FY27 Concrete Repair Callout
6504-69-001 · let Sep 16, 2026 · Wood, Tyler · Bridge Preventative Maintenance - Sealed
$667,750Low bid: RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC-31.0% vs estimate $967,500
$168,750Left on the table25.3% gap to the second bid
8BiddersSpread 95% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC | $667,750 | -31.0% | $168,750 | 3+$78,725 | 3-$56,080 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $836,500 | +25.3% | -13.5% | $43,379 | 4+$144,875 | 0 |
| 3 | THE TRUESDELL CORPORATION | $879,879 | +31.8% | -9.1% | $17,621 | 5+$222,862 | 2-$87,580 |
| 4 | WINDING ROAD CONSTRUCTION, INC. | $897,500 | +34.4% | -7.2% | $36,900 | 6+$217,580 | 0 |
| 5 | CROSS PLUS CONSTRUCTION, LLC | $934,400 | +39.9% | -3.4% | $274,900 | 5+$237,465 | 0 |
| 6 | GIBSON & ASSOCIATES, INC. | $1,209,300 | +81.1% | 25.0% | $6,900 | ||
| 7 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $1,216,200 | +82.1% | 25.7% | $87,050 | ||
| 8 | HIGHWAY 19 CONSTRUCTION LLC | $1,303,250 | +95.2% | 34.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 2,400 SF | $137.00 | $160.00 | $150.68 | $55,200 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $100.00 | $5,000.00 | $600.85 | $49,000 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $300.00 | $217.57 | $29,900 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 500 LF | $18.00 | $60.00 | $76.83 | $21,000 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 15 CY | $1,700.00 | $3,000.00 | $827.85 | $19,500 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 1,000 SF | $95.00 | $80.00 | $120.92 | -$15,000 |
| 780-7001 CNC CRACK REPAIR (DISCRETE)(GRAVITY) | 250 LF | $18.00 | $60.00 | $25.51 | $10,500 |
| 401-7001 FLOWABLE BACKFILL | 150 CY | $285.00 | $300.00 | $298.77 | $2,250 |
| 439-7014 MULTI-LAYER POLYMER OVERLAY | 1,000 SY | $102.00 | $100.00 | $40.32 | -$2,000 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 400 SF | $104.00 | $100.00 | $151.82 | -$1,600 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 50 SF | $175.00 | $150.00 | $95.74 | -$1,250 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 50 SF | $175.00 | $200.00 | $192.68 | $1,250 |
Positive: the low bidder was cheaper on that item. These 12 items account for $168,750 of the $168,750 gap.
RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 439-7014 MULTI-LAYER POLYMER OVERLAY | 1,000 SY | $102.00 | $40.32 | 2.53x | $61,680 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 15 CY | $1,700.00 | $827.85 | 2.05x | $13,082 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 50 SF | $175.00 | $95.74 | 1.83x | $3,963 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 500 LF | $18.00 | $76.83 | 0.23x | -$29,415 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $100.00 | $600.85 | 0.17x | -$5,008 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 439-7014 MULTI-LAYER POLYMER OVERLAY | 1,000 SY | $100.00 | $40.32 | 2.48x | $59,680 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $5,000.00 | $600.85 | 8.32x | $43,992 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 15 CY | $3,000.00 | $827.85 | 3.62x | $32,582 |
| 780-7001 CNC CRACK REPAIR (DISCRETE)(GRAVITY) | 250 LF | $60.00 | $25.51 | 2.35x | $8,621 |
THE TRUESDELL CORPORATION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $12,852.90 | $600.85 | 21.39x | $122,521 |
| 439-7014 MULTI-LAYER POLYMER OVERLAY | 1,000 SY | $88.00 | $40.32 | 2.18x | $47,680 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 15 CY | $2,300.00 | $827.85 | 2.78x | $22,082 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 50 SF | $525.00 | $192.68 | 2.72x | $16,616 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 50 SF | $375.00 | $95.74 | 3.92x | $13,963 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 1,000 SF | $55.00 | $120.92 | 0.45x | -$65,923 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
WINDING ROAD CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 401-7001 FLOWABLE BACKFILL | 150 CY | $750.00 | $298.77 | 2.51x | $67,685 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $5,500.00 | $600.85 | 9.15x | $48,992 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $700.00 | $217.57 | 3.22x | $48,243 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 15 CY | $2,800.00 | $827.85 | 3.38x | $29,582 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 50 SF | $500.00 | $192.68 | 2.59x | $15,366 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 50 SF | $250.00 | $95.74 | 2.61x | $7,713 |
CROSS PLUS CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 401-7001 FLOWABLE BACKFILL | 150 CY | $1,100.00 | $298.77 | 3.68x | $120,185 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $5,500.00 | $600.85 | 9.15x | $48,992 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $550.00 | $217.57 | 2.53x | $33,243 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 15 CY | $2,750.00 | $827.85 | 3.32x | $28,832 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 50 SF | $220.00 | $95.74 | 2.30x | $6,213 |