Win Price: 0594-03-029

Rusk · lets Jan 7, 2027 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Safety Improvement Projects

Unofficial

CCSJ 0594-03-029 · lets Thursday, Jan 7, 2027 · Rusk, Tyler · FM 225 · Hazard Elimination & Safety

$1,283,904Predicted low bid-12.9% vs the engineer's estimate of $1,474,875
$1,123,324 – $1,439,497Likely rangeThe low bid lands here about half the time. 8 in 10: $969,533 to $1,606,086
5.1Expected biddersFrom similar jobs; no plan holders posted yet
MediumConfidenceBacked by 1,141 closely comparable lettings (2,268 in all)

Where the low bid should land

$969,533: 1 in 10 low bids go lower$1,606,086: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$969,533-34.3% 90%
$1,123,324-23.8% 75%
$1,283,904-12.9% 50%
$1,439,497-2.4% 25%
$1,606,086+8.9% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids

No plan holders posted for this job yet. The expected field comes from similar jobs until they are.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Jul 20260199-01-090 CherokeeTylerSafety Improvement Projects3 $1,304,448$1,093,712-16.2% REYNOLDS & KAY, LTD.
Jun 20260190-05-078 SmithTylerSafety Improvement Projects5 $1,960,952$2,362,671+20.5% ICOS MANAGEMENT, LLC
Aug 20260910-00-165 SmithTylerSafety Improvement Projects10 $926,787$655,280-29.3% STRIPING TECHNOLOGY, L.P.
Nov 20266508-86-001 GreggTylerRoutine Maintenance Project - Sealed4 $1,405,700$1,372,080-2.4% HIGHWAY 19 CONSTRUCTION LLC
Oct 20266496-83-001 GreggTylerRoutine Maintenance Project - Sealed2 $1,529,895$1,287,808-15.8% STRIPING TECHNOLOGY, L.P.
Nov 20266509-96-001 HendersonTylerRoutine Maintenance Project - Sealed4 $1,193,200$1,217,140+2.0% HIGHWAY 19 CONSTRUCTION LLC
Apr 20261790-02-048 SmithTylerBridge Replacement9 $1,629,506$1,516,226-7.0% DRAKE COMPANIES LLC
May 20266500-78-001 HendersonTylerMaterial Maintenance Project2 $1,826,000$1,561,000-14.5% BIG CREEK CONSTRUCTION, LTD.
Oct 20266508-38-001 SmithTylerRoutine Maintenance Project - Sealed3 $940,700$1,076,000+14.4% FLEX SUPPLY, LLC
Sep 20266504-69-001 WoodTylerBridge Preventative Maintenance - Sealed8 $967,500$667,750-31.0% RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.