SH 114, FM 2178N to Ave C
0133-08-038 · let Jun 2, 2026 · Young, Wichita Falls · Overlay
$3,044,169Low bid: ZACK BURKETT CO.+15.9% vs estimate $2,626,973
$128,288Left on the table4.2% gap to the second bid
2BiddersSpread 4% low to high
115Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ZACK BURKETT CO. | $3,044,169 | 15.9% | $128,288 | 2+$123,925 | 1-$313,850 | |
| 2 | A. L. HELMCAMP, INC. | $3,172,457 | +4.2% | 20.8% | 1+$40,459 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
ZACK BURKETT CO. vs A. L. HELMCAMP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 10,002 SY | $40.00 | $60.00 | $35.01 | $200,040 |
| 500-7001 MOBILIZATION | 1 LS | $210,000.00 | $280,000.00 | $523,850.32 | $70,000 |
| 341-7054 D-GR HMA TY-D SAC-B PG70-28 | 12,404 TON | $145.20 | $140.00 | $124.60 | -$64,501 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 36,193 SY | $4.22 | $3.10 | $2.13 | -$40,536 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $297.50 | $100.00 | $217.57 | -$19,750 |
| 134-7002 BACKFILL (TY B) | 175 STA | $200.00 | $310.00 | $206.94 | $19,250 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 90 CY | $50.00 | $185.00 | $16.96 | $12,150 |
| 341-7082 TACK COAT | 6,478 GAL | $5.00 | $6.50 | $3.93 | $9,717 |
| 104-7017 REMOV CONC (CURB & GUTTER) | 600 LF | $14.30 | $30.00 | $8.04 | $9,420 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 4 EA | $5,950.00 | $3,600.00 | $3,190.07 | -$9,400 |
| 479-7005 ADJUSTING MANHOLES (CAP) | 5 EA | $4,165.00 | $2,500.00 | $2,566.51 | -$8,325 |
| 529-7009 CONC CURB & GUTTER (TY II) | 600 LF | $113.05 | $100.00 | $32.57 | -$7,830 |
| 164-7009 DRILL SEED (PERM_RURAL_SAND) | 19,255 SY | $0.5800 | $0.2000 | $0.1844 | -$7,317 |
| 451-7020 RETROFIT RAIL (TY T631) | 75 LF | $178.50 | $100.00 | $110.49 | -$5,888 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 262.5 LF | $52.36 | $30.00 | $25.60 | -$5,870 |
| 164-7013 DRILL SEED (TEMP_WARM) | 9,628 SY | $0.6100 | $0.1800 | $0.1903 | -$4,140 |
| 164-7014 DRILL SEED (TEMP_COOL) | 9,628 SY | $0.6100 | $0.1800 | $0.1596 | -$4,140 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 48,916 LF | $0.6200 | $0.5500 | $0.4757 | -$3,424 |
| 420-7148 CLASS K CONCRETE (MISC) | 4 CY | $4,760.00 | $4,000.00 | $1,507.23 | -$3,040 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 32,894 LF | $0.6200 | $0.5500 | $0.4986 | -$2,303 |
Positive: the low bidder was cheaper on that item. These 20 items account for $134,114 of the $128,288 gap.
ZACK BURKETT CO.: unbalanced items
Placed 1A. L. HELMCAMP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7009 CONC CURB & GUTTER (TY II) | 600 LF | $100.00 | $32.57 | 3.07x | $40,459 |