US 69 - SUPERELEVATION
0199-01-090 · let Jul 1, 2026 · Cherokee, Tyler · Safety Improvement Projects
$1,093,712Low bid: REYNOLDS & KAY, LTD.-16.2% vs estimate $1,304,448
$140,375Left on the table12.8% gap to the second bid
3BiddersSpread 22% low to high
107Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | REYNOLDS & KAY, LTD. | $1,093,712 | -16.2% | $140,375 | 6+$63,771 | 3-$773,605 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $1,234,087 | +12.8% | -5.4% | $99,133 | 3+$34,218 | 4-$733,240 |
| 3 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $1,333,220 | +21.9% | 2.2% | 9+$209,765 | 3-$835,755 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
REYNOLDS & KAY, LTD. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 181 CY | $660.00 | $915.00 | $616.83 | $46,155 |
| 100-7002 PREPARING ROW | 87 STA | $2,700.00 | $3,000.00 | $6,072.92 | $26,100 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $120,000.00 | $523,850.32 | $20,000 |
| 530-7010 DRIVEWAYS (ACP) | 472 SY | $50.00 | $87.00 | $54.96 | $17,464 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 2,850 LF | $30.00 | $34.00 | $30.74 | $11,400 |
| 344-7009 SP MIXES SP-C PG64-22 | 432 TON | $150.00 | $175.00 | $131.13 | $10,800 |
| 403-7001 TEMPORARY SPL SHORING | 528 SF | $55.00 | $35.00 | $25.56 | -$10,560 |
| 344-7044 SP MIXES SP-D PG64-22 (LEVEL-UP) | 234 TON | $150.00 | $195.00 | $153.47 | $10,530 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 3,755 SY | $5.00 | $2.50 | $1.43 | -$9,388 |
| 134-7001 BACKFILL (TY A) | 15 STA | $800.00 | $300.00 | $224.26 | -$7,500 |
| 734-7002 LITTER REMOVAL | 2 CYC | $500.00 | $4,200.00 | $1,937.87 | $7,400 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 250 SY | $88.00 | $115.00 | $49.06 | $6,750 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 3,780 SY | $4.00 | $2.25 | $1.35 | -$6,615 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 328 SY | $20.00 | $40.00 | $6.84 | $6,560 |
| 168-7001 VEGETATIVE WATERING | 103 TGL | $15.00 | $75.00 | $8.43 | $6,180 |
| 466-7178 WINGWALL (PW - 1) (HW=8 FT) | 1 EA | $25,000.00 | $31,000.00 | $42,198.45 | $6,000 |
| 316-7080 ASPH (CHFRS-2P OR CRS-2P) | 1,490 GAL | $9.00 | $5.00 | $9.00 | -$5,960 |
| 354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2") | 1,960 SY | $5.50 | $2.50 | $2.98 | -$5,880 |
| 466-7099 HEADWALL (CH - PW - 0) (DIA= 18 IN) | 1 EA | $10,400.00 | $5,500.00 | $10,404.65 | -$4,900 |
| 150-7001 BLADING | 48 STA | $170.00 | $75.00 | $152.64 | -$4,560 |
Positive: the low bidder was cheaper on that item. These 20 items account for $119,977 of the $140,375 gap.
REYNOLDS & KAY, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 528 SF | $55.00 | $25.56 | 2.15x | $15,544 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 3,755 SY | $5.00 | $1.43 | 3.50x | $13,408 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 3,780 SY | $4.00 | $1.35 | 2.95x | $9,999 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 250 SY | $88.00 | $49.06 | 1.79x | $9,734 |
| 134-7001 BACKFILL (TY A) | 15 STA | $800.00 | $224.26 | 3.57x | $8,636 |
| 316-7253 AGGR (TY-D OR L, GR-4) | 33 CY | $350.00 | $154.53 | 2.26x | $6,451 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 100-7002 PREPARING ROW | 87 STA | $2,700.00 | $6,072.92 | 0.44x | -$293,444 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,200.00 | $11,585.04 | 0.19x | -$56,310 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 250 SY | $115.00 | $49.06 | 2.34x | $16,484 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 328 SY | $40.00 | $6.84 | 5.85x | $10,877 |
| 168-7001 VEGETATIVE WATERING | 103 TGL | $75.00 | $8.43 | 8.89x | $6,856 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
| 100-7002 PREPARING ROW | 87 STA | $3,000.00 | $6,072.92 | 0.49x | -$267,344 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,400.00 | $11,585.04 | 0.21x | -$55,110 |
| 730-7019 FULL - WIDTH MOWING | 2 CYC | $1,250.00 | $4,717.56 | 0.26x | -$6,935 |
DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 342-7001 PFC-C PG76-22 SAC-A | 304 TON | $425.00 | $170.34 | 2.50x | $77,417 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 3,755 SY | $12.00 | $1.43 | 8.40x | $39,693 |
| 134-7001 BACKFILL (TY A) | 15 STA | $1,700.00 | $224.26 | 7.58x | $22,136 |
| 505-7001 TMA (STATIONARY) | 82 DAY | $400.00 | $217.57 | 1.84x | $14,959 |
| 403-7001 TEMPORARY SPL SHORING | 528 SF | $50.00 | $25.56 | 1.96x | $12,904 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 250 SY | $100.00 | $49.06 | 2.04x | $12,734 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 328 SY | $40.00 | $6.84 | 5.85x | $10,877 |
| 354-7074 PLANE ASPH CONC PAV (1.5") | 3,780 SY | $4.00 | $1.35 | 2.95x | $9,999 |
| 164-7076 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 3,755 SY | $3.00 | $0.5910 | 5.08x | $9,046 |
| 500-7001 MOBILIZATION | 1 LS | $110,000.00 | $523,850.32 | 0.21x | -$413,850 |
| 100-7002 PREPARING ROW | 87 STA | $1,850.00 | $6,072.92 | 0.30x | -$367,394 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,500.00 | $11,585.04 | 0.22x | -$54,510 |