Win Price: 0911-28-062

Houston · lets Dec 2, 2026 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Bridge Replacement

Official

CCSJ 0911-28-062 · lets Wednesday, Dec 2, 2026 · Houston, Lufkin · COUNTY ROAD 2065 · Bridge Replacement

$1,367,225Predicted low bid-14.4% vs the engineer's estimate of $1,597,562
$1,204,037 – $1,527,874Likely rangeThe low bid lands here about half the time. 8 in 10: $1,061,154 to $1,674,461
6.8Expected bidders13 plan holders so far
MediumConfidenceBacked by 650 closely comparable lettings (2,192 in all)

Where the low bid should land

$1,061,154: 1 in 10 low bids go lower$1,674,461: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$1,061,154-33.6% 90%
$1,204,037-24.6% 75%
$1,367,225-14.4% 50%
$1,527,874-4.4% 25%
$1,674,461+4.8% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
A. L. HELMCAMP, INC.Bidders 60% 21038 8.8% $1,738,924
LONGVIEW BRIDGE AND ROAD, LTD.Bidders 60% 9715 3.5% $1,652,843
EAST TEXAS BRIDGE, INC.Bidders 60% 12613 11.8% $1,786,012
TREVWAY, INC.Bidders 60% 4310 13.5% $1,813,848
R CONSTRUCTION CIVIL, LLCBidders 60% 5810 3.2% $1,649,432
THK CONSTRUCTION LLCBidders 60% 9830 2.7% $1,641,428
GARRET SHIELDS INFRASTRUCTUREBidders 60% 465100 3.0% $1,644,914
RB CONTRACTING, LLCBidders 60% 254 8.1% $1,727,726
TUCAN CONTRACTING, LLCBidders 60% 355 0.1% $1,599,092
SKYLINE BRIDGE LLCBidders 60% 7710 1.5% $1,621,897
DRAKE COMPANIES LLCBidders 60% 215 4.3% $1,666,214
A T CONSTRUCTION, LLCInformational Proposals 20% 10 -3.8% $1,537,582
VERNARA LLCBidders 3% 00

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Aug 20260911-28-082 HoustonLufkinBridge Replacement6 $2,474,314$2,809,388+13.5% THK CONSTRUCTION LLC
Mar 20260200-03-034 AngelinaLufkinSafety Improvement Projects7 $1,693,881$1,511,792-10.7% MASSANA CONSTRUCTION INC.
Sep 20252591-01-015 PolkLufkinBridge Replacement7 $2,506,060$2,472,737-1.3% THK CONSTRUCTION LLC
Jul 20250911-28-061 HoustonLufkinBridge Replacement6 $1,498,562$1,408,212-6.0% BLACKSMITH VENTURES LLC
Sep 20260427-01-042 Red RiverParisBridge Replacement7 $1,783,455$1,792,908+0.5% HIGHWAY 19 CONSTRUCTION LLC
Apr 20260911-00-127 AngelinaLufkinBridge Maintenance7 $1,032,174$948,750-8.1% GARRET SHIELDS INFRASTRUCTURE
Jun 20250911-04-098 PolkLufkinBridge Replacement8 $1,912,209$1,653,086-13.6% TRUE ROADS CONSTRUCTION LLC
Aug 20250911-39-074 ShelbyLufkinBridge Replacement8 $2,163,444$1,630,098-24.7% HODGES AND SON CONSTRUCTION COMPANY, INC.
Oct 20266507-80-001 AngelinaLufkinBridge Preventative Maintenance8 $999,970$681,151-31.9% BLACKSMITH VENTURES LLC
Nov 20260922-33-234 WebbLaredoBridge Replacement7 $2,562,657$2,866,785+11.9% STX CIVIL

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.