CR 1170 at Sikes Creek - HBP
0911-28-082 · let Aug 6, 2026 · Houston, Lufkin · Bridge Replacement
$2,809,388Low bid: THK CONSTRUCTION LLC+13.5% vs estimate $2,474,314
$174,230Left on the table6.2% gap to the second bid
6BiddersSpread 22% low to high
197Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | THK CONSTRUCTION LLC | $2,809,388 | 13.5% | $174,230 | 3+$156,826 | 6-$724,890 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $2,983,618 | +6.2% | 20.6% | $45,793 | 2+$86,165 | 4-$611,169 |
| 3 | SKYLINE BRIDGE LLC | $3,029,411 | +7.8% | 22.4% | $76,092 | 5+$201,874 | 4-$633,499 |
| 4 | LONGVIEW BRIDGE AND ROAD, LTD. | $3,105,504 | +10.5% | 25.5% | $214,872 | 4+$227,877 | 4-$821,129 |
| 5 | A. L. HELMCAMP, INC. | $3,320,376 | +18.2% | 34.2% | $102,107 | 4+$255,287 | 2-$189,764 |
| 6 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,422,483 | +21.8% | 38.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
THK CONSTRUCTION LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $1,614.53 | $10,000.00 | $11,585.04 | $184,480 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 2,246 CY | $160.00 | $230.00 | $190.61 | $157,220 |
| 420-7012 CL C CONC (ABUT) | 130.2 CY | $975.00 | $100.00 | $1,307.98 | -$113,925 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 5 EA | $40,000.00 | $25,000.00 | $28,021.15 | -$75,000 |
| 450-7008 RAIL (TY T223) | 786 LF | $175.00 | $100.00 | $141.07 | -$58,950 |
| 247-7056 FL BS (CMP IN PLC)(TY D GR 1-2) (6") | 3,503 SY | $45.00 | $30.00 | $23.16 | -$52,545 |
| 454-7001 TYPE A JOINT | 267 LF | $200.00 | $30.00 | $64.16 | -$45,390 |
| 500-7001 MOBILIZATION | 1 LS | $210,000.00 | $250,000.00 | $523,850.32 | $40,000 |
| 110-7001 EXCAV (ROADWAY) | 3,030 CY | $18.00 | $30.00 | $11.68 | $36,360 |
| 425-7030 PRESTR CONC BOX BEAM (4B34) | 358 LF | $307.83 | $400.00 | $353.67 | $32,997 |
| 416-7005 DRILL SHAFT (30 IN) | 930 LF | $268.09 | $300.00 | $239.74 | $29,676 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 1,331 CY | $18.00 | $40.00 | $16.96 | $29,282 |
| 400-7010 CEM STABIL BKFL | 322 CY | $275.00 | $200.00 | $138.14 | -$24,150 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 2,600 SF | $28.00 | $20.00 | $23.90 | -$20,800 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 500 LF | $259.05 | $300.00 | $261.75 | $20,475 |
| 422-7020 SHEAR KEY | 40.7 CY | $800.00 | $300.00 | $650.48 | -$20,350 |
| 552-7010 WIRE FENCE (WATER GAP) | 493 LF | $20.00 | $60.00 | $49.94 | $19,720 |
| 425-7026 PRESTR CONC BOX BEAM (4B20) | 496 LF | $310.80 | $340.00 | $285.37 | $14,483 |
| 425-7031 PRESTR CONC BOX BEAM (5B34) | 179 LF | $332.50 | $400.00 | $345.03 | $12,083 |
| 416-7004 DRILL SHAFT (24 IN) | 555 LF | $178.65 | $200.00 | $234.98 | $11,849 |
Positive: the low bidder was cheaper on that item. These 20 items account for $177,515 of the $174,230 gap.
THK CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7056 FL BS (CMP IN PLC)(TY D GR 1-2) (6") | 3,503 SY | $45.00 | $23.16 | 1.94x | $76,489 |
| 400-7010 CEM STABIL BKFL | 322 CY | $275.00 | $138.14 | 1.99x | $44,068 |
| 454-7001 TYPE A JOINT | 267 LF | $200.00 | $64.16 | 3.12x | $36,269 |
| 500-7001 MOBILIZATION | 1 LS | $210,000.00 | $523,850.32 | 0.40x | -$313,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $1,614.53 | $11,585.04 | 0.14x | -$219,351 |
| 100-7002 PREPARING ROW | 19.22 STA | $1,500.00 | $6,072.92 | 0.25x | -$87,892 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 10 EA | $2,000.00 | $9,253.78 | 0.22x | -$72,538 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 560 SY | $1.00 | $30.47 | 0.03x | -$16,500 |
| 552-7010 WIRE FENCE (WATER GAP) | 493 LF | $20.00 | $49.94 | 0.40x | -$14,758 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 3,030 CY | $30.00 | $11.68 | 2.57x | $55,503 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 1,331 CY | $40.00 | $16.96 | 2.36x | $30,662 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 420-7012 CL C CONC (ABUT) | 130.2 CY | $100.00 | $1,307.98 | 0.08x | -$157,279 |
| 100-7002 PREPARING ROW | 19.22 STA | $1,000.00 | $6,072.92 | 0.16x | -$97,502 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 10 EA | $1,000.00 | $9,253.78 | 0.11x | -$82,538 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7056 FL BS (CMP IN PLC)(TY D GR 1-2) (6") | 3,503 SY | $45.00 | $23.16 | 1.94x | $76,489 |
| 400-7010 CEM STABIL BKFL | 322 CY | $300.00 | $138.14 | 2.17x | $52,118 |
| 552-7010 WIRE FENCE (WATER GAP) | 493 LF | $100.00 | $49.94 | 2.00x | $24,682 |
| 552-7003 WIRE FENCE (TY C) | 1,908 LF | $25.00 | $12.12 | 2.06x | $24,578 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 1,331 CY | $35.00 | $16.96 | 2.06x | $24,007 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $2,000.00 | $11,585.04 | 0.17x | -$210,871 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 5 EA | $12,000.00 | $28,021.15 | 0.43x | -$80,106 |
| 100-7002 PREPARING ROW | 19.22 STA | $2,500.00 | $6,072.92 | 0.41x | -$68,672 |
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 425-7027 PRESTR CONC BOX BEAM (5B20) | 248 LF | $720.00 | $294.26 | 2.45x | $105,584 |
| 425-7031 PRESTR CONC BOX BEAM (5B34) | 179 LF | $655.00 | $345.03 | 1.90x | $55,484 |
| 400-7010 CEM STABIL BKFL | 322 CY | $253.00 | $138.14 | 1.83x | $36,984 |
| 552-7003 WIRE FENCE (TY C) | 1,908 LF | $27.75 | $12.12 | 2.29x | $29,825 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $1,600.00 | $11,585.04 | 0.14x | -$219,671 |
| 100-7002 PREPARING ROW | 19.22 STA | $1,000.00 | $6,072.92 | 0.16x | -$97,502 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 5 EA | $12,000.00 | $28,021.15 | 0.43x | -$80,106 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 450-7008 RAIL (TY T223) | 786 LF | $250.00 | $141.07 | 1.77x | $85,622 |
| 110-7001 EXCAV (ROADWAY) | 3,030 CY | $37.00 | $11.68 | 3.17x | $76,713 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 2,600 SF | $48.00 | $23.90 | 2.01x | $62,650 |
| 552-7003 WIRE FENCE (TY C) | 1,908 LF | $28.00 | $12.12 | 2.31x | $30,302 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $4,000.00 | $11,585.04 | 0.35x | -$166,871 |
| 552-7010 WIRE FENCE (WATER GAP) | 493 LF | $3.50 | $49.94 | 0.07x | -$22,893 |