Routine Maintenance Project - Sealed
UnofficialCCSJ 6496-54-001 · lets Wednesday, Jan 6, 2027 · Travis, Austin · IH0035
$1,115,219Predicted low bid-14.2% vs the engineer's estimate of $1,299,670
$957,826 – $1,260,032Likely rangeThe low bid lands here about half the time. 8 in 10: $833,736 to $1,414,156
4.8Expected biddersFrom similar jobs; no plan holders posted yet
MediumConfidenceBacked by 1,063 closely comparable lettings (2,399 in all)
Where the low bid should land
$1,115,219
Estimate $1,299,670
$833,736: 1 in 10 low bids go lower$1,414,156: 1 in 10 go higher
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $833,736 | -35.9% | 90% |
| $957,826 | -26.3% | 75% |
| $1,115,219 | -14.2% | 50% |
| $1,260,032 | -3.0% | 25% |
| $1,414,156 | +8.8% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bidsNo plan holders posted for this job yet. The expected field comes from similar jobs until they are.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| Nov 2026 | 6484-51-001 | WilliamsonAustin | Routine Maintenance Project - Sealed | 7 | $1,160,586 | $962,812-17.0% | RHINO EQUITY, LLC |
| Jul 2026 | 6484-37-001 | TravisAustin | Routine Maintenance Project - Sealed | 3 | $1,178,810 | $756,200-35.9% | ROY JORGENSEN ASSOCIATES, INC. |
| Sep 2026 | 6499-28-001 | WilliamsonAustin | Routine Maintenance Project - Sealed | 5 | $965,583 | $660,385-31.6% | VACA UNDERGROUND UTILITIES INC |
| Aug 2026 | 6487-45-001 | HaysAustin | Routine Maintenance Project - Sealed | 5 | $1,745,379 | $1,975,939+13.2% | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC |
| Sep 2026 | 6498-20-001 | TravisAustin | Routine Maintenance Project - Sealed | 4 | $908,691 | $668,419-26.4% | VACA UNDERGROUND UTILITIES INC |
| Apr 2026 | 6498-60-001 | BastropAustin | Routine Maintenance Project - Sealed | 5 | $1,575,809 | $1,057,585-32.9% | STRIPE-A-ZONE, LLC |
| May 2026 | 6499-06-001 | BastropAustin | Routine Maintenance Project - Sealed | 5 | $970,617 | $757,352-22.0% | ROSS SA ENTERPRISE LLC |
| May 2026 | 6495-92-001 | HaysAustin | Routine Maintenance Project - Sealed | 3 | $938,785 | $890,314-5.2% | LONE STAR PAVING COMPANY |
| Apr 2026 | 6498-59-001 | BurnetAustin | Routine Maintenance Project - Sealed | 4 | $1,706,599 | $1,072,388-37.2% | STRIPE-A-ZONE, LLC |
| May 2026 | 6498-17-001 | HaysAustin | Routine Maintenance Project - Sealed | 4 | $929,515 | $754,625-18.8% | RHINO EQUITY, LLC |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.