Overlay
OfficialCCSJ 0011-06-050 · lets Wednesday, Dec 2, 2026 · Jones, Shackelford, Abilene · FM 1084, FM 1226, FM 576, US 180 · Preventive Maintenance
Where the low bid should land
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $1,913,280 | -31.2% | 90% |
| $2,182,055 | -21.5% | 75% |
| $2,447,057 | -12.0% | 50% |
| $2,720,085 | -2.2% | 25% |
| $3,010,561 | +8.2% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bids| Plan holder | Chance they bid | Bids | Wins | Avg bid vs est. | Their typical bid here |
|---|---|---|---|---|---|
| BONTKE BROTHERS CONSTRUCTION COMPANYBidders | 60% | 16 | 2 | 13.3% | $3,152,317 |
| ZACK BURKETT CO.Bidders | 60% | 74 | 41 | -0.7% | $2,761,459 |
| BIG CREEK CONSTRUCTION, LTD.Bidders | 60% | 239 | 106 | -4.9% | $2,645,558 |
| A. L. HELMCAMP, INC.Bidders | 60% | 210 | 38 | 8.8% | $3,027,520 |
| LONE STAR PAVING COMPANYBidders | 60% | 160 | 44 | -1.0% | $2,752,237 |
| CK NEWBERRY, LLCBidders | 60% | 261 | 34 | 9.9% | $3,056,730 |
| FOUTSCO PAVING COMPANY, LLCBidders | 60% | 102 | 32 | -4.3% | $2,660,505 |
Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| Nov 2025 | 0069-01-062 | HowardAbilene | Overlay | 5 | $2,777,235 | $2,026,248-27.0% | RK HALL, LLC |
| Sep 2026 | 0337-03-020 | WilliamsonAustin | Overlay | 4 | $2,537,276 | $2,174,856-14.3% | LONE STAR PAVING COMPANY |
| Jan 2026 | 0975-02-023 | JonesAbilene | Safety Improvement Projects | 5 | $2,746,601 | $2,611,155-4.9% | J. H. STRAIN & SONS, INC. |
| Oct 2026 | 0249-02-026 | ArcherWichita Falls | Overlay | 5 | $3,056,397 | $3,682,675+20.5% | OVERLAND CORPORATION |
| Apr 2026 | 0337-02-054 | WilliamsonAustin | Overlay | 4 | $2,566,159 | $2,388,456-6.9% | LONE STAR PAVING COMPANY |
| Nov 2026 | 0045-09-113 | LamarParis | Overlay | 5 | $3,685,991 | $3,510,998-4.7% | DRAKE COMPANIES LLC |
| Aug 2026 | 0363-03-061 | TarrantFort Worth | Overlay | 5 | $2,924,978 | $3,202,525+9.5% | FOUTSCO PAVING COMPANY, LLC |
| Feb 2026 | 1549-03-031 | San PatricioCorpus Christi | Overlay | 4 | $2,494,844 | $2,477,701-0.7% | ANDERSON COLUMBIA CO., INC. |
| Aug 2026 | 0208-01-026 | HarrisonAtlanta | Overlay | 5 | $3,307,700 | $3,320,428+0.4% | MADDEN CONTRACTING COMPANY, LLC. |
| Jan 2026 | 0492-04-047 | SmithTyler | Overlay | 4 | $2,636,546 | $3,056,756+15.9% | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.