FY 27 Gregg/Rusk Co Traffic Control
6508-86-001 · let Nov 3, 2026 · Gregg, Tyler · Routine Maintenance Project - Sealed
$1,372,080Low bid: HIGHWAY 19 CONSTRUCTION LLC-2.4% vs estimate $1,405,700
$43,870Left on the table3.2% gap to the second bid
4BiddersSpread 47% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HIGHWAY 19 CONSTRUCTION LLC | $1,372,080 | -2.4% | $43,870 | 0 | 1-$499,850 | |
| 2 | FLEX SUPPLY, LLC | $1,415,950 | +3.2% | 0.7% | $583,250 | 1+$117,262 | 1-$495,850 |
| 3 | AWP SAFETY | $1,999,200 | +45.7% | 42.2% | $11,800 | 2+$544,219 | 1-$478,850 |
| 4 | FC TRAFFIC CONTROL, LLC | $2,011,000 | +46.6% | 43.1% | 3+$738,196 | 1-$523,350 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
HIGHWAY 19 CONSTRUCTION LLC vs FLEX SUPPLY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 650 DAY | $320.00 | $410.00 | $229.60 | $58,500 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 3,000 HR | $65.00 | $48.00 | $58.00 | -$51,000 |
| 790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5) | 1,200 HR | $75.00 | $112.00 | $78.14 | $44,400 |
| 790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20) | 2,000 HR | $55.00 | $35.00 | $48.40 | -$40,000 |
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 4,000 HR | $105.00 | $110.50 | $104.45 | $22,000 |
| 505-7001 TMA (STATIONARY) | 600 DAY | $340.00 | $365.00 | $217.57 | $15,000 |
| 7007-7002 FLAGGER CONTROL METHOD (DAY) | 200 DAY | $285.00 | $250.00 | $247.50 | -$7,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $1,000.00 | $100.00 | $844.81 | -$4,500 |
| 500-7001 MOBILIZATION | 1 LS | $24,000.00 | $28,000.00 | $523,850.32 | $4,000 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 250 HR | $85.00 | $100.00 | $78.09 | $3,750 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 100 DAY | $45.00 | $20.00 | $87.82 | -$2,500 |
| 790-7026 LANE CLOSURE(MAINTENANCE)(TYP 7) | 50 HR | $78.00 | $110.00 | $75.83 | $1,600 |
| 790-7025 LANE CLOSURE(MAINTENANCE)(TYP 6) | 100 HR | $75.00 | $90.00 | $62.12 | $1,500 |
| 7007-7001 FLAGGER CONTROL METHOD (HR) | 200 HR | $35.00 | $28.00 | $37.86 | -$1,400 |
| 790-7060 ADDITIONAL LANE CLOSURE ITEM(TYPE 22) | 60 HR | $23.00 | $5.00 | $18.58 | -$1,080 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 10 DAY | $23.00 | $75.00 | $117.34 | $520 |
| 790-7030 LANE CLOSURE(MAINTENANCE)(TYP 11) | 20 HR | $100.00 | $80.00 | $71.51 | -$400 |
| 790-7031 LANE CLOSURE(MAINTENANCE)(TYP 12) | 10 HR | $50.00 | $80.00 | $36.42 | $300 |
| 790-7032 LANE CLOSURE(MAINTENANCE)(TYP 13) | 10 HR | $70.00 | $80.00 | $62.93 | $100 |
| 790-7033 LANE CLOSURE(MAINTENANCE)(TYP 14) | 10 HR | $75.00 | $80.00 | $55.52 | $50 |
Positive: the low bidder was cheaper on that item. These 20 items account for $43,840 of the $43,870 gap.
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $24,000.00 | $523,850.32 | 0.05x | -$499,850 |
FLEX SUPPLY, LLC: unbalanced items
Placed 2AWP SAFETY: unbalanced items
Placed 3FC TRAFFIC CONTROL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 650 DAY | $800.00 | $229.60 | 3.48x | $370,762 |
| 505-7001 TMA (STATIONARY) | 600 DAY | $800.00 | $217.57 | 3.68x | $349,457 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 250 HR | $150.00 | $78.09 | 1.92x | $17,978 |
| 500-7001 MOBILIZATION | 1 LS | $500.00 | $523,850.32 | 0.00x | -$523,350 |