FY 26-2 SAAO MBGF
6498-17-001 · let May 13, 2026 · Hays, Austin · Routine Maintenance Project - Sealed
$754,625Low bid: RHINO EQUITY, LLC-18.8% vs estimate $929,515
$246Left on the table0.0% gap to the second bid
4BiddersSpread 31% low to high
35Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RHINO EQUITY, LLC | $754,625 | -18.8% | $246 | 3+$75,311 | 7-$267,139 | |
| 2 | ROSS SA ENTERPRISE LLC | $754,871 | +0.0% | -18.8% | $91,359 | 1+$98,037 | 11-$341,069 |
| 3 | AUSTIN BARRICADE COMPANY, L.L.C. | $846,230 | +12.1% | -9.0% | $144,725 | 6+$388,322 | 11-$609,968 |
| 4 | T&L CLEANING SERVICES LLC | $990,955 | +31.3% | 6.6% | 3+$56,995 | 7-$266,520 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RHINO EQUITY, LLC vs ROSS SA ENTERPRISE LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 774-7014 REPLACE (REACT)(M) | 4 EA | $3,000.00 | $32,000.00 | $7,490.80 | $116,000 |
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 115 EA | $1,900.00 | $2,500.00 | $2,869.78 | $69,000 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 2,000 LF | $50.00 | $25.00 | $31.82 | -$50,000 |
| 770-7010 REALIGN POSTS | 270 EA | $125.00 | $25.00 | $24.32 | -$27,000 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 20 EA | $1,000.00 | $1.00 | $534.87 | -$19,980 |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 50 EA | $650.00 | $350.00 | $975.38 | -$15,000 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 30 EA | $1,000.00 | $500.00 | $1,019.22 | -$15,000 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 5 EA | $3,000.00 | $1.00 | $3,190.07 | -$14,995 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 4,800 LF | $22.00 | $25.00 | $22.03 | $14,400 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 250 EA | $300.00 | $250.00 | $144.70 | -$12,500 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 125 EA | $150.00 | $60.00 | $89.82 | -$11,250 |
| 770-7018 REPLACE BLOCKOUT | 445 EA | $30.00 | $6.00 | $44.95 | -$10,680 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 125 EA | $125.00 | $60.00 | $94.21 | -$8,125 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 300 EA | $100.00 | $80.00 | $67.59 | -$6,000 |
| 770-7027 REPAIR RAIL ELEMENT (CURVED RAIL) | 1,000 LF | $22.00 | $18.00 | $24.16 | -$4,000 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 10 EA | $300.00 | $1.00 | $65.99 | -$2,990 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 100 EA | $50.00 | $25.00 | $26.51 | -$2,500 |
| 658-7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | 100 EA | $1.00 | $25.00 | $35.16 | $2,400 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $200.00 | $1.00 | $616.83 | -$1,990 |
| 500-7033 MOBILIZATION (EMERGENCY) | 1 EA | $1,000.00 | $1.00 | $844.81 | -$999 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$1,209 of the $246 gap.
RHINO EQUITY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 250 EA | $300.00 | $144.70 | 2.07x | $38,826 |
| 770-7010 REALIGN POSTS | 270 EA | $125.00 | $24.32 | 5.14x | $27,183 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 20 EA | $1,000.00 | $534.87 | 1.87x | $9,303 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 45 EA | $1.00 | $1,297.32 | 0.00x | -$58,335 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $1.00 | $217.57 | 0.00x | -$27,071 |
| 774-7014 REPLACE (REACT)(M) | 4 EA | $3,000.00 | $7,490.80 | 0.40x | -$17,963 |
| 770-7023 REPLACE SGT CABLE ASSEMBLY | 50 EA | $1.00 | $98.88 | 0.01x | -$4,894 |
| 770-7022 REPLACE SGT CABLE ANCHOR | 50 EA | $1.00 | $95.89 | 0.01x | -$4,745 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $200.00 | $616.83 | 0.32x | -$4,168 |
ROSS SA ENTERPRISE LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 774-7014 REPLACE (REACT)(M) | 4 EA | $32,000.00 | $7,490.80 | 4.27x | $98,037 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 45 EA | $1.00 | $1,297.32 | 0.00x | -$58,335 |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 50 EA | $350.00 | $975.38 | 0.36x | -$31,269 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $1.00 | $217.57 | 0.00x | -$27,071 |
| 770-7018 REPLACE BLOCKOUT | 445 EA | $6.00 | $44.95 | 0.13x | -$17,335 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 5 EA | $1.00 | $3,190.07 | 0.00x | -$15,945 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 30 EA | $500.00 | $1,019.22 | 0.49x | -$15,577 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 20 EA | $1.00 | $534.87 | 0.00x | -$10,677 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $1.00 | $616.83 | 0.00x | -$6,158 |
| 770-7023 REPLACE SGT CABLE ASSEMBLY | 50 EA | $10.00 | $98.88 | 0.10x | -$4,444 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 125 DAY | $2,500.00 | $217.57 | 11.49x | $285,304 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 250 EA | $400.00 | $144.70 | 2.76x | $63,826 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 125 EA | $200.00 | $89.82 | 2.23x | $13,772 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 125 EA | $200.00 | $94.21 | 2.12x | $13,224 |
| 770-7010 REALIGN POSTS | 270 EA | $50.00 | $24.32 | 2.06x | $6,933 |
| 771-7016 REPLACE CABLE (TL-4) | 110 LF | $50.00 | $2.15 | 23.26x | $5,264 |
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 115 EA | $1,000.00 | $2,869.78 | 0.35x | -$215,025 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 4,800 LF | $1.00 | $22.03 | 0.05x | -$100,932 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 45 EA | $1.00 | $1,297.32 | 0.00x | -$58,335 |
| 774-7014 REPLACE (REACT)(M) | 4 EA | $1,000.00 | $7,490.80 | 0.13x | -$25,963 |
| 770-7027 REPAIR RAIL ELEMENT (CURVED RAIL) | 1,000 LF | $1.00 | $24.16 | 0.04x | -$23,162 |
| 770-7018 REPLACE BLOCKOUT | 445 EA | $20.00 | $44.95 | 0.44x | -$11,105 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 20 EA | $1.00 | $534.87 | 0.00x | -$10,677 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $100.00 | $616.83 | 0.16x | -$5,168 |
| 770-7023 REPLACE SGT CABLE ASSEMBLY | 50 EA | $1.00 | $98.88 | 0.01x | -$4,894 |
T&L CLEANING SERVICES LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 250 EA | $270.00 | $144.70 | 1.87x | $31,326 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 20 EA | $1,500.00 | $534.87 | 2.80x | $19,303 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 10 EA | $900.00 | $263.33 | 3.42x | $6,367 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 45 EA | $300.00 | $1,297.32 | 0.23x | -$44,880 |
| 505-7001 TMA (STATIONARY) | 125 DAY | $1.00 | $217.57 | 0.00x | -$27,071 |
| 770-7018 REPLACE BLOCKOUT | 445 EA | $10.00 | $44.95 | 0.22x | -$15,555 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 125 EA | $1.00 | $94.21 | 0.01x | -$11,651 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 125 EA | $1.00 | $89.82 | 0.01x | -$11,103 |
| 770-7010 REALIGN POSTS | 270 EA | $1.00 | $24.32 | 0.04x | -$6,297 |