US 69, N of IH 20 & S of IH 20 FRTG
0190-05-078 · let Jun 2, 2026 · Smith, Tyler · Safety Improvement Projects
$2,362,671Low bid: ICOS MANAGEMENT, LLC+20.5% vs estimate $1,960,952
$58,393Left on the table2.5% gap to the second bid
5BiddersSpread 14% low to high
93Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ICOS MANAGEMENT, LLC | $2,362,671 | 20.5% | $58,393 | 3+$163,760 | 1-$367,852 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $2,421,064 | +2.5% | 23.5% | $131,781 | 2+$40,066 | 1-$306,523 |
| 3 | LONGVIEW BRIDGE AND ROAD, LTD. | $2,552,845 | +8.0% | 30.2% | $146,035 | 3+$116,007 | 2-$335,190 |
| 4 | BIG CREEK CONSTRUCTION, LTD. | $2,698,880 | +14.2% | 37.6% | $4,716 | 6+$264,042 | 2-$301,390 |
| 5 | EAST TEXAS BRIDGE, INC. | $2,703,596 | +14.4% | 37.9% | 2+$43,929 | 1-$290,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ICOS MANAGEMENT, LLC vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $39,600.00 | $13,182.18 | $11,585.04 | -$105,671 |
| 500-7001 MOBILIZATION | 1 LS | $155,998.50 | $217,326.93 | $523,850.32 | $61,328 |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 4,169 TON | $213.70 | $222.07 | $156.93 | $34,895 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 863 SY | $57.75 | $20.00 | $19.70 | -$32,578 |
| 530-7007 DRIVEWAYS (CONC) (HES) | 667 SY | $116.35 | $160.00 | $122.10 | $29,115 |
| 536-7002 CONC MEDIAN | 292 SY | $91.40 | $165.00 | $92.13 | $21,491 |
| 536-7004 CONC DIRECTIONAL ISLAND | 222 SY | $106.44 | $190.00 | $111.05 | $18,550 |
| 6017-7001 VDS PROSR SYS | 2 EA | $11,825.00 | $20,500.00 | $13,134.89 | $17,350 |
| 505-7001 TMA (STATIONARY) | 68 DAY | $495.00 | $266.18 | $217.57 | -$15,560 |
| 531-7005 CURB RAMPS (TY 1) | 6 EA | $1,509.10 | $4,000.00 | $2,772.62 | $14,945 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 2 EA | $38,885.00 | $31,520.00 | $34,944.96 | -$14,730 |
| 680-7004 REMOVING TRAFFIC SIGNALS | 2 EA | $2.20 | $6,850.00 | $5,086.47 | $13,696 |
| 687-7001 PED POLE ASSEMBLY | 10 EA | $2,024.00 | $3,315.50 | $2,930.76 | $12,915 |
| 684-7010 TRF SIG CBL (TY A)(12 AWG)(5 CONDR) | 8,647 LF | $4.40 | $3.00 | $2.99 | -$12,106 |
| 531-7014 CURB RAMPS (TY 22) | 4 EA | $3,415.04 | $6,000.00 | $4,240.88 | $10,340 |
| 686-7059 INS TRF SIG PL AM(S)1 ARM(55')LUM | 1 EA | $31,020.00 | $39,450.00 | $37,709.54 | $8,430 |
| 688-7001 PED DETECT PUSH BUTTON (APS) | 13 EA | $1,567.50 | $925.25 | $1,056.39 | -$8,349 |
| 344-7001 SP MIXES SP-B PG64-22 | 613 TON | $185.14 | $197.94 | $124.45 | $7,846 |
| 464-7003 RC PIPE (CL III)(18 IN) | 50 LF | $71.50 | $225.00 | $83.08 | $7,675 |
| 618-7061 CONDT (PVC) (SCH 80) (3") (BORE) | 1,210 LF | $30.80 | $24.50 | $26.77 | -$7,623 |
Positive: the low bidder was cheaper on that item. These 20 items account for $61,959 of the $58,393 gap.
ICOS MANAGEMENT, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $39,600.00 | $11,585.04 | 3.42x | $112,060 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 863 SY | $57.75 | $19.70 | 2.93x | $32,835 |
| 505-7001 TMA (STATIONARY) | 68 DAY | $495.00 | $217.57 | 2.28x | $18,865 |
| 500-7001 MOBILIZATION | 1 LS | $155,998.50 | $523,850.32 | 0.30x | -$367,852 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7052 PLANE ASPH CONC PAV(3") | 23,552 SY | $6.00 | $2.92 | 2.05x | $72,531 |
| 6017-7001 VDS PROSR SYS | 2 EA | $25,000.00 | $13,134.89 | 1.90x | $23,730 |
| 536-7004 CONC DIRECTIONAL ISLAND | 222 SY | $200.00 | $111.05 | 1.80x | $19,747 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,500.00 | $11,585.04 | 0.22x | -$36,340 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7007 DRIVEWAYS (CONC) (HES) | 667 SY | $285.00 | $122.10 | 2.33x | $108,655 |
| 536-7004 CONC DIRECTIONAL ISLAND | 222 SY | $420.00 | $111.05 | 3.78x | $68,587 |
| 687-7001 PED POLE ASSEMBLY | 10 EA | $5,750.00 | $2,930.76 | 1.96x | $28,192 |
| 536-7002 CONC MEDIAN | 292 SY | $180.00 | $92.13 | 1.95x | $25,658 |
| 134-7001 BACKFILL (TY A) | 17 STA | $1,300.00 | $224.26 | 5.80x | $18,288 |
| 112-7002 SUBGR WIDEN (DC) | 4.2 STA | $4,500.00 | $1,009.03 | 4.46x | $14,662 |
| 500-7001 MOBILIZATION | 1 LS | $260,000.00 | $523,850.32 | 0.50x | -$263,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,200.00 | $11,585.04 | 0.19x | -$37,540 |