 1845, FM 2494, FM 2495, FM 2661, FM 314, FM 316, FM 317, FM 321, FM 344, FM 515, FM 782, FM 837, FM 840, FM 848, FM 855, FS 782, RM 3054, SH 154, SH 21, SH 294, SH 322, SH 334, SH 42, SH 64, SL 62, SS 364, US 271, US 80, Various Seal Coat $23,738,912 $21,264,805-10.4% vs est. $18,668,588 – $23,809,806 1.83 plan holders Check my bid
Dec 1, 2026 0035-01-036 Concho, RunnelsSan Angelo · FM 2134, US 83 Overlay $17,029,710 $14,736,484-13.5% vs est. $13,273,907 – $16,421,018 3.66 plan holders Check my bid
Dec 1, 2026 3524-01-008 HoodFort Worth · SL 567 Rehabilitation of Existing Road $16,526,560 $14,565,968-11.9% vs est. $12,720,527 – $16,060,133 3.66 plan holders Check my bid
Dec 1, 2026 0405-01-027 Concho, Glasscock, SterlingSan Angelo · SH 158, US 87 Seal Coat $13,888,098 $12,474,728-10.2% vs est. $10,962,419 – $13,697,167 1.83 plan holders Check my bid
Dec 1, 2026 1598-01-023 Erath, Hood, Jack, Johnson, Palo Pinto, Parker, Tarrant, WiseFort Worth · FM 167, FM 1810, FM 2265, FM 2303, FM 2331, FM 3450, FM 4, FM 51, FM 730, RM 2871, SH 144, SH 16, SH 171, SH 59, Various Seal Coat $13,619,545 $12,278,592-9.8% vs est. $10,639,771 – $13,447,420 2.34 plan holders Check my bid
Dec 1, 2026 0005-08-107 Borden, Fisher, Howard, Jones, Kent, Mitchell, Nolan, Scurry, Shackelford, TaylorAbilene · BI 20N, BS 208B, BU 84J, FM 1170, FM 1605, FM 2833, FM 3326, FM 3525, FM 669, FM 700, FM 707, IH 20, SH 163, SH 208, SH 70, US 180, US 84 Seal Coat $12,574,772 $11,430,691-9.1% vs est. $10,066,485 – $12,575,447 1.83 plan holders Check my bid
Dec 1, 2026 0693-03-046 ScurryAbilene · SH 350 Overlay $11,054,519 $9,784,220-11.5% vs est. $8,694,489 – $10,813,379 4.28 plan holders Check my bid
Dec 1, 2026 0918-47-460 DallasDallas · W PLEASANT RUN RD, WESTMORELAND Bridge Replacement $8,607,909 $7,442,344-13.5% vs est. $6,645,299 – $8,094,035 9.817 plan holders Check my bid
Dec 1, 2026 0113-13-193 TravisAustin · SL 275, SL 360 Overlay $8,182,630 $7,217,150-11.8% vs est. $6,478,482 – $8,003,744 4.17 plan holders Check my bid
Dec 1, 2026 0252-01-084 BurnetAustin · US 281 Intersection & Operational Imprv $6,953,263 $6,165,742-11.3% vs est. $5,562,077 – $6,766,846 6.010 plan holders Check my bid
Dec 1, 2026 0893-04-015 Angelina, ShelbyLufkin · FM 2026, FM 328, Various Safety Improvement Projects $4,851,340 $4,387,279-9.6% vs est. $3,976,457 – $4,802,649 3.05 plan holders Check my bid
Dec 1, 2026 2635-03-031 Potter, RandallAmarillo · FM 2590 Overlay $4,418,881 $4,032,661-8.7% vs est. $3,626,623 – $4,439,289 1.23 plan holders Check my bid
Dec 1, 2026 0913-00-140 De WittYoakum · Various Bridge Maintenance $4,401,018 $3,870,142-12.1% vs est. $3,490,467 – $4,260,904 5.910 plan holders Check my bid
Dec 1, 2026 0924-00-133 El PasoEl Paso · Various Traffic Control Devices $3,554,027 $3,179,045-10.6% vs est. $2,870,445 – $3,543,987 2.44 plan holders Check my bid
Dec 1, 2026 0627-04-070 NewtonBeaumont · FM 1416 Overlay $3,184,851 $2,895,426-9.1% vs est. $2,621,681 – $3,189,319 1.83 plan holders Check my bid
Dec 1, 2026 0916-36-024 KarnesCorpus Christi · COUNTY ROAD 326 Bridge Replacement $3,101,274 $2,701,743-12.9% vs est. $2,381,334 – $2,973,087 6.211 plan holders Check my bid
Dec 1, 2026 6508-44-001 ChildressChildress · US0287 Material Maintenance Project $2,591,200 $2,366,014-8.7% vs est. $2,130,859 – $2,589,646 1.83 plan holders Check my bid
Dec 1, 2026 1718-05-021 AndrewsOdessa · FM 1788 Safety Improvement Projects $2,153,994 $1,918,010-11.0% vs est. $1,722,954 – $2,132,497 3.05 plan holders Check my bid
Dec 1, 2026 0905-00-136 LubbockLubbock · Various Bridge Maintenance $1,934,816 $1,628,618-15.8% vs est. $1,431,210 – $1,802,636 9.015 plan holders Check my bid
Dec 1, 2026 0923-00-085 EastlandBrownwood · Various Traffic Control Devices $1,889,401 $1,720,829-8.9% vs est. $1,516,727 – $1,894,124 1.83 plan holders Check my bid
Dec 1, 2026 6511-43-001 McLennanWaco · SH0006 Material Maintenance Project $1,886,091 $1,684,492-10.7% vs est. $1,514,127 – $1,840,114 3.67 plan holders Check my bid
Dec 1, 2026 1062-01-218 MontgomeryHouston · FM 1485 Overlay $1,271,319 $1,119,562-11.9% vs est. $973,362 – $1,243,448 4.17 plan holders Check my bid
Dec 1, 2026 6504-82-001 McLennanWaco · SH0006 Routine Maintenance Project - Sealed $1,049,092 $887,085-15.4% vs est. $771,049 – $1,002,442 6.010 plan holders Check my bid
Dec 1, 2026 6505-42-001 GreggTyler · SL0281 Material Maintenance Project $1,020,300 $937,738-8.1% vs est. $831,241 – $1,019,629 3.26 plan holders Check my bid
Dec 1, 2026 0917-31-041 MadisonBryan · Various Safety Improvement Projects $126,512 $114,613-9.4% vs est. $101,948 – $126,512 4.910 plan holders Check my bid
Dec 2, 2026 0070-01-056 Coke, Concho, Edwards, Glasscock, Kimble, Menard, Reagan, Real, Runnels, Schleicher, Tom GreenSan Angelo · FM 1223, FM 1678, FM 1874, FM 2406, FM 2742, FM 2873, FM 3463, RM 1555, RM 2401, RM 335, SH 158, SH 208, SH 41, SL 110, US 190, US 377 Seal Coat $9,464,478 $8,649,737-8.6% vs est. $7,740,584 – $9,416,928 1.83 plan holders Check my bid
Dec 2, 2026 6512-67-001 HidalgoPharr · IH0002 Material Maintenance Project - Sealed $9,038,132 $8,209,744-9.2% vs est. $7,366,761 – $8,931,649 1.83 plan holders Check my bid
Dec 2, 2026 0042-01-032 Carson, PotterAmarillo · IH 40, SS 228, US 287 Safety Improvement Projects $7,782,909 $7,076,202-9.1% vs est. $6,349,092 – $7,744,260 2.44 plan holders Check my bid
Dec 2, 2026 1469-01-025 Hood, Johnson, ParkerFort Worth · FM 167, FM 1718, FM 5 Seal Coat $6,142,029 $5,414,483-11.8% vs est. $4,883,862 – $5,970,267 5.49 plan holders Check my bid
Dec 2, 2026 0048-04-111 EllisDallas · IH 35E Rehabilitation of Existing Road $6,007,682 $5,297,453-11.8% vs est. $4,865,016 – $5,805,517 5.310 plan holders Check my bid
Dec 2, 2026 0104-07-027 Brewster, PresidioEl Paso · US 385, US 67 Seal Coat $5,924,303 $5,488,464-7.4% vs est. $4,902,063 – $5,945,632 1.22 plan holders Check my bid
Dec 2, 2026 0028-03-119 Hardin, Liberty, NewtonBeaumont · SH 326, US 190, US 90 Bridge Maintenance $5,428,043 $4,563,168-15.9% vs est. $4,001,500 – $5,036,024 10.117 plan holders Check my bid
Dec 2, 2026 0905-06-129 LubbockLubbock · Various Rehabilitation of Existing Road $3,128,110 $2,733,437-12.6% vs est. $2,416,684 – $3,013,848 5.49 plan holders Check my bid
Dec 2, 2026 0366-01-084 HaysAustin · SH 123 Bridge Replacement $2,818,472 $2,374,380-15.8% vs est. $2,112,576 – $2,617,789 10.518 plan holders Check my bid
Dec 2, 2026 1743-01-012 HarrisHouston · FM 1876 Overlay $2,783,535 $2,437,506-12.4% vs est. $2,157,076 – $2,721,481 4.78 plan holders Check my bid
Dec 2, 2026 0011-06-050 Jones, ShackelfordAbilene · FM 1084, FM 1226, FM 576, US 180 Overlay $2,781,404 $2,447,057-12.0% vs est. $2,182,055 – $2,720,085 4.27 plan holders Check my bid
Dec 2, 2026 0500-04-145 Galveston, MontgomeryHouston · FM 1488, IH 45 Intersection & Operational Imprv $2,699,624 $2,272,825-15.8% vs est. $1,996,405 – $2,529,137 8.615 plan holders Check my bid
Dec 2, 2026 6510-95-001 PecosOdessa · IH0010 Routine Maintenance Project $2,486,888 $2,186,424-12.1% vs est. $1,965,674 – $2,437,179 4.17 plan holders Check my bid
Dec 2, 2026 0904-00-229 PotterAmarillo · Various Safety Improvement Projects $2,090,094 $1,887,704-9.7% vs est. $1,671,202 – $2,082,530 2.44 plan holders Check my bid
Dec 2, 2026 1127-05-024 EctorOdessa · FM 866 Safety Improvement Projects $2,084,737 $1,857,709-10.9% vs est. $1,667,407 – $2,067,217 3.05 plan holders Check my bid
Dec 2, 2026 0211-03-039 LeeAustin · US 77 Overlay $1,977,990 $1,740,477-12.0% vs est. $1,543,524 – $1,930,743 3.56 plan holders Check my bid
Dec 2, 2026 0914-00-513 TravisAustin · Various Overlay $1,909,738 $1,695,490-11.2% vs est. $1,514,562 – $1,882,604 2.75 plan holders Check my bid
Dec 2, 2026 0913-00-134 De WittYoakum · Various Traffic Control Devices $1,866,640 $1,660,217-11.1% vs est. $1,471,489 – $1,845,299 3.66 plan holders Check my bid
Dec 2, 2026 0923-00-086 BrownBrownwood · Various Traffic Control Devices $1,832,003 $1,670,024-8.8% vs est. $1,470,955 – $1,836,812 1.83 plan holders Check my bid
Dec 2, 2026 2850-01-020 WalkerBryan · FM 2821 Intersection & Operational Imprv $1,793,073 $1,560,888-12.9% vs est. $1,368,331 – $1,742,521 5.39 plan holders Check my bid
Dec 2, 2026 0911-28-062 HoustonLufkin · COUNTY ROAD 2065 Bridge Replacement $1,597,562 $1,367,225-14.4% vs est. $1,204,037 – $1,527,874 6.813 plan holders Check my bid
Dec 2, 2026 6508-52-001 TarrantFort Worth · IH0030 Routine Maintenance Project - Sealed $1,475,661 $1,224,347-17.0% vs est. $1,078,923 – $1,385,380 7.315 plan holders Check my bid
Dec 2, 2026 0002-02-065 El PasoEl Paso · FM 258, PEBBLE HILLS BLVD, SH 20, SHADOW MTN, US 62 Safety Improvement Projects $1,370,184 $1,203,617-12.2% vs est. $1,060,962 – $1,339,606 4.48 plan holders Check my bid
Dec 2, 2026 0156-07-115 WichitaWichita Falls · IH 44 Safety Improvement Projects $1,210,801 $1,062,475-12.3% vs est. $935,717 – $1,181,628 4.78 plan holders Check my bid
Dec 2, 2026 0016-08-053 BexarSan Antonio · SL 368 Pedestrian, Sidewalks & Curb Ramps $1,151,070 $959,106-16.7% vs est. $846,552 – $1,079,971 7.716 plan holders Check my bid
Dec 2, 2026 6511-12-001 Live OakCorpus Christi · US0281 Routine Maintenance Project - Sealed $1,019,175 $907,927-10.9% vs est. $800,790 – $1,008,755 3.05 plan holders Check my bid
Dec 2, 2026 0916-27-016 RefugioCorpus Christi · MULLENS BAYOU RD Bridge Replacement $882,212 $778,469-11.8% vs est. $688,375 – $858,715 4.48 plan holders Check my bid
Dec 2, 2026 0917-16-046 Freestone, LeonBryan · Various Safety Improvement Projects $184,986 $164,740-10.9% vs est. $146,173 – $182,004 5.410 plan holders Check my bid
Dec 3, 2026 6512-18-001 JeffersonBeaumont · US0069 Material Maintenance Project - Sealed $879,500 $842,930-4.2% vs est. $742,967 – $921,710 1.03 plan holders Check my bid
Dec 3, 2026 6512-22-001 OrangeBeaumont · FM0105 Material Maintenance Project - Sealed $729,900 $700,681-4.0% vs est. $620,659 – $769,242 1.02 plan holders Check my bid
Dec 3, 2026 6513-16-001 LibertyBeaumont · US0090 Material Maintenance Project - Sealed $688,500 $661,285-4.0% vs est. $587,039 – $726,128 1.02 plan holders Check my bid
Dec 3, 2026 6502-57-001 DentonDallas · IH0035 Routine Maintenance Project - Sealed $637,400 $555,724-12.8% vs est. $472,914 – $622,703 3.87 plan holders Check my bid
Dec 3, 2026 6507-34-001 EllisDallas · IH0035E Routine Maintenance Project $572,500 $534,290-6.7% vs est. $467,667 – $587,339 1.74 plan holders Check my bid
Dec 3, 2026 6511-59-001 LubbockLubbock · IH0027 Routine Maintenance Project - Sealed $542,225 $509,501-6.0% vs est. $445,014 – $563,898 1.22 plan holders Check my bid
Dec 3, 2026 6502-79-001 EllisDallas · IH0035E Routine Maintenance Project - Sealed $523,050 $460,382-12.0% vs est. $392,390 – $516,889 3.66 plan holders Check my bid
Dec 3, 2026 6508-10-001 CollinDallas · US0075 Routine Maintenance Project - Sealed $437,898 $385,435-12.0% vs est. $329,574 – $433,293 3.79 plan holders Check my bid
Dec 3, 2026 6511-55-001 TerryLubbock · US0062 Routine Maintenance Project - Sealed $421,350 $392,498-6.8% vs est. $342,262 – $433,388 1.83 plan holders Check my bid
Dec 3, 2026 6508-07-001 CollinDallas · US0075 Routine Maintenance Project - Sealed $403,750 $369,619-8.5% vs est. $317,158 – $412,480 2.44 plan holders Check my bid
Dec 3, 2026 6511-56-001 TerryLubbock · US0062 Routine Maintenance Project - Sealed $381,375 $356,047-6.6% vs est. $311,567 – $392,428 1.83 plan holders Check my bid
Dec 3, 2026 6511-58-001 LambLubbock · US0084 Routine Maintenance Project - Sealed $381,375 $361,169-5.3% vs est. $317,634 – $397,798 1.22 plan holders Check my bid
Dec 3, 2026 6511-61-001 LubbockLubbock · IH0027 Routine Maintenance Project - Sealed $380,750 $337,202-11.4% vs est. $291,314 – $378,814 3.8 Check my bid
Dec 3, 2026 6503-02-001 EllisDallas · FM0876 Material Maintenance Project $378,125 $364,413-3.6% vs est. $321,334 – $391,209 1.73 plan holders Check my bid
Dec 3, 2026 6511-57-001 LambLubbock · US0084 Routine Maintenance Project - Sealed $353,850 $335,434-5.2% vs est. $295,039 – $369,663 1.22 plan holders Check my bid
Dec 3, 2026 6508-09-001 CollinDallas · US0380 Routine Maintenance Project - Sealed $295,106 $262,421-11.1% vs est. $226,760 – $294,358 3.78 plan holders Check my bid
Dec 3, 2026 6505-10-001 NavarroDallas · IH0045 Routine Maintenance Project - Sealed $283,568 $262,268-7.5% vs est. $226,479 – $290,025 2.44 plan holders Check my bid
Dec 3, 2026 6511-60-001 LubbockLubbock · IH0027 Routine Maintenance Project - Sealed $256,375 $244,303-4.7% vs est. $217,557 – $269,994 1.22 plan holders Check my bid
Dec 3, 2026 6511-66-001 EllisDallas · FM0876 Material Maintenance Project $231,000 $218,922-5.2% vs est. $193,078 – $236,609 2.95 plan holders Check my bid
Dec 3, 2026 6508-31-001 KaufmanDallas · FM2728 Material Maintenance Project $208,000 $195,552-6.0% vs est. $172,274 – $212,473 3.36 plan holders Check my bid
Dec 3, 2026 6508-08-001 CollinDallas · US0075 Routine Maintenance Project - Sealed $177,825 $169,146-4.9% vs est. $148,863 – $185,461 1.83 plan holders Check my bid
Dec 3, 2026 6508-30-001 DentonDallas · IH0035W Routine Maintenance Project - Sealed $126,550 $119,174-5.8% vs est. $105,346 – $131,370 2.76 plan holders Check my bid
Dec 3, 2026 6503-03-001 EllisDallas · FM0876 Material Maintenance Project $120,000 $117,633-2.0% vs est. $106,666 – $129,239 1.73 plan holders Check my bid
Dec 3, 2026 6508-11-001 CollinDallas · US0075 Routine Maintenance Project - Sealed $115,770 $105,908-8.5% vs est. $92,366 – $118,390 3.87 plan holders Check my bid
Dec 3, 2026 6498-22-001 CollinDallas · US0075 Routine Maintenance Project - Sealed $87,676 $84,159-4.0% vs est. $74,420 – $94,190 2.56 plan holders Check my bid
Dec 8, 2026 6499-91-001 WallerHouston · US0290 Bridge Preventative Maintenance - Sealed $758,000 $667,086-12.0% vs est. $571,555 – $749,371 4.5 Check my bid
Dec 8, 2026 6506-76-001 MontgomeryHouston · IH0045 Routine Maintenance Project - Sealed $725,905 $644,353-11.2% vs est. $563,013 – $720,528 3.57 plan holders Check my bid
Dec 8, 2026 6506-38-001 HarrisHouston · IH0069 Routine Maintenance Project - Sealed $666,517 $586,551-12.0% vs est. $504,734 – $660,385 4.1 Check my bid
Dec 8, 2026 6505-24-001 EctorOdessa · IH0020 Routine Maintenance Project - Sealed $665,370 $611,355-8.1% vs est. $533,428 – $681,052 2.44 plan holders Check my bid
Dec 8, 2026 6506-85-001 MontgomeryHouston · IH0045 Routine Maintenance Project - Sealed $629,321 $596,568-5.2% vs est. $522,255 – $663,205 1.01 plan holders Check my bid
Dec 8, 2026 6510-87-001 EctorOdessa · IH0020 Bridge Preventative Maintenance - Sealed $607,000 $538,305-11.3% vs est. $470,808 – $593,304 4.27 plan holders Check my bid
Dec 8, 2026 6504-29-001 GalvestonHouston · SH0087 Routine Maintenance Project - Sealed $495,189 $448,706-9.4% vs est. $388,971 – $498,331 3.17 plan holders Check my bid
Dec 8, 2026 6509-26-001 Fort BendHouston · US0059 Routine Maintenance Project - Sealed $410,070 $366,256-10.7% vs est. $319,472 – $408,489 3.78 plan holders Check my bid
Dec 8, 2026 6506-83-001 MontgomeryHouston · IH0045 Routine Maintenance Project - Sealed $367,699 $350,935-4.6% vs est. $310,041 – $387,818 1.01 plan holders Check my bid
Dec 8, 2026 6506-82-001 MontgomeryHouston · IH0045 Routine Maintenance Project - Sealed $334,340 $319,207-4.5% vs est. $282,817 – $352,603 1.01 plan holders Check my bid
Dec 8, 2026 6513-10-001 EctorOdessa · BI0020E Material Maintenance Project $286,800 $278,043-3.1% vs est. $253,340 – $300,322 1.22 plan holders Check my bid
Dec 8, 2026 6502-84-001 HarrisHouston · FM1093 Routine Maintenance Project - Sealed $261,585 $250,006-4.4% vs est. $223,752 – $275,891 1.01 plan holders Check my bid
Dec 8, 2026 6512-48-001 TerrellOdessa · US0090 Routine Maintenance Project $106,560 $102,045-4.2% vs est. $92,707 – $111,469 1.74 plan holders Check my bid
Dec 9, 2026 6510-86-001 El PasoEl Paso · IH0010 Routine Maintenance Project $963,350 $850,265-11.7% vs est. $744,171 – $950,344 4.3 Check my bid
Dec 9, 2026 6513-02-001 ChildressChildress · US0287 Routine Maintenance Project - Sealed $529,190 $484,326-8.5% vs est. $423,287 – $536,976 2.65 plan holders Check my bid
Dec 10, 2026 6508-64-001 La SalleLaredo · IH0035 Material Maintenance Project - Sealed $850,150 $806,235-5.2% vs est. $711,897 – $875,816 1.83 plan holders Check my bid
Dec 10, 2026 6511-62-001 StonewallAbilene · US0083 Routine Maintenance Project - Sealed $682,373 $627,914-8.0% vs est. $547,226 – $696,984 2.15 plan holders Check my bid
Dec 10, 2026 6509-62-001 Val VerdeLaredo · US0090 Routine Maintenance Project - Sealed $680,095 $635,402-6.6% vs est. $557,766 – $705,805 1.83 plan holders Check my bid
Dec 10, 2026 6510-72-001 JonesAbilene · FM0126 Routine Maintenance Project - Sealed $571,125 $525,270-8.0% vs est. $457,899 – $583,178 2.35 plan holders Check my bid
Dec 10, 2026 6508-63-001 La SalleLaredo · IH0035 Routine Maintenance Project - Sealed $489,500 $466,451-4.7% vs est. $410,087 – $516,115 1.22 plan holders Check my bid
Dec 10, 2026 6504-73-001 SmithTyler · IH0020 Routine Maintenance Project - Sealed $311,575 $293,184-5.9% vs est. $259,379 – $322,793 1.84 plan holders Check my bid
Dec 10, 2026 6512-97-001 Val VerdeLaredo · SH0163 Routine Maintenance Project - Sealed $111,879 $102,929-8.0% vs est. $88,406 – $115,020 3.7 Check my bid
Dec 11, 2026 6512-19-001 BowieAtlanta · US0059 Routine Maintenance Project - Sealed $935,100 $864,684-7.5% vs est. $755,576 – $957,031 1.84 plan holders Check my bid
Dec 11, 2026 6509-76-001 HarrisonAtlanta · US0080 Routine Maintenance Project $324,574 $310,314-4.4% vs est. $277,590 – $337,099 1.23 plan holders Check my bid
Dec 11, 2026 6509-77-001 TitusAtlanta · US0271 Routine Maintenance Project $283,652 $269,340-5.0% vs est. $240,232 – $291,482 1.83 plan holders Check my bid
Dec 11, 2026 6509-78-001 BowieAtlanta · US0259 Routine Maintenance Project $252,868 $242,370-4.2% vs est. $218,450 – $263,027 1.23 plan holders Check my bid
Dec 11, 2026 6509-75-001 CassAtlanta · FM0251 Routine Maintenance Project $231,926 $220,495-4.9% vs est. $198,679 – $239,579 1.83 plan holders Check my bid
Dec 11, 2026 6509-71-001 PanolaAtlanta · US0059 Routine Maintenance Project $216,492 $207,882-4.0% vs est. $188,299 – $225,988 1.23 plan holders Check my bid
Dec 11, 2026 6509-73-001 UpshurAtlanta · FM0556 Routine Maintenance Project $207,284 $199,325-3.8% vs est. $180,444 – $216,673 1.22 plan holders Check my bid
Dec 11, 2026 6509-72-001 MorrisAtlanta · FM0161 Routine Maintenance Project $198,632 $189,002-4.8% vs est. $171,109 – $206,232 1.83 plan holders Check my bid
Dec 11, 2026 6509-74-001 MarionAtlanta · SH0049 Routine Maintenance Project $172,467 $164,577-4.6% vs est. $149,077 – $179,599 1.84 plan holders Check my bid
Dec 11, 2026 6509-79-001 BowieAtlanta · IH0030 Routine Maintenance Project $169,432 $163,178-3.7% vs est. $147,646 – $177,904 1.22 plan holders Check my bid
Dec 15, 2026 6513-22-001 KarnesCorpus Christi · US0181 Material Maintenance Project $800,000 $718,936-10.1% vs est. $641,595 – $786,332 4.05 plan holders Check my bid
Dec 15, 2026 6513-21-001 Jim WellsCorpus Christi · US0281 Material Maintenance Project $780,000 $701,672-10.0% vs est. $626,591 – $767,005 4.05 plan holders Check my bid
Dec 15, 2026 6513-20-001 San PatricioCorpus Christi · US0181 Material Maintenance Project $754,000 $680,260-9.8% vs est. $607,348 – $742,306 4.05 plan holders Check my bid
Dec 15, 2026 6513-40-001 HarrisHouston · US0290 Routine Maintenance Project - Sealed $711,194 $624,235-12.2% vs est. $536,280 – $703,677 4.1 Check my bid
Dec 15, 2026 6511-45-001 McLennanWaco · US0084 Routine Maintenance Project $633,642 $559,108-11.8% vs est. $491,944 – $625,077 4.1 Check my bid
Dec 15, 2026 6513-19-001 GoliadCorpus Christi · US0059 Material Maintenance Project $300,000 $282,799-5.7% vs est. $253,429 – $303,962 3.45 plan holders Check my bid
Dec 15, 2026 6511-69-001 BrazosBryan · SH0006 Material Maintenance Project $245,508 $229,133-6.7% vs est. $205,991 – $249,357 3.42 plan holders Check my bid
Dec 15, 2026 6512-86-001 GrimesBryan · FM0244 Routine Maintenance Project $210,153 $191,993-8.6% vs est. $171,222 – $211,059 3.81 plan holders Check my bid
Dec 15, 2026 6512-83-001 KimbleSan Angelo · US0377 Material Maintenance Project $153,230 $145,248-5.2% vs est. $129,710 – $158,521 3.45 plan holders Check my bid
Dec 15, 2026 6464-60-001 RobertsonBryan · US0079 Routine Maintenance Project $122,000 $113,289-7.1% vs est. $100,289 – $125,050 3.72 plan holders Check my bid
Dec 15, 2026 6510-27-001 NuecesCorpus Christi · US0181 Routine Maintenance Project - Sealed $88,668 $82,823-6.6% vs est. $71,576 – $92,568 3.5 Check my bid
Dec 16, 2026 6509-00-001 ParkerFort Worth · IH0020 Routine Maintenance Project - Sealed $886,974 $769,868-13.2% vs est. $660,429 – $868,072 4.4 Check my bid
Dec 17, 2026 6511-76-001 GraysonParis · US0075 Routine Maintenance Project - Sealed $487,915 $430,151-11.8% vs est. $376,095 – $477,937 3.91 plan holders Check my bid
Dec 17, 2026 6513-00-001 HopkinsParis · IH0030 Routine Maintenance Project - Sealed $287,282 $256,472-10.7% vs est. $222,406 – $286,191 3.9 Check my bid
Dec 17, 2026 6513-09-001 HopkinsParis · IH0030 Routine Maintenance Project - Sealed $125,450 $114,549-8.7% vs est. $100,099 – $127,229 3.91 plan holders Check my bid
Dec 21, 2026 6511-16-001 VictoriaYoakum · US0077 Routine Maintenance Project - Sealed $999,500 $881,810-11.8% vs est. $767,438 – $980,350 4.41 plan holders Check my bid
Dec 21, 2026 6508-68-001 BrewsterEl Paso · SH0118 Material Maintenance Project $743,050 $671,585-9.6% vs est. $593,339 – $736,072 3.91 plan holders Check my bid
Dec 21, 2026 6513-37-001 MooreAmarillo · US0087 Routine Maintenance Project - Sealed $598,500 $529,443-11.5% vs est. $454,606 – $593,966 4.0 Check my bid
Jan 6, 2027 0265-03-042 BastropAustin · SH 71 Interchange (New or Reconstructed) $49,159,553 $44,038,101-10.4% vs est. $40,909,960 – $48,465,773 5.8 Check my bid
Jan 6, 2027 0249-07-072 JackFort Worth · US 281 Interchange (New or Reconstructed) $34,966,830 $30,820,917-11.9% vs est. $27,998,014 – $33,751,143 5.4 Check my bid
Jan 6, 2027 0016-05-133 ComalSan Antonio · IH 35 Overlay $16,478,234 $14,021,232-14.9% vs est. $12,583,784 – $15,663,320 5.0 Check my bid
Jan 6, 2027 0136-05-049 Delta, LamarParis · SH 19 Overlay $13,004,091 $11,443,943-12.0% vs est. $10,069,598 – $12,549,343 5.0 Check my bid
Jan 6, 2027 0445-01-072 Colorado, Gonzales, LavacaYoakum · UA 90 Overlay $12,372,894 $10,890,233-12.0% vs est. $9,668,087 – $12,041,634 5.1 Check my bid
Jan 6, 2027 0085-01-053 Bowie, MorrisAtlanta · FM 561, US 259 Overlay $7,996,510 $7,023,973-12.2% vs est. $6,300,783 – $7,766,049 5.2 Check my bid
Jan 6, 2027 0495-03-070 Van ZandtTyler · IH 20 New Location Non-Freeway $6,110,601 $5,374,000-12.1% vs est. $4,814,322 – $5,939,742 5.4 Check my bid
Jan 6, 2027 0049-09-103 Brazos, FreestoneBryan · BS 6R, US 84 Bridge Maintenance $5,234,866 $4,594,063-12.2% vs est. $4,114,429 – $5,086,913 5.6 Check my bid
Jan 6, 2027 1057-03-060 CameronPharr · FM 510 Rehabilitation of Existing Road $5,174,097 $4,550,021-12.1% vs est. $4,120,368 – $5,014,288 5.4 Check my bid
Jan 6, 2027 0054-06-109 Brown, ColemanBrownwood · FM 2524, SH 153, US 67 Overlay $4,925,730 $4,304,240-12.6% vs est. $3,858,325 – $4,765,119 5.5 Check my bid
Jan 6, 2027 0389-05-134 HarrisHouston · SH 146 Transportation Non-Roadway $4,320,890 $3,759,175-13.0% vs est. $3,304,435 – $4,163,479 5.6 Check my bid
Jan 6, 2027 0910-00-170 SmithTyler · Various Traffic Control Devices $3,654,646 $3,180,412-13.0% vs est. $2,795,819 – $3,533,162 5.4 Check my bid
Jan 6, 2027 1728-02-069 ComalSan Antonio · FM 306 Safety Improvement Projects $3,646,201 $3,172,028-13.0% vs est. $2,792,596 – $3,525,204 5.6 Check my bid
Jan 6, 2027 3312-02-019 GalvestonHouston · FM 270 Overlay $3,480,730 $3,020,449-13.2% vs est. $2,663,004 – $3,359,208 5.5 Check my bid
Jan 6, 2027 1685-02-058 HarrisHouston · FM 1960 Safety Improvement Projects $3,426,835 $2,961,982-13.6% vs est. $2,604,132 – $3,297,997 5.7 Check my bid
Jan 6, 2027 6509-80-001 BowieAtlanta · IH0030 Material Maintenance Project $3,332,165 $2,912,005-12.6% vs est. $2,580,872 – $3,229,196 5.4 Check my bid
Jan 6, 2027 0172-09-047 TarrantFort Worth · US 287 Rehabilitation of Existing Road $2,919,363 $2,528,631-13.4% vs est. $2,208,225 – $2,817,461 5.4 Check my bid
Jan 6, 2027 0089-15-019 Colorado, Matagorda, WhartonYoakum · BS 71F, BU 59S, FM 2540, SH 35, SH 71 Pedestrian, Sidewalks & Curb Ramps $2,767,889 $2,417,881-12.6% vs est. $2,163,893 – $2,671,616 5.8 Check my bid
Jan 6, 2027 6496-63-001 BurnetAustin · US0281 Routine Maintenance Project - Sealed $2,048,175 $1,757,519-14.2% vs est. $1,529,176 – $1,972,780 5.1 Check my bid
Jan 6, 2027 0179-02-092 BrazoriaHouston · SH 35 Bridge Maintenance $2,043,210 $1,764,721-13.6% vs est. $1,540,524 – $1,975,566 5.5 Check my bid
Jan 6, 2027 0906-00-273 EctorOdessa · Various Bridge Maintenance $2,041,975 $1,769,105-13.4% vs est. $1,550,705 – $1,976,435 5.4 Check my bid
Jan 6, 2027 6496-57-001 BlancoAustin · US0281 Material Maintenance Project $1,990,050 $1,734,416-12.8% vs est. $1,518,645 – $1,926,928 5.1 Check my bid
Jan 6, 2027 0001-04-109 El PasoEl Paso · US 85 Safety Improvement Projects $1,898,569 $1,649,346-13.1% vs est. $1,452,529 – $1,844,969 5.2 Check my bid
Jan 6, 2027 6512-38-001 BosqueWaco · SH0006 Material Maintenance Project $1,579,936 $1,392,341-11.9% vs est. $1,235,225 – $1,538,220 4.8 Check my bid
Jan 6, 2027 6513-51-001 NolanMaintenance Division · IH0020 Material Maintenance Project $1,515,000 $1,340,022-11.5% vs est. $1,171,595 – $1,484,300 4.8 Check my bid
Jan 6, 2027 0925-00-085 ChildressChildress · Various Traffic Control Devices $1,490,805 $1,291,456-13.4% vs est. $1,129,191 – $1,448,506 5.2 Check my bid
Jan 6, 2027 6513-45-001 GrayAmarillo · SH0070 Material Maintenance Project $1,408,564 $1,251,718-11.1% vs est. $1,100,623 – $1,382,364 4.6 Check my bid
Jan 6, 2027 6513-05-001 TitusMaintenance Division · IH0030 Material Maintenance Project $1,404,700 $1,244,537-11.4% vs est. $1,091,445 – $1,379,770 4.7 Check my bid
Jan 6, 2027 0918-47-586 DallasDallas · Various Bridge Maintenance $1,371,728 $1,186,109-13.5% vs est. $1,021,696 – $1,330,528 5.1 Check my bid
Jan 6, 2027 0069-10-003 HowardAbilene · US 87 Bridge Maintenance $1,356,095 $1,178,443-13.1% vs est. $1,017,797 – $1,321,365 5.0 Check my bid
Jan 6, 2027 6503-99-001 JeffersonBeaumont · IH0010 Routine Maintenance Project - Sealed $1,328,803 $1,148,202-13.6% vs est. $994,649 – $1,294,475 4.7 Check my bid
Jan 6, 2027 6506-09-001 KaufmanDallas · IH0020 Routine Maintenance Project - Sealed $1,306,469 $1,124,528-13.9% vs est. $961,277 – $1,264,810 4.7 Check my bid
Jan 6, 2027 6496-54-001 TravisAustin · IH0035 Routine Maintenance Project - Sealed $1,299,670 $1,115,219-14.2% vs est. $957,826 – $1,260,032 4.8 Check my bid
Jan 6, 2027 6513-38-001 JeffersonBeaumont · SH0347 Material Maintenance Project - Sealed $1,231,500 $1,077,519-12.5% vs est. $936,248 – $1,205,743 4.7 Check my bid
Jan 6, 2027 6512-37-001 BellWaco · SH0036 Material Maintenance Project $1,086,157 $969,543-10.7% vs est. $854,018 – $1,069,174 4.4 Check my bid
Jan 6, 2027 1685-05-141 HarrisHouston · SH 6 Safety Improvement Projects $1,071,674 $936,257-12.6% vs est. $815,938 – $1,049,791 4.8 Check my bid
Jan 6, 2027 0922-00-092 WebbLaredo · Various Safety Improvement Projects $1,060,926 $933,757-12.0% vs est. $811,922 – $1,040,642 4.7 Check my bid
Jan 6, 2027 0700-04-056 Llano, TravisAustin · SH 71, Various Bridge Maintenance $700,723 $614,881-12.3% vs est. $526,401 – $688,296 4.5 Check my bid
Jan 6, 2027 6513-53-001 GuadalupeMaintenance Division · SH0046 Material Maintenance Project $481,740 $441,885-8.3% vs est. $384,083 – $483,238 3.6 Check my bid
Jan 7, 2027 0440-05-015 Travis, WilliamsonAustin · SH 130, SH 45 Widen Freeway $210,801,460 $190,188,639-9.8% vs est. $174,889,172 – $211,376,944 5.7 Check my bid
Jan 7, 2027 0024-08-152 BexarSan Antonio · US 90 Safety Improvement Projects $14,023,512 $12,061,909-14.0% vs est. $10,805,955 – $13,528,339 5.1 Check my bid
Jan 7, 2027 0063-04-069 PanolaAtlanta · US 59 Overlay $6,932,121 $6,090,396-12.1% vs est. $5,472,241 – $6,731,988 5.3 Check my bid
Jan 7, 2027 1530-01-012 ScurryAbilene · FM 1609 Widen Non-Freeway $5,191,836 $4,554,818-12.3% vs est. $4,056,289 – $5,027,732 5.5 Check my bid
Jan 7, 2027 0527-06-022 Fort BendHouston · FM 360 Overlay $3,778,339 $3,283,670-13.1% vs est. $2,893,138 – $3,650,521 5.5 Check my bid
Jan 7, 2027 0045-19-066 Fannin, GraysonParis · US 82 Bridge Maintenance $3,108,693 $2,706,831-12.9% vs est. $2,382,071 – $3,005,811 5.6 Check my bid
Jan 7, 2027 0336-03-082 AngelinaLufkin · SH 103 Overlay $3,001,030 $2,622,466-12.6% vs est. $2,332,753 – $2,904,468 5.5 Check my bid
Jan 7, 2027 0128-04-045 McCullochBrownwood · US 190 Rehabilitation of Existing Road $2,972,327 $2,587,407-13.0% vs est. $2,290,917 – $2,866,411 5.5 Check my bid
Jan 7, 2027 0906-00-296 EctorOdessa · Various Bridge Maintenance $2,887,932 $2,514,252-12.9% vs est. $2,211,736 – $2,792,326 5.6 Check my bid
Jan 7, 2027 6513-47-001 HutchinsonAmarillo · SH0207 Material Maintenance Project $2,648,344 $2,318,006-12.5% vs est. $2,050,713 – $2,562,929 5.2 Check my bid
Jan 7, 2027 0908-00-135 TaylorAbilene · Various Traffic Control Devices $2,223,712 $1,912,523-14.0% vs est. $1,679,275 – $2,141,493 5.4 Check my bid
Jan 7, 2027 0508-01-401 HarrisHouston · IH 10 Bridge Maintenance $1,892,530 $1,635,331-13.6% vs est. $1,427,062 – $1,832,732 5.4 Check my bid
Jan 7, 2027 0922-33-246 WebbLaredo · Various Texas Park and Wildlife $1,794,109 $1,561,267-13.0% vs est. $1,366,759 – $1,739,429 5.2 Check my bid
Jan 7, 2027 0914-00-584 TravisAustin · Various Bridge Maintenance $1,628,329 $1,402,626-13.9% vs est. $1,219,337 – $1,575,088 5.3 Check my bid
Jan 7, 2027 0594-03-029 RuskTyler · FM 225 Safety Improvement Projects $1,474,875 $1,283,904-12.9% vs est. $1,123,324 – $1,439,497 5.1 Check my bid
Jan 7, 2027 0914-00-518 TravisAustin · Various Traffic Control Devices $1,170,970 $1,013,357-13.5% vs est. $879,634 – $1,139,898 4.9 Check my bid
Jan 7, 2027 0914-00-510 TravisAustin · Various Bridge Maintenance $1,030,008 $893,306-13.3% vs est. $767,314 – $1,004,507 4.8 Check my bid
Jan 7, 2027 0922-33-217 WebbLaredo · LOWRY LN Bridge Replacement $766,971 $681,413-11.2% vs est. $592,783 – $760,583 4.4 Check my bid
Jan 7, 2027 0111-08-130 BrazoriaHouston · SH 288 Bridge Maintenance $744,996 $658,154-11.7% vs est. $568,458 – $738,786 4.3 Check my bid
Jan 7, 2027 1062-02-030 HarrisHouston · FM 1485 Overlay $724,764 $641,957-11.4% vs est. $558,445 – $718,883 4.3 Check my bid
Jan 7, 2027 0910-00-151 SmithTyler · Various Bridge Maintenance $714,808 $634,591-11.2% vs est. $547,507 – $708,096 4.3 Check my bid
Jan 7, 2027 0014-01-032 TarrantFort Worth · BU 287P Safety Improvement Projects $606,395 $535,646-11.7% vs est. $467,422 – $600,635 4.2 Check my bid
Jan 7, 2027 0718-01-077 DentonDallas · FM 156 Safety Improvement Projects $504,590 $444,808-11.8% vs est. $383,541 – $500,511 4.1 Check my bid
Jan 7, 2027 0598-02-133 BrazoriaHouston · SH 288 Bridge Maintenance $470,290 $419,467-10.8% vs est. $364,548 – $469,243 4.0 Check my bid
Jan 7, 2027 0227-06-033 Dawson, HockleyLubbock · SH 137, US 180, US 385 Safety Improvement Projects $374,764 $336,089-10.3% vs est. $292,775 – $374,450 3.8 Check my bid
Jan 7, 2027 0902-20-242 WiseFort Worth · Various Safety Improvement Projects $276,185 $248,675-10.0% vs est. $215,414 – $276,302 3.8 Check my bid

Predicted low = the most likely low bid. Likely range = the middle half: the low bid lands inside it about half the time. Bidders = expected bids from the plan holders (or, before plans are out, what similar jobs drew). Always confirm against the official proposal.