OfficialCCSJ 2635-03-031 · lets Tuesday, Dec 1, 2026 · Potter, Randall, Amarillo · FM 2590 · Preventive Maintenance
Where the low bid should land
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $3,147,079 | -28.8% | 90% |
| $3,626,623 | -17.9% | 75% |
| $4,032,661 | -8.7% | 50% |
| $4,439,289 | +0.5% | 25% |
| $5,022,836 | +13.7% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bids| Plan holder | Chance they bid | Bids | Wins | Avg bid vs est. | Their typical bid here |
|---|---|---|---|---|---|
| J. LEE MILLIGAN, INC.Bidders | 60% | 49 | 11 | 10.6% | $4,886,059 |
| GILVIN-TERRILL, LTD.Bidders | 60% | 74 | 6 | 23.4% | $5,452,582 |
| CUTLER REPAVING, INC.Bidders | 3% | 0 | 0 |
Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| Aug 2026 | 6505-55-001 | HutchinsonAmarillo | Material Maintenance Project | 2 | $4,090,043 | $4,484,629+9.6% | NSG LOGISTICS, LLC |
| May 2026 | 6497-68-001 | PotterAmarillo | Routine Maintenance Project - Sealed | 1 | $6,607,850 | $6,531,750-1.2% | J. LEE MILLIGAN, INC. |
| Aug 2026 | 0784-02-011 | JasperBeaumont | Overlay | 1 | $3,763,964 | $3,276,381-13.0% | TEXAS MATERIALS GROUP, INC. |
| Nov 2026 | 6510-98-001 | GrayAmarillo | Material Maintenance Project | 3 | $5,284,907 | $3,073,285-41.8% | L A FULLER & SONS CONSTRUCTION, LTD. |
| Aug 2025 | 6486-56-001 | MooreAmarillo | Material Maintenance Project | 1 | $2,970,468 | $2,695,200-9.3% | NSG LOGISTICS, LLC |
| Nov 2025 | 6489-44-001 | CarsonAmarillo | Material Maintenance Project | 1 | $2,303,132 | $2,264,271-1.7% | VOLCANIC STONE CO. |
| Nov 2026 | 6509-25-001 | HarrisHouston | Routine Maintenance Project - Sealed | 2 | $3,805,043 | $4,495,312+18.1% | SWEEPING CORPORATION OF AMERICA, LLC |
| Nov 2026 | 6509-27-001 | HarrisHouston | Routine Maintenance Project - Sealed | 2 | $3,636,811 | $4,204,328+15.6% | SWEEPING CORPORATION OF AMERICA, LLC |
| Jun 2026 | 0133-08-038 | YoungWichita Falls | Overlay | 2 | $2,626,973 | $3,044,169+15.9% | ZACK BURKETT CO. |
| Jul 2026 | 0508-02-140 | ChambersBeaumont | Overlay | 3 | $3,459,416 | $3,332,075-3.7% | DURWOOD GREENE CONSTRUCTION CO. |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.