Win Price accuracy · Texas
We predicted every recent letting before bid day. Here is how close we got.
Bid Potato replays real TxDOT lettings. Each job is predicted using only the jobs that let before it, exactly as you would have seen it before bids opened, then compared with the real low bid.
Win Price vs the engineer's estimate
| Win Price | Engineer's estimate | |
|---|---|---|
| Typical miss on the low bid (median) | 12.2% | 13.4% |
| Within 10% of the low bid | 41% | 40% |
| Within 20% of the low bid | 75% |
When the number of bidders is known (as it is once the plan holder list is final), the typical miss is 11.0% and 46% land within 10%.
Do the odds hold up?
| We said | It happened |
|---|---|
| Low bid inside the likely range (half the time) | 47% |
| Low bid inside the wide range (8 in 10) | 78% |
| A bid at our "3 in 4 chance of lowest" number would have been lowest | 84% |
The ranges and odds are corrected using the year of lettings before the scored year, so these numbers are a fair test, not a fit to the answers.
By job size
| Engineer's estimate | Lettings | Typical miss | Within 10% | Estimate's typical miss | Inside likely range |
|---|---|---|---|---|---|
| Under $1M | 1,243 | 12.2% | 40% | 13.4% | 46% |
| $1M to $5M | 529 | 12.1% | 41% | 14.6% | 49% |
| $5M to $20M | 199 | 12.7% | 43% | 12.0% | 44% |
| $20M and up | 70 | 10.0% | 50% | 11.3% | 44% |
Month by month
| Letting month | Lettings | Win Price typical miss | Estimate's typical miss | Inside likely range |
|---|---|---|---|---|
| Nov 2026 | 123 | 11.3% | 13.5% | 49% |
| Oct 2026 | 131 | 13.0% | 11.6% | 45% |
| Sep 2026 | 171 | 11.7% | 11.4% | 44% |
| Aug 2026 | 240 | 12.6% | 12.4% | 43% |
| Jul 2026 | 157 | 12.9% | 16.3% | 47% |
| Jun 2026 | 224 | 11.5% | 14.4% | 49% |
| May 2026 | 158 | 12.9% | 12.2% | 45% |
| Apr 2026 | 192 | 12.2% | 11.2% | 45% |
| Mar 2026 | 157 | 11.8% | 13.7% | 49% |
| Feb 2026 | 173 | 10.1% | 16.2% | 53% |
| Jan 2026 | 153 | 12.0% | 12.1% | 48% |
| Dec 2025 | 162 | 13.8% | 18.6% | 42% |
Latest predictions against the real low bid
| Let | CCSJ | Where | Estimate | Predicted low | Likely range | Real low bid | Miss | Low bidder |
|---|---|---|---|---|---|---|---|---|
| Nov 23, 2026 | 6509-54-001 | MaverickLaredo · 1 bidders | $402,300 | $353,860 | $307,013 – $393,509 | $400,400 | -11.6% | ERGON ASPHALT & EMULSIONS, INC. |
| Nov 22, 2026 | 6512-29-001 | ZapataPharr · 1 bidders | $714,400 | $615,649 | $532,422 – $690,468 | $861,764 | -28.6% | IOC COMPANY LLC |
| Nov 22, 2026 | 6512-28-001 | CameronPharr · 1 bidders | $714,400 | $615,649 | $532,422 – $690,468 | $831,060 | -25.9% | IOC COMPANY LLC |
| Nov 22, 2026 | 6511-88-001 | HidalgoPharr · 2 bidders | $714,400 | $615,649 | $532,422 – $690,468 | $662,226in range | -7.0% | IOC COMPANY LLC |
| Nov 18, 2026 | 6512-46-001 | KimbleSan Angelo · 8 bidders | $202,250 | $177,210 | $152,006 – $198,238 | $159,400in range | 11.2% | ALLIES LAND CLEARING |
| Nov 18, 2026 | 6510-75-001 | EctorOdessa · 4 bidders | $969,250 | $815,223 | $698,698 – $925,561 | $669,750 | 21.7% | RELMCO, INC. |
| Nov 18, 2026 | 6510-23-001 | LamarParis · 2 bidders | $317,490 | $272,587 | $235,334 – $304,464 | $328,899 | -17.1% | AUSTIN BARRICADE COMPANY, L.L.C. |
| Nov 18, 2026 | 6509-66-001 | DimmitLaredo · 4 bidders | $470,814 | $402,735 | $346,499 – $454,923 | $428,848in range | -6.1% | BOEN LANDSCAPING & IRRIGATION, LLC |
| Nov 18, 2026 | 6508-67-001 | El PasoEl Paso · 2 bidders | $225,750 | $203,248 | $177,632 – $224,621 | $212,269in range | -4.2% | HALL BROTHERS, INC. |
| Nov 17, 2026 | 6511-39-001 | BrazosBryan · 2 bidders | $315,000 | $282,913 | $248,352 – $311,402 | $325,253 | -13.0% | VULCAN CONSTRUCTION MATERIALS, LLC |
| Nov 17, 2026 | 6511-08-001 | MadisonBryan · 3 bidders | $310,000 | $278,719 | $244,493 – $306,517 | $270,750in range | 2.9% | KNIFE RIVER CORPORATION - SOUTH |
| Nov 17, 2026 | 6511-07-001 | LeonBryan · 3 bidders | $335,000 | $300,674 | $263,643 – $330,658 | $283,600in range | 6.0% | BIG CREEK CONSTRUCTION, LTD. |
| Nov 17, 2026 | 6510-96-001 | BrazosBryan · 2 bidders | $386,400 | $334,248 | $295,785 – $373,695 | $294,248 | 13.6% | ANTHONY SERVICES |
| Nov 16, 2026 | 6511-87-001 | HidalgoPharr · 1 bidders | $59,600 | $54,834 | $46,669 – $59,709 | $77,000 | -28.8% | TOUCHSTONE RESOURCES, LLC |
| Nov 16, 2026 | 6511-75-001 | NuecesCorpus Christi · 2 bidders | $147,200 | $135,929 | $118,877 – $147,739 | $154,800 | -12.2% | TOUCHSTONE RESOURCES, LLC |
| Nov 16, 2026 | 6511-74-001 | KarnesCorpus Christi · 1 bidders | $160,200 | $147,562 | $128,770 – $160,705 | $172,800 | -14.6% | ERGON ASPHALT & EMULSIONS, INC. |
| Nov 16, 2026 | 6511-73-001 | NuecesCorpus Christi · 2 bidders | $237,958 | $217,783 | $190,587 – $237,204 | $222,080in range | -1.9% | AKA-MATERIALS |
| Nov 16, 2026 | 6511-72-001 | NuecesCorpus Christi · 1 bidders | $115,210 | $106,344 | $92,716 – $116,370 | $110,850in range | -4.1% | ERGON ASPHALT & EMULSIONS, INC. |
| Nov 16, 2026 | 6511-71-001 | KlebergCorpus Christi · 5 bidders | $515,000 | $460,378 | $402,232 – $504,693 | $563,000 | -18.2% | BRAUNTEX MATERIALS, INC. |
| Nov 16, 2026 | 6511-40-001 | WalkerBryan · 2 bidders | $210,000 | $190,791 | $167,688 – $209,091 | $221,348 | -13.8% | MARTIN MARIETTA MATERIALS, INC. |
| Nov 16, 2026 | 6511-38-001 | BrazosBryan · 4 bidders | $42,000 | $36,975 | $32,298 – $41,874 | $47,904 | -22.8% | COLORADO MATERIALS, LTD. |
| Nov 16, 2026 | 6511-06-001 | FreestoneBryan · 3 bidders | $510,000 | $453,641 | $394,643 – $498,544 | $444,000in range | 2.2% | BIG CREEK CONSTRUCTION, LTD. |
| Nov 16, 2026 | 6511-05-001 | BrazosBryan · 3 bidders | $476,000 | $423,598 | $368,899 – $466,067 | $378,400in range | 11.9% | KNIFE RIVER CORPORATION - SOUTH |
| Nov 16, 2026 | 6511-02-001 | BrazosBryan · 7 bidders | $881,400 | $753,233 | $647,961 – $843,122 | $759,200in range | -0.8% | BOEN LANDSCAPING & IRRIGATION, LLC |
| Nov 16, 2026 | 6510-61-001 | BrazosBryan · 9 bidders | $570,783 | $490,798 | $427,418 – $548,929 | $476,081in range | 3.1% | ORTEGA'S LAWN AND LANDSCAPING, LLC |
| Nov 16, 2026 | 6509-99-001 | BexarSan Antonio · 2 bidders | $256,331 | $232,852 | $201,082 – $255,574 | $207,100in range | 12.4% | RELMCO, INC. |
| Nov 16, 2026 | 6509-22-001 | Live OakCorpus Christi · 3 bidders | $370,000 | $335,947 | $292,743 – $366,219 | $370,000 | -9.2% | CK NEWBERRY, LLC |
| Nov 16, 2026 | 6509-21-001 | Jim WellsCorpus Christi · 4 bidders | $498,200 | $446,493 | $389,371 – $488,917 | $427,000in range | 4.6% | CK NEWBERRY, LLC |
| Nov 16, 2026 | 6508-79-001 | JasperBeaumont · 8 bidders | $417,800 | $359,157 | $311,443 – $403,652 | $319,025in range | 12.6% | ACE CONTRACTORS, INC. |
| Nov 16, 2026 | 6508-77-001 | LibertyBeaumont · 9 bidders | $271,375 | $236,506 | $206,719 – $264,552 | $191,770 | 23.3% | L & M MOWING CONTRACTORS, LLC |
| Nov 16, 2026 | 6508-25-001 | JeffersonBeaumont · 7 bidders | $430,050 | $369,429 | $320,164 – $415,382 | $360,270in range | 2.5% | ACE CONTRACTORS, INC. |
| Nov 16, 2026 | 6506-96-001 | HillWaco · 2 bidders | $594,384 | $525,051 | $454,894 – $580,161 | $614,800 | -14.6% | VULCAN CONSTRUCTION MATERIALS, LLC |
| Nov 16, 2026 | 6506-95-001 | BellWaco · 3 bidders | $484,930 | $430,094 | $373,616 – $474,514 | $467,875in range | -8.1% | LONE STAR PAVING COMPANY |
| Nov 16, 2026 | 6506-52-001 | CoryellWaco · 8 bidders | $295,251 | $255,442 | $225,251 – $286,267 | $254,153in range | 0.5% | JASCO |
| Nov 16, 2026 | 6506-50-001 | BosqueWaco · 7 bidders | $318,167 | $274,964 | $242,026 – $308,052 | $261,287in range | 5.2% | JASCO |
| Nov 11, 2026 | 6510-59-001 | HemphillAmarillo · 8 bidders | $303,900 | $266,539 | $233,751 – $295,907 | $226,590 | 17.6% | ALLIES LAND CLEARING |
| Nov 11, 2026 | 6509-36-001 | CollinDallas · 6 bidders | $925,400 | $767,106 | $653,279 – $879,820 | $615,350 | 24.7% | STRUCTURAL INTEGRITY GROUP LLC |
| Nov 11, 2026 | 6508-80-001 | PotterAmarillo · 14 bidders | $613,278 | $526,787 | $450,064 – $592,454 | $306,731 | 71.7% | INFRATEX CONSTRUCTION LLC |
| Nov 11, 2026 | 6507-50-001 | El PasoEl Paso · 2 bidders | $474,900 | $422,571 | $367,588 – $465,614 | $346,860 | 21.8% | DIGG COMMERCIAL, LLC |
| Nov 11, 2026 | 6506-91-001 | NavarroDallas · 6 bidders | $319,240 | $269,616 | $231,403 – $307,187 | $252,894in range | 6.6% | FIREMAN EXCAVATING, INC. |
How Win Price works
For each job, Win Price looks at every Texas letting of the 3 years before it and weights each one by how alike the two jobs are: size (engineer's estimate), district, type of work, how recent it is, and how many bidders it drew compared with the field expected on this job. Where the low bids on those jobs landed against their estimates gives the most likely low bid and its range.
The field comes from the plan holders: each one's chance of bidding is based on how often they bid prime contracts and how many plan sets they took turned into bids.
Tested on 2,041 lettings from Nov 28, 2025 to Nov 28, 2026, using 17,897 Texas lettings with an estimate and a low bid. Last run Nov 29, 2026 7:02 AM CT.