SH 43 from US 59 to SL 390

0208-01-026 · let Aug 6, 2026 · Harrison, Atlanta · Overlay

$3,320,428Low bid: MADDEN CONTRACTING COMPANY, LLC.+0.4% vs estimate $3,307,700
$70,403Left on the table2.1% gap to the second bid
5BiddersSpread 27% low to high
84Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1MADDEN CONTRACTING COMPANY, LLC. $3,320,4280.4% $70,403 0 4-$602,188
2LONGVIEW BRIDGE AND ROAD, LTD. $3,390,831+2.1%2.5% $51,334 2+$83,031 4-$747,360
3HIGHWAY 19 CONSTRUCTION LLC $3,442,165+3.7%4.1% $610,489 1+$18,704 1-$32,925
4EAST TEXAS BRIDGE, INC. $4,052,654+22.1%22.5% $180,345 1+$296,353 0
5DREWERY CONSTRUCTION COMPANY, INCORPORATED $4,232,999+27.5%28.0% 6+$365,636 3-$308,223

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

MADDEN CONTRACTING COMPANY, LLC. vs LONGVIEW BRIDGE AND ROAD, LTD., biggest item swings
ItemQtyLow2ndMarket2nd minus low
3019-7001 COMPOSITE GEOGRID FOR ASPHALT OVERLAY65,423 SY $4.40$6.05$3.97 $107,948
500-7001 MOBILIZATION1 LS $180,000.00$100,000.00$523,850.32 -$80,000
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)28,617 LF $0.0100$2.65$0.8371 $75,549
354-7051 PLANE ASPH CONC PAV(2")70,484 SY $1.85$1.00$1.86 -$59,911
100-7002 PREPARING ROW46.4 STA $1,725.00$550.00$6,072.92 -$54,520
344-7030 SP MIXES SP-C SAC-A PG76-2210,606 TON $170.00$175.00$138.38 $53,030
530-7010 DRIVEWAYS (ACP)35 SY $100.00$945.00$54.96 $29,575
354-7076 PLANE ASPH CONC PAV (1" TO 2")25,922 SY $1.85$1.00$1.92 -$22,034
351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")3,793 SY $50.00$45.50$35.01 -$17,069
134-7003 BACKFILL (TY C)102.4 STA $263.00$101.00$167.35 -$16,589
344-7077 TACK COAT3,575 GAL $0.0100$4.00$3.25 $14,264
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING5 MO $5,000.00$2,310.00$11,585.04 -$13,450
505-7001 TMA (STATIONARY)130 DAY $300.00$200.00$217.57 -$13,000
150-7001 BLADING109.69 STA $186.00$73.00$152.64 -$12,395
466-7190 WINGWALL (PW - 2) (HW=6 FT)2 EA $15,889.00$9,915.00$20,350.40 -$11,948
496-7007 REMOV STR (PIPE)308 LF $8.00$45.00$23.96 $11,396
662-7065 WK ZN PAV MRK REMOV (W)6"(BRK)4,140 LF $0.0100$2.65$1.02 $10,930
467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)89 EA $910.00$1,015.00$1,176.76 $9,345
530-7008 DRIVEWAYS (CONC) (TY 1)37 SY $182.00$400.00$141.54 $8,066
467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P)42 EA $1,250.00$1,440.00$1,883.43 $7,980

Positive: the low bidder was cheaper on that item. These 20 items account for $27,167 of the $70,403 gap.

MADDEN CONTRACTING COMPANY, LLC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $180,000.00$523,850.320.34x-$343,850
100-7002 PREPARING ROW46.4 STA $1,725.00$6,072.920.28x-$201,744
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING5 MO $5,000.00$11,585.040.43x-$32,925
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)28,617 LF $0.0100$0.83710.01x-$23,669

LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)28,617 LF $2.65$0.83713.17x$51,880
530-7010 DRIVEWAYS (ACP)35 SY $945.00$54.9617.20x$31,152
500-7001 MOBILIZATION1 LS $100,000.00$523,850.320.19x-$423,850
100-7002 PREPARING ROW46.4 STA $550.00$6,072.920.09x-$256,264
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING5 MO $2,310.00$11,585.040.20x-$46,375
466-7190 WINGWALL (PW - 2) (HW=6 FT)2 EA $9,915.00$20,350.400.49x-$20,871

HIGHWAY 19 CONSTRUCTION LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
134-7003 BACKFILL (TY C)102.4 STA $350.00$167.352.09x$18,704
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING5 MO $5,000.00$11,585.040.43x-$32,925

EAST TEXAS BRIDGE, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
3019-7001 COMPOSITE GEOGRID FOR ASPHALT OVERLAY65,423 SY $8.50$3.972.14x$296,353

DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
3019-7001 COMPOSITE GEOGRID FOR ASPHALT OVERLAY65,423 SY $6.95$3.971.75x$194,947
505-7001 TMA (STATIONARY)130 DAY $650.00$217.572.99x$56,216
464-7003 RC PIPE (CL III)(18 IN)154 LF $350.00$83.084.21x$41,105
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)28,617 LF $1.75$0.83712.09x$26,124
134-7003 BACKFILL (TY C)102.4 STA $400.00$167.352.39x$23,824
496-7007 REMOV STR (PIPE)308 LF $100.00$23.964.17x$23,419
100-7002 PREPARING ROW46.4 STA $1,050.00$6,072.920.17x-$233,064
3019-7002 TACK COAT9,326 GAL $0.0100$4.460.00x-$41,459
466-7190 WINGWALL (PW - 2) (HW=6 FT)2 EA $3,500.00$20,350.400.17x-$33,701