Bid code 8017-7020

SP MIXTURES SP-D PG64-22 (DEL)(SITE 1) · per TON

‹ All bid codes

$116.58Avg low bid / TON
$119.23Avg of all bids
$121.08Avg engineer's estimate
5Jobs · 32,500 TON

Average low bid by year

YearJobsQuantityAvg lowAvg all
2026425,500$115.10$119.30
202517,000$122.00$119.00

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Jul 1, 20266501-35-001 WoodTyler10,000 TON $115.90LONGVIEW ASPHALT, INC.
May 6, 20266500-76-001 RuskTyler8,000 TON $114.00BIG CREEK CONSTRUCTION, LTD.
May 6, 20266500-78-001 HendersonTyler3,500 TON $112.00BIG CREEK CONSTRUCTION, LTD.
Apr 7, 20266499-43-001 SmithTyler4,000 TON $118.00TEXAS MATERIALS GROUP, INC.
Nov 5, 20256491-57-001 AndersonTyler7,000 TON $122.00BIG CREEK CONSTRUCTION, LTD.