‹ All Win Price jobs Job page Bid Day Forecast
Routine Maintenance Project - Sealed
UnofficialCCSJ 6513-67-001 · lets Sunday, Nov 29, 2026 · Zavala, Laredo · US0083
$266,565Predicted low bid-10.2% vs the engineer's estimate of $296,881
$230,793 – $296,881Likely rangeThe low bid lands here about half the time. 8 in 10: $193,052 to $331,673
3.8Expected biddersFrom similar jobs; no plan holders posted yet
MediumConfidenceBacked by 1,320 closely comparable lettings (2,481 in all)
Where the low bid should land
$266,565
Estimate $296,881
$193,052: 1 in 10 low bids go lower$331,673: 1 in 10 go higher
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $193,052 | -35.0% | 90% |
| $230,793 | -22.3% | 75% |
| $266,565 | -10.2% | 50% |
| $296,881 | 0.0% | 25% |
| $331,673 | +11.7% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bidsNo plan holders posted for this job yet. The expected field comes from similar jobs until they are.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| Nov 2026 | 6509-66-001 | DimmitLaredo | Routine Maintenance Project - Sealed | 4 | $470,814 | $428,848-8.9% | BOEN LANDSCAPING & IRRIGATION, LLC |
| Jun 2026 | 6500-57-001 | MaverickLaredo | Routine Maintenance Project - Sealed | 3 | $439,480 | $460,615+4.8% | R&M INCORPORATED |
| Nov 2025 | 6492-47-001 | KinneyLaredo | Routine Maintenance Project - Sealed | 2 | $295,530 | $241,954-18.1% | ABESCAPE GROUP LLC |
| Oct 2025 | 6492-06-001 | Val VerdeLaredo | Routine Maintenance Project - Sealed | 1 | $318,192 | $363,296+14.2% | VIZCAINO, L.P. |
| Oct 2025 | 6491-96-001 | MaverickLaredo | Routine Maintenance Project - Sealed | 1 | $385,248 | $694,203+80.2% | VIZCAINO, L.P. |
| Nov 2026 | 6509-54-001 | MaverickLaredo | Material Maintenance Project - Sealed | 1 | $402,300 | $400,400-0.5% | ERGON ASPHALT & EMULSIONS, INC. |
| May 2026 | 6498-99-001 | La SalleLaredo | Routine Maintenance Project - Sealed | 1 | $531,343 | $632,346+19.0% | R&M INCORPORATED |
| May 2026 | 6500-60-001 | Val VerdeLaredo | Material Maintenance Project - Sealed | 1 | $280,800 | $287,820+2.5% | ERGON ASPHALT & EMULSIONS, INC. |
| Nov 2025 | 6492-75-001 | DuvalLaredo | Routine Maintenance Project - Sealed | 2 | $478,179 | $569,033+19.0% | R&M INCORPORATED |
| Nov 2026 | 6510-23-001 | LamarParis | Routine Maintenance Project - Sealed | 2 | $317,490 | $328,899+3.6% | AUSTIN BARRICADE COMPANY, L.L.C. |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.