CR 3689_At Cypress Creek - HBP
0911-39-074 · let Aug 7, 2025 · Shelby, Lufkin · Bridge Replacement
$1,630,098Low bid: HODGES AND SON CONSTRUCTION COMPANY, INC.-24.7% vs estimate $2,163,444
$65,773Left on the table4.0% gap to the second bid
8BiddersSpread 28% low to high
134Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,630,098 | -24.7% | $65,773 | 3+$70,012 | 5-$686,996 | |
| 2 | THK CONSTRUCTION LLC | $1,695,871 | +4.0% | -21.6% | $158,592 | 4+$110,314 | 4-$685,806 |
| 3 | TALBERT COMPANIES LLC | $1,854,462 | +13.8% | -14.3% | $111,056 | 5+$82,899 | 2-$206,096 |
| 4 | TRUE ROADS CONSTRUCTION LLC | $1,965,519 | +20.6% | -9.1% | $13,556 | 6+$226,410 | 4-$588,709 |
| 5 | BLACKSMITH VENTURES LLC | $1,979,075 | +21.4% | -8.5% | $18,624 | 5+$277,270 | 3-$524,986 |
| 6 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $1,997,699 | +22.6% | -7.7% | $54,467 | ||
| 7 | LAKEY, INC. | $2,052,166 | +25.9% | -5.1% | $35,233 | ||
| 8 | SKYLINE BRIDGE LLC | $2,087,399 | +28.1% | -3.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HODGES AND SON CONSTRUCTION COMPANY, INC. vs THK CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 420-7012 CL C CONC (ABUT) | 97.6 CY | $1,400.00 | $1,050.00 | $1,307.98 | -$34,160 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $160,000.00 | $523,850.32 | $20,000 |
| 416-7006 DRILL SHAFT (36 IN) | 252 LF | $230.00 | $301.47 | $280.58 | $18,010 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 703 CY | $225.00 | $200.00 | $190.61 | -$17,575 |
| 450-7008 RAIL (TY T223) | 530 LF | $150.00 | $180.00 | $141.07 | $15,900 |
| 416-7005 DRILL SHAFT (30 IN) | 417 LF | $230.00 | $266.63 | $239.74 | $15,275 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $1,800.00 | $1,008.06 | $11,585.04 | -$15,047 |
| 344-7011 SP MIXES SP-C SAC-B PG64-22 | 148 TON | $200.00 | $300.00 | $130.31 | $14,800 |
| 425-7027 PRESTR CONC BOX BEAM (5B20) | 258 LF | $310.00 | $366.06 | $294.26 | $14,463 |
| 422-7005 REINF CONC SLAB (BOX BEAM) | 3,402 SF | $25.00 | $21.00 | $35.96 | -$13,608 |
| 100-7002 PREPARING ROW | 12.75 STA | $3,000.00 | $2,000.00 | $6,072.92 | -$12,750 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 305 SY | $1.00 | $42.80 | $30.47 | $12,749 |
| 416-7002 DRILL SHAFT (18 IN) | 168 LF | $140.00 | $206.11 | $161.72 | $11,106 |
| 316-7254 AGGR (TY E OR L, GR-5) | 10 CY | $1,500.00 | $500.00 | $192.05 | -$10,000 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 2,469 LF | $1.00 | $4.28 | $3.92 | $8,098 |
| 552-7003 WIRE FENCE (TY C) | 775 LF | $20.00 | $30.00 | $12.12 | $7,750 |
| 400-7010 CEM STABIL BKFL | 151 CY | $300.00 | $350.00 | $138.14 | $7,550 |
| 247-7033 FL BS (CMP IN PLC)(TY D GR 1-2) (4") | 1,372 SY | $35.00 | $40.00 | $11.32 | $6,860 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 297.69 LF | $300.00 | $322.52 | $217.69 | $6,704 |
| 454-7003 ARMOR JOINT (SEALED) | 139 LF | $190.00 | $150.00 | $154.25 | -$5,560 |
Positive: the low bidder was cheaper on that item. These 20 items account for $50,567 of the $65,773 gap.
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7033 FL BS (CMP IN PLC)(TY D GR 1-2) (4") | 1,372 SY | $35.00 | $11.32 | 3.09x | $32,492 |
| 400-7010 CEM STABIL BKFL | 151 CY | $300.00 | $138.14 | 2.17x | $24,440 |
| 316-7254 AGGR (TY E OR L, GR-5) | 10 CY | $1,500.00 | $192.05 | 7.81x | $13,080 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $523,850.32 | 0.27x | -$383,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $1,800.00 | $11,585.04 | 0.16x | -$185,916 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $5,000.00 | $28,021.15 | 0.18x | -$69,063 |
| 100-7002 PREPARING ROW | 12.75 STA | $3,000.00 | $6,072.92 | 0.49x | -$39,180 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 305 SY | $1.00 | $30.47 | 0.03x | -$8,987 |
THK CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7033 FL BS (CMP IN PLC)(TY D GR 1-2) (4") | 1,372 SY | $40.00 | $11.32 | 3.53x | $39,352 |
| 400-7010 CEM STABIL BKFL | 151 CY | $350.00 | $138.14 | 2.53x | $31,990 |
| 344-7011 SP MIXES SP-C SAC-B PG64-22 | 148 TON | $300.00 | $130.31 | 2.30x | $25,114 |
| 552-7003 WIRE FENCE (TY C) | 775 LF | $30.00 | $12.12 | 2.48x | $13,858 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $1,008.06 | $11,585.04 | 0.09x | -$200,963 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $5,000.00 | $28,021.15 | 0.18x | -$69,063 |
| 100-7002 PREPARING ROW | 12.75 STA | $2,000.00 | $6,072.92 | 0.33x | -$51,930 |
TALBERT COMPANIES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7033 FL BS (CMP IN PLC)(TY D GR 1-2) (4") | 1,372 SY | $31.50 | $11.32 | 2.78x | $27,690 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 2,743 SY | $9.00 | $1.43 | 6.30x | $20,766 |
| 110-7001 EXCAV (ROADWAY) | 977 CY | $26.00 | $11.68 | 2.23x | $13,988 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 746 CY | $31.00 | $16.96 | 1.83x | $10,471 |
| 552-7003 WIRE FENCE (TY C) | 775 LF | $25.00 | $12.12 | 2.06x | $9,983 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $2,800.00 | $11,585.04 | 0.24x | -$166,916 |
| 100-7002 PREPARING ROW | 12.75 STA | $3,000.00 | $6,072.92 | 0.49x | -$39,180 |
TRUE ROADS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7005 DRILL SHAFT (30 IN) | 417 LF | $495.00 | $239.74 | 2.06x | $106,445 |
| 416-7002 DRILL SHAFT (18 IN) | 168 LF | $375.00 | $161.72 | 2.32x | $35,832 |
| 400-7010 CEM STABIL BKFL | 151 CY | $350.00 | $138.14 | 2.53x | $31,990 |
| 344-7011 SP MIXES SP-C SAC-B PG64-22 | 148 TON | $280.00 | $130.31 | 2.15x | $22,154 |
| 247-7033 FL BS (CMP IN PLC)(TY D GR 1-2) (4") | 1,372 SY | $25.00 | $11.32 | 2.21x | $18,772 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 746 CY | $32.00 | $16.96 | 1.89x | $11,217 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $2,000.00 | $11,585.04 | 0.17x | -$182,116 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $13,500.00 | $28,021.15 | 0.48x | -$43,563 |
| 100-7002 PREPARING ROW | 12.75 STA | $3,000.00 | $6,072.92 | 0.49x | -$39,180 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7012 CL C CONC (ABUT) | 97.6 CY | $2,500.00 | $1,307.98 | 1.91x | $116,341 |
| 416-7005 DRILL SHAFT (30 IN) | 417 LF | $425.00 | $239.74 | 1.77x | $77,255 |
| 247-7033 FL BS (CMP IN PLC)(TY D GR 1-2) (4") | 1,372 SY | $40.00 | $11.32 | 3.53x | $39,352 |
| 416-7002 DRILL SHAFT (18 IN) | 168 LF | $325.00 | $161.72 | 2.01x | $27,432 |
| 400-7010 CEM STABIL BKFL | 151 CY | $250.00 | $138.14 | 1.81x | $16,890 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $263.00 | $11,585.04 | 0.02x | -$215,119 |
| 454-7003 ARMOR JOINT (SEALED) | 139 LF | $75.00 | $154.25 | 0.49x | -$11,016 |