FM 1069 San Pat overlay pt 2
1549-03-031 · let Feb 4, 2026 · San Patricio, Corpus Christi · Overlay
$2,477,701Low bid: ANDERSON COLUMBIA CO., INC.-0.7% vs estimate $2,494,844
$35,335Left on the table1.4% gap to the second bid
4BiddersSpread 15% low to high
82Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ANDERSON COLUMBIA CO., INC. | $2,477,701 | -0.7% | $35,335 | 0 | 4-$1,316,904 | |
| 2 | HUNTER INDUSTRIES, LTD. | $2,513,036 | +1.4% | 0.7% | $220,194 | 0 | 4-$1,249,468 |
| 3 | CK NEWBERRY, LLC | $2,733,230 | +10.3% | 9.6% | $114,663 | 0 | 5-$1,115,658 |
| 4 | J E CONSTRUCTION SERVICES, LLC | $2,847,893 | +14.9% | 14.2% | 2+$67,298 | 3-$1,157,238 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
ANDERSON COLUMBIA CO., INC. vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $65,000.00 | $170,017.22 | $523,850.32 | $105,017 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $12,000.00 | $1,910.33 | $11,585.04 | -$70,628 |
| 354-7003 PLANE & TEXT ASPH CONC PAV(0" TO 3") | 94,617 SY | $1.45 | $2.09 | $2.75 | $60,555 |
| 530-7010 DRIVEWAYS (ACP) | 2,878 SY | $45.00 | $30.80 | $54.96 | -$40,868 |
| 316-7212 AGGR (TY-PB, GR-4S OR 4)(SAC-B) | 873 CY | $165.00 | $132.30 | $125.13 | -$28,547 |
| 100-7002 PREPARING ROW | 141 STA | $175.00 | $304.70 | $6,072.92 | $18,288 |
| 351-7004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(5") | 2,449 SY | $42.00 | $36.38 | $35.89 | -$13,763 |
| 505-7003 TMA (MOBILE OPERATION) | 107 DAY | $100.00 | $189.44 | $229.60 | $9,570 |
| 316-7070 ASPH(AC-15P, HFRS-2P OR CRS-2P) | 33,126 GAL | $3.60 | $3.41 | $3.32 | -$6,294 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 526 LF | $9.00 | $19.25 | $5.23 | $5,392 |
| 529-7002 CONC CURB (TY II) | 691 LF | $18.00 | $23.00 | $26.45 | $3,455 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 25,684 LF | $0.7500 | $0.6600 | $0.5014 | -$2,312 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 1,042 LF | $18.00 | $16.00 | $13.72 | -$2,084 |
| 505-7001 TMA (STATIONARY) | 107 DAY | $100.00 | $81.19 | $217.57 | -$2,013 |
| 658-7078 REMOVE DELIN & OBJECT MARKER ASSMS | 107 EA | $11.00 | $28.00 | $23.28 | $1,819 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 13,120 TON | $114.50 | $114.40 | $116.75 | -$1,312 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 3,882 EA | $1.30 | $1.63 | $0.5715 | $1,281 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 2,105 EA | $1.20 | $1.63 | $1.03 | $905 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 526 LF | $3.00 | $4.50 | $1.29 | $789 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 25,684 LF | $0.3500 | $0.3200 | $0.2770 | -$771 |
Positive: the low bidder was cheaper on that item. These 20 items account for $38,480 of the $35,335 gap.
ANDERSON COLUMBIA CO., INC.: unbalanced items
Placed 1HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 141 STA | $304.70 | $6,072.92 | 0.05x | -$813,319 |
| 500-7001 MOBILIZATION | 1 LS | $170,017.22 | $523,850.32 | 0.32x | -$353,833 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,910.33 | $11,585.04 | 0.16x | -$67,723 |
| 505-7001 TMA (STATIONARY) | 107 DAY | $81.19 | $217.57 | 0.37x | -$14,593 |
CK NEWBERRY, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 141 STA | $50.00 | $6,072.92 | 0.01x | -$849,232 |
| 354-7003 PLANE & TEXT ASPH CONC PAV(0" TO 3") | 94,617 SY | $1.00 | $2.75 | 0.36x | -$165,684 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,500.00 | $11,585.04 | 0.22x | -$63,595 |
| 505-7003 TMA (MOBILE OPERATION) | 107 DAY | $50.00 | $229.60 | 0.22x | -$19,217 |
| 505-7001 TMA (STATIONARY) | 107 DAY | $50.00 | $217.57 | 0.23x | -$17,930 |
J E CONSTRUCTION SERVICES, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 107 DAY | $685.00 | $229.60 | 2.98x | $48,728 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 25,684 LF | $1.00 | $0.2770 | 3.61x | $18,570 |
| 100-7002 PREPARING ROW | 141 STA | $224.00 | $6,072.92 | 0.04x | -$824,698 |
| 500-7001 MOBILIZATION | 1 LS | $260,156.00 | $523,850.32 | 0.50x | -$263,694 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,750.00 | $11,585.04 | 0.15x | -$68,845 |