Bid Tab X-ray: 6497-68-001

May 6, 2026 · Potter Sign up free
Set your company to personalize scores

General Maintenance Amarillo AE FY 26

6497-68-001 · let May 6, 2026 · Potter, Amarillo · Routine Maintenance Project - Sealed

$6,531,750Low bid: J. LEE MILLIGAN, INC.-1.2% vs estimate $6,607,850
—Left on the tableOnly one bidder
1Bidders
16Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1J. LEE MILLIGAN, INC. $6,531,750-1.2% 5+$543,622 1-$156,516

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 1 bidders.

J. LEE MILLIGAN, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7003 MOBILIZATION (CALLOUT 1)10 EA $21,000.00$599.9335.00x$204,001
351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")500 SY $285.00$35.018.14x$124,993
354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2")20,000 SY $6.85$2.243.06x$92,264
432-7004 RIPRAP (CONC)(CL A)100 CY $1,335.00$469.092.85x$86,591
531-7001 CONC SIDEWALKS (4")400 SY $160.00$70.572.27x$35,774
500-7004 MOBILIZATION (CALLOUT 2)10 EA $3,300.00$18,951.600.17x-$156,516