MMC HMA Henderson Co
6500-78-001 · let May 6, 2026 · Henderson, Tyler · Material Maintenance Project
$1,561,000Low bid: BIG CREEK CONSTRUCTION, LTD.-14.5% vs estimate $1,826,000
$193,300Left on the table12.4% gap to the second bid
2BiddersSpread 12% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,561,000 | -14.5% | $193,300 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,754,300 | +12.4% | -3.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP) | 5,000 TON | $94.00 | $112.00 | $96.97 | $90,000 |
| 8017-7020 SP MIXTURES SP-D PG64-22 (DEL)(SITE 1) | 3,500 TON | $112.00 | $124.00 | $115.75 | $42,000 |
| 8017-7011 SP MIXTURES SP-C PG70-22 (DEL)(SITE 1) | 3,500 TON | $116.00 | $127.00 | $122.15 | $38,500 |
| 8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP) | 1,000 TON | $99.00 | $115.00 | $104.70 | $16,000 |
| 8017-7021 SP MIXTURES SP-D PG64-22 (DEL)(SITE 2) | 200 TON | $119.00 | $124.00 | $119.57 | $1,000 |
| 8017-7022 SP MIXTURES SP-D PG64-22 (DEL)(SITE 3) | 200 TON | $119.00 | $124.00 | $121.52 | $1,000 |
| 8017-7023 SP MIXTURES SP-D PG64-22 (DEL)(SITE 4) | 200 TON | $119.00 | $124.00 | $118.56 | $1,000 |
| 8017-7012 SP MIXTURES SP-C PG70-22 (DEL)(SITE 2) | 200 TON | $123.00 | $127.00 | $123.37 | $800 |
| 8017-7013 SP MIXTURES SP-C PG70-22 (DEL)(SITE 3) | 200 TON | $123.00 | $127.00 | $125.42 | $800 |
| 8017-7014 SP MIXTURES SP-C PG70-22 (DEL)(SITE 4) | 200 TON | $123.00 | $127.00 | $122.21 | $800 |
| 8017-7024 SP MIXTURES SP-D PG64-22 (DEL)(SITE 5) | 200 TON | $120.00 | $124.00 | $117.18 | $800 |
| 8017-7015 SP MIXTURES SP-C PG70-22 (DEL)(SITE 5) | 200 TON | $124.00 | $127.00 | $121.18 | $600 |