FY 26 Striping Bastrop AE
6498-60-001 · let Apr 7, 2026 · Bastrop, Austin · Routine Maintenance Project - Sealed
$1,057,585Low bid: STRIPE-A-ZONE, LLC-32.9% vs estimate $1,575,809
$21,384Left on the table2.0% gap to the second bid
5BiddersSpread 31% low to high
59Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPE-A-ZONE, LLC | $1,057,585 | -32.9% | $21,384 | 0 | 3-$574,223 | |
| 2 | D. I. J. CONSTRUCTION, INC. | $1,078,969 | +2.0% | -31.5% | $9,261 | 0 | 3-$529,223 |
| 3 | TRP INFRASTRUCTURE SERVICES, LLC | $1,088,230 | +2.9% | -30.9% | $287,083 | 0 | 2-$581,996 |
| 4 | INTERSTATE BARRICADES & MARKINGS, INC. | $1,375,313 | +30.0% | -12.7% | $14,937 | 1+$7,853 | 2-$556,746 |
| 5 | BATTERSON, LLP | $1,390,250 | +31.5% | -11.8% | 1+$15,649 | 1-$423,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRIPE-A-ZONE, LLC vs D. I. J. CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $70,000.00 | $523,850.32 | $45,000 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 485,000 LF | $0.1800 | $0.2500 | $0.1749 | $33,950 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 610,000 LF | $0.1800 | $0.1500 | $0.1701 | -$18,300 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 610,000 LF | $0.6600 | $0.6500 | $0.6515 | -$6,100 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 485,000 LF | $0.6600 | $0.6500 | $0.6629 | -$4,850 |
| 666-7090 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) | 100 EA | $50.00 | $10.00 | $35.36 | -$4,000 |
| 666-7045 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) | 10 EA | $350.00 | $50.00 | $240.06 | -$3,000 |
| 666-7087 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) | 100 EA | $40.00 | $10.00 | $34.28 | -$3,000 |
| 672-7006 REFL PAV MRKR TY II-C-R | 1,000 EA | $4.00 | $1.00 | $4.19 | -$3,000 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 6,000 LF | $0.6500 | $1.00 | $0.5627 | $2,100 |
| 666-7042 REFL PAV MRK TY I (W)(ARROW)(100MIL) | 10 EA | $250.00 | $100.00 | $156.95 | -$1,500 |
| 666-7060 REFL PAV MRK TY I(W)(LNDP ARW)(100MIL) | 5 EA | $500.00 | $200.00 | $328.61 | -$1,500 |
| 666-7066 REFL PAV MRK TY I (W)(WORD)(100MIL) | 10 EA | $300.00 | $150.00 | $184.78 | -$1,500 |
| 666-7123 REFL PAV MRK TY I (Y)24"(SLD)(100MIL) | 100 LF | $12.00 | $2.00 | $7.76 | -$1,000 |
| 672-7002 REFL PAV MRKR TY I-C | 1,000 EA | $4.00 | $3.00 | $4.04 | -$1,000 |
| 672-7004 REFL PAV MRKR TY II-A-A | 9,000 EA | $4.00 | $3.90 | $3.97 | -$900 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 30,000 LF | $0.1800 | $0.1500 | $0.1759 | -$900 |
| 666-7120 REFL PAV MRK TY I (Y)18"(SLD)(100MIL) | 100 LF | $9.00 | $1.00 | $4.76 | -$800 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 600 LF | $1.50 | $0.3000 | $0.9489 | -$720 |
| 666-7033 REFL PAV MRK TY I (W)18"(SLD)(100MIL) | 100 LF | $9.00 | $2.00 | $6.06 | -$700 |
Positive: the low bidder was cheaper on that item. These 20 items account for $28,280 of the $21,384 gap.