Bid Tab X-ray: 6492-47-001

Nov 18, 2025 · Kinney Sign up free
Set your company to personalize scores

Mowing of highways ROW

6492-47-001 · let Nov 18, 2025 · Kinney, Laredo · Routine Maintenance Project - Sealed

$241,954Low bid: ABESCAPE GROUP LLC-18.1% vs estimate $295,530
$6,758Left on the table2.8% gap to the second bid
2BiddersSpread 3% low to high
3Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1ABESCAPE GROUP LLC $241,954-18.1% $6,758 0 1-$45,065
2R&M INCORPORATED $248,712+2.8%-15.8% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

ABESCAPE GROUP LLC vs R&M INCORPORATED, biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7020 STRIP MOWING1,448 AC $1.00$31.98$32.12 $44,859
730-7022 FULL - WIDTH MOWING3,566.1 AC $38.00$31.98$38.53 -$21,468
730-7001 FULL - WIDTH MOWING - TRACT (1)2,763 AC $38.00$31.98$42.29 -$16,633

Positive: the low bidder was cheaper on that item. These 3 items account for $6,758 of the $6,758 gap.

ABESCAPE GROUP LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
730-7020 STRIP MOWING1,448 AC $1.00$32.120.03x-$45,065