FY 26 Supplemental Illumination
0910-00-165 · let Aug 6, 2026 · Smith, Tyler · Safety Improvement Projects
$655,280Low bid: STRIPING TECHNOLOGY, L.P.-29.3% vs estimate $926,787
$48,552Left on the table7.4% gap to the second bid
10BiddersSpread 51% low to high
15Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPING TECHNOLOGY, L.P. | $655,280 | -29.3% | $48,552 | 1+$12,797 | 2-$547,026 | |
| 2 | NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION | $703,832 | +7.4% | -24.1% | $6,321 | 0 | 3-$521,367 |
| 3 | JASCO | $710,153 | +8.4% | -23.4% | $33,104 | 0 | 5-$559,680 |
| 4 | ALBATROSS CONSTRUCTION LLC | $743,256 | +13.4% | -19.8% | $34,938 | 0 | 1-$467,132 |
| 5 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC | $778,194 | +18.8% | -16.0% | $18,368 | 1+$5,724 | 1-$449,388 |
| 6 | TEXAS TRAFFIC CONTROL SYSTEMS, INC. | $796,563 | +21.6% | -14.1% | $3,023 | ||
| 7 | 3LW CIVIL LLC | $799,586 | +22.0% | -13.7% | $127,564 | ||
| 8 | FLORIDA TRAFFIC CONTROL DEVICES, INC. | $927,150 | +41.5% | 0.0% | $20,285 | ||
| 9 | STRUCTURAL INTEGRITY GROUP LLC | $947,435 | +44.6% | 2.2% | $41,145 | ||
| 10 | CREACOM, INC. | $988,580 | +50.9% | 6.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRIPING TECHNOLOGY, L.P. vs NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $14,250.00 | $55,000.00 | $523,850.32 | $40,750 |
| 610-7200 IN RD IL (TY SA) 50T-12 (400W EQ) LED | 25 EA | $3,750.00 | $5,200.00 | $5,867.03 | $36,250 |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN) | 500 LF | $248.00 | $200.00 | $270.84 | -$24,000 |
| 610-7128 IN RD IL (TY SA) 40T-12 (250W EQ) LED | 21 EA | $3,400.00 | $4,300.00 | $5,496.74 | $18,900 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 5,805 LF | $7.75 | $10.00 | $13.17 | $13,061 |
| 100-7002 PREPARING ROW | 1 STA | $18,870.00 | $7,000.00 | $6,072.92 | -$11,870 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $4,100.00 | $1,800.00 | $11,585.04 | -$11,500 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $300.00 | $140.00 | $217.57 | -$9,600 |
| 505-7003 TMA (MOBILE OPERATION) | 20 DAY | $300.00 | $50.00 | $229.60 | -$5,000 |
| 618-7055 CONDT (PVC) (SCH 80) (2") (BORE) | 4,416 LF | $19.00 | $18.00 | $20.33 | -$4,416 |
| 620-7008 ELEC CONDR (NO.8) INSULATED | 20,442 LF | $2.25 | $2.45 | $2.11 | $4,088 |
| 620-7007 ELEC CONDR (NO.8) BARE | 10,221 LF | $2.00 | $2.20 | $1.94 | $2,044 |
| 624-7002 GROUND BOX TY A (122311)W/APRON | 27 EA | $1,103.00 | $1,075.00 | $1,460.15 | -$756 |
| 610-7201 IN RD IL (TY SA) 50T-12-12(400W EQ)LED | 4 EA | $5,725.00 | $5,800.00 | $7,335.08 | $300 |
| 628-7009 ELC SRV TY A 120/240 060(NS)SS(E)SP(O) | 6 EA | $6,750.00 | $6,800.00 | $8,773.00 | $300 |
Positive: the low bidder was cheaper on that item. These 15 items account for $48,552 of the $48,552 gap.
STRIPING TECHNOLOGY, L.P.: unbalanced items
Placed 1NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION: unbalanced items
Placed 2JASCO: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $1.00 | $11,585.04 | 0.00x | -$57,920 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 5,805 LF | $4.50 | $13.17 | 0.34x | -$50,343 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $1.00 | $217.57 | 0.00x | -$12,994 |
| 505-7003 TMA (MOBILE OPERATION) | 20 DAY | $1.00 | $229.60 | 0.00x | -$4,572 |
ALBATROSS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $56,718.00 | $523,850.32 | 0.11x | -$467,132 |