Bid Tab X-ray: 6509-96-001

Nov 4, 2026 · Henderson Sign up free
Set your company to personalize scores

FY 27 Athens AO Traffic Control

6509-96-001 · let Nov 4, 2026 · Henderson, Tyler · Routine Maintenance Project - Sealed

$1,217,140Low bid: HIGHWAY 19 CONSTRUCTION LLC+2.0% vs estimate $1,193,200
$84,860Left on the table7.0% gap to the second bid
4BiddersSpread 39% low to high
18Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1HIGHWAY 19 CONSTRUCTION LLC $1,217,1402.0% $84,860 0 1-$468,850
2FLEX SUPPLY, LLC $1,302,000+7.0%9.1% $334,100 1+$108,828 1-$497,350
3FC TRAFFIC CONTROL, LLC $1,636,100+34.4%37.1% $55,850 4+$414,640 1-$522,850
4AWP SAFETY $1,691,950+39.0%41.8% 2+$328,889 1-$473,850

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

HIGHWAY 19 CONSTRUCTION LLC vs FLEX SUPPLY, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1)4,600 HR $98.00$115.00$104.45 $78,200
500-7001 MOBILIZATION1 LS $55,000.00$26,500.00$523,850.32 -$28,500
505-7001 TMA (STATIONARY)650 DAY $345.00$385.00$217.57 $26,000
790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5)800 HR $88.00$112.00$78.14 $19,200
7007-7002 FLAGGER CONTROL METHOD (DAY)200 DAY $300.00$250.00$247.50 -$10,000
790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2)320 HR $98.00$115.00$78.09 $5,440
500-7033 MOBILIZATION (EMERGENCY)5 EA $1,000.00$100.00$844.81 -$4,500
505-7003 TMA (MOBILE OPERATION)150 DAY $375.00$400.00$229.60 $3,750
790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20)700 HR $45.00$40.00$48.40 -$3,500
790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21)4,000 HR $52.00$52.50$58.00 $2,000
7010-7002 MAINTENANCE SPEED LIMIT SIGNING20 DAY $155.00$75.00$117.34 -$1,600
7007-7001 FLAGGER CONTROL METHOD (HR)200 HR $35.00$30.00$37.86 -$1,000
790-7060 ADDITIONAL LANE CLOSURE ITEM(TYPE 22)40 HR $24.00$5.00$18.58 -$760
790-7030 LANE CLOSURE(MAINTENANCE)(TYP 11)20 HR $100.00$80.00$71.51 -$400
505-7002 TMA (MOBILE OPERATION)100 HR $70.00$73.50$64.00 $350
790-7037 LANE CLOSURE(MAINTENANCE)(TYP 18)30 HR $80.00$90.00$144.65 $300
790-7025 LANE CLOSURE(MAINTENANCE)(TYP 6)20 HR $86.00$80.00$62.12 -$120
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN20 DAY $20.00$20.00$87.82 $0

Positive: the low bidder was cheaper on that item. These 18 items account for $84,860 of the $84,860 gap.

HIGHWAY 19 CONSTRUCTION LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $55,000.00$523,850.320.10x-$468,850

FLEX SUPPLY, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)650 DAY $385.00$217.571.77x$108,828
500-7001 MOBILIZATION1 LS $26,500.00$523,850.320.05x-$497,350

FC TRAFFIC CONTROL, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)650 DAY $600.00$217.572.76x$248,578
505-7003 TMA (MOBILE OPERATION)150 DAY $800.00$229.603.48x$85,560
790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5)800 HR $150.00$78.141.92x$57,490
790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2)320 HR $150.00$78.091.92x$23,011
500-7001 MOBILIZATION1 LS $1,000.00$523,850.320.00x-$522,850

AWP SAFETY: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)650 DAY $615.00$217.572.83x$258,328
505-7003 TMA (MOBILE OPERATION)150 DAY $700.00$229.603.05x$70,560
500-7001 MOBILIZATION1 LS $50,000.00$523,850.320.10x-$473,850