SH 43 from US 59 to SL 390
0208-01-026 · let Aug 6, 2026 · Harrison, Atlanta · Overlay
$3,320,428Low bid: MADDEN CONTRACTING COMPANY, LLC.+0.4% vs estimate $3,307,700
$70,403Left on the table2.1% gap to the second bid
5BiddersSpread 27% low to high
84Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MADDEN CONTRACTING COMPANY, LLC. | $3,320,428 | 0.4% | $70,403 | 0 | 4-$602,188 | |
| 2 | LONGVIEW BRIDGE AND ROAD, LTD. | $3,390,831 | +2.1% | 2.5% | $51,334 | 2+$83,031 | 4-$747,360 |
| 3 | HIGHWAY 19 CONSTRUCTION LLC | $3,442,165 | +3.7% | 4.1% | $610,489 | 1+$18,704 | 1-$32,925 |
| 4 | EAST TEXAS BRIDGE, INC. | $4,052,654 | +22.1% | 22.5% | $180,345 | 1+$296,353 | 0 |
| 5 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $4,232,999 | +27.5% | 28.0% | 6+$365,636 | 3-$308,223 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
MADDEN CONTRACTING COMPANY, LLC. vs LONGVIEW BRIDGE AND ROAD, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 3019-7001 COMPOSITE GEOGRID FOR ASPHALT OVERLAY | 65,423 SY | $4.40 | $6.05 | $3.97 | $107,948 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $100,000.00 | $523,850.32 | -$80,000 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 28,617 LF | $0.0100 | $2.65 | $0.8371 | $75,549 |
| 354-7051 PLANE ASPH CONC PAV(2") | 70,484 SY | $1.85 | $1.00 | $1.86 | -$59,911 |
| 100-7002 PREPARING ROW | 46.4 STA | $1,725.00 | $550.00 | $6,072.92 | -$54,520 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 10,606 TON | $170.00 | $175.00 | $138.38 | $53,030 |
| 530-7010 DRIVEWAYS (ACP) | 35 SY | $100.00 | $945.00 | $54.96 | $29,575 |
| 354-7076 PLANE ASPH CONC PAV (1" TO 2") | 25,922 SY | $1.85 | $1.00 | $1.92 | -$22,034 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 3,793 SY | $50.00 | $45.50 | $35.01 | -$17,069 |
| 134-7003 BACKFILL (TY C) | 102.4 STA | $263.00 | $101.00 | $167.35 | -$16,589 |
| 344-7077 TACK COAT | 3,575 GAL | $0.0100 | $4.00 | $3.25 | $14,264 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $5,000.00 | $2,310.00 | $11,585.04 | -$13,450 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $300.00 | $200.00 | $217.57 | -$13,000 |
| 150-7001 BLADING | 109.69 STA | $186.00 | $73.00 | $152.64 | -$12,395 |
| 466-7190 WINGWALL (PW - 2) (HW=6 FT) | 2 EA | $15,889.00 | $9,915.00 | $20,350.40 | -$11,948 |
| 496-7007 REMOV STR (PIPE) | 308 LF | $8.00 | $45.00 | $23.96 | $11,396 |
| 662-7065 WK ZN PAV MRK REMOV (W)6"(BRK) | 4,140 LF | $0.0100 | $2.65 | $1.02 | $10,930 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 89 EA | $910.00 | $1,015.00 | $1,176.76 | $9,345 |
| 530-7008 DRIVEWAYS (CONC) (TY 1) | 37 SY | $182.00 | $400.00 | $141.54 | $8,066 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 42 EA | $1,250.00 | $1,440.00 | $1,883.43 | $7,980 |
Positive: the low bidder was cheaper on that item. These 20 items account for $27,167 of the $70,403 gap.
MADDEN CONTRACTING COMPANY, LLC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |
| 100-7002 PREPARING ROW | 46.4 STA | $1,725.00 | $6,072.92 | 0.28x | -$201,744 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $5,000.00 | $11,585.04 | 0.43x | -$32,925 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 28,617 LF | $0.0100 | $0.8371 | 0.01x | -$23,669 |
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 28,617 LF | $2.65 | $0.8371 | 3.17x | $51,880 |
| 530-7010 DRIVEWAYS (ACP) | 35 SY | $945.00 | $54.96 | 17.20x | $31,152 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 100-7002 PREPARING ROW | 46.4 STA | $550.00 | $6,072.92 | 0.09x | -$256,264 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $2,310.00 | $11,585.04 | 0.20x | -$46,375 |
| 466-7190 WINGWALL (PW - 2) (HW=6 FT) | 2 EA | $9,915.00 | $20,350.40 | 0.49x | -$20,871 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 3EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 3019-7001 COMPOSITE GEOGRID FOR ASPHALT OVERLAY | 65,423 SY | $8.50 | $3.97 | 2.14x | $296,353 |
DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 3019-7001 COMPOSITE GEOGRID FOR ASPHALT OVERLAY | 65,423 SY | $6.95 | $3.97 | 1.75x | $194,947 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $650.00 | $217.57 | 2.99x | $56,216 |
| 464-7003 RC PIPE (CL III)(18 IN) | 154 LF | $350.00 | $83.08 | 4.21x | $41,105 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 28,617 LF | $1.75 | $0.8371 | 2.09x | $26,124 |
| 134-7003 BACKFILL (TY C) | 102.4 STA | $400.00 | $167.35 | 2.39x | $23,824 |
| 496-7007 REMOV STR (PIPE) | 308 LF | $100.00 | $23.96 | 4.17x | $23,419 |
| 100-7002 PREPARING ROW | 46.4 STA | $1,050.00 | $6,072.92 | 0.17x | -$233,064 |
| 3019-7002 TACK COAT | 9,326 GAL | $0.0100 | $4.46 | 0.00x | -$41,459 |
| 466-7190 WINGWALL (PW - 2) (HW=6 FT) | 2 EA | $3,500.00 | $20,350.40 | 0.17x | -$33,701 |