15BidsDec 2, 2025 to Oct 7, 2026
3Wins (low bidder)
20.0%Win rate
$6,352,134Total won
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Oct 7, 2026 | 0907-00-217 | 0907-00-217 VA PAVEMENT MARKINGSTom Green · San Angelo | 2 of 7 | $2,821,484 | $2,539,432FLAT LINE, INC. | +11.1% |
| Sep 2, 2026 | 6506-24-001 | Debris Removal La Salle, Webb & DimmitLa Salle · Laredo | 2 of 4 | $1,488,846 | $1,244,224TAYLOR BRIDGE LLC | +19.7% |
| Aug 18, 2026 | 6503-18-001 | Tom Green Sweeping FY 27Tom Green · San Angelo | 3 of 4 | $625,670 | $490,191SUNDROP GARDENS LANDSCAPING… | +27.6% |
| Aug 5, 2026 | 6504-94-001 | RMC6504-94-00 Striping Pavement MarkingsLive Oak · Corpus Christi | 3 of 3 | $2,783,031 | $1,742,362TRP INFRASTRUCTURE SERVICES… | +59.7% |
| Aug 5, 2026 | 0916-00-254 | FY 2026 DW Pavement MarkingsNueces · Corpus Christi | 6 of 6 | $6,154,215 | $4,763,993TRP INFRASTRUCTURE SERVICES… | +29.2% |
| Jul 1, 2026 | 0906-00-264 | Non-IH Pavement Markings (2026)Ector · Odessa | 1 of 8 | $5,487,908 | $5,487,908 | Won |
| Jun 2, 2026 | 0915-00-285 | VA: 0915-00-285: TCDBexar · San Antonio | 4 of 9 | $2,915,943 | $2,418,380CENTERLINE TECHNOLOGIES, LLC | +20.6% |
| Apr 21, 2026 | 6497-99-001 | 6497-99-001 Striping CalloutMidland · Odessa | 2 of 6 | $218,680 | $207,027PMI PAVEMENT MARKING, LLC | +5.6% |
| Mar 26, 2026 | 6481-65-001 | PAVEMENT MARKINGS SOUTH FY 26Kimble · San Angelo | 2 of 5 | $291,750 | $199,196L&L COMPANY | +46.5% |
| Mar 26, 2026 | 6497-93-001 | 2026 Debris RemovalTaylor · Abilene | 1 of 4 | $624,648 | $624,648 | Won |
| Mar 24, 2026 | 6480-65-001 | PAVEMENT MARKINGS NORTH FY 26Tom Green · San Angelo | 5 of 6 | $159,596 | $77,856FLAT LINE, INC. | +105.0% |
| Mar 10, 2026 | 6497-99-001 | 6497-99-001 Striping CalloutMidland · Odessa | 1 of 7 | $239,578 | $239,578 | Won |
| Feb 5, 2026 | 0905-00-127 | FY 2026 Striping-LonglineLubbock · Lubbock | 4 of 10 | $7,273,691 | $6,490,125CENTERLINE TECHNOLOGIES, LLC | +12.1% |
| Dec 2, 2025 | 0276-01-048 | HSIP Install Chevrons & RPMMaverick · Laredo | 5 of 5 | $1,894,045 | $1,201,489CENTERLINE TECHNOLOGIES, LLC | +57.6% |
| Dec 2, 2025 | 0924-00-124 | VA FY 2026 STRIPING PROJ (DISTRICTWIDE)El Paso · El Paso | 2 of 4 | $3,275,947 | $2,979,312CENTERLINE TECHNOLOGIES, LLC | +10.0% |
Subcontracts on active jobs 0