US 281, FM 1954 to Lake Creek
0249-02-026 · let Oct 6, 2026 · Archer, Wichita Falls · Overlay
$3,682,675Low bid: OVERLAND CORPORATION+20.5% vs estimate $3,056,397
$205,586Left on the table5.6% gap to the second bid
5BiddersSpread 51% low to high
87Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | OVERLAND CORPORATION | $3,682,675 | 20.5% | $205,586 | 4+$146,598 | 1-$72,695 | |
| 2 | ZACK BURKETT CO. | $3,888,262 | +5.6% | 27.2% | $218,730 | 3+$114,790 | 0 |
| 3 | JAGOE-PUBLIC COMPANY | $4,106,991 | +11.5% | 34.4% | $64,085 | 6+$402,434 | 0 |
| 4 | A. L. HELMCAMP, INC. | $4,171,076 | +13.3% | 36.5% | $1,395,056 | 4+$167,462 | 0 |
| 5 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $5,566,132 | +51.1% | 82.1% | 11+$1,286,980 | 1-$53,095 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
OVERLAND CORPORATION vs ZACK BURKETT CO., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 4,600 SY | $80.00 | $91.75 | $60.19 | $54,050 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,200.00 | $7,400.00 | $11,585.04 | $43,400 |
| 346-7010 STONE-MTRX-ASPH SMA-D SAC-A PG76-28 | 7,196 TON | $172.00 | $177.30 | $170.42 | $38,139 |
| 341-7054 D-GR HMA TY-D SAC-B PG70-28 | 5,581 TON | $140.00 | $134.50 | $124.60 | -$30,696 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 686 CY | $115.00 | $71.40 | $16.96 | -$29,910 |
| 134-7002 BACKFILL (TY B) | 235 STA | $140.00 | $262.00 | $206.94 | $28,670 |
| 420-7148 CLASS K CONCRETE (MISC) | 7 CY | $2,280.00 | $5,932.15 | $1,507.23 | $25,565 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 20 EA | $3,100.00 | $4,284.00 | $3,190.07 | $23,680 |
| 500-7001 MOBILIZATION | 1 LS | $357,500.00 | $336,000.00 | $523,850.32 | -$21,500 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $9,900.00 | $6,500.00 | $9,253.78 | -$20,400 |
| 104-7003 REMOV CONC (MOWSTRIP) | 1,460 SY | $40.00 | $27.40 | $20.48 | -$18,396 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,650 LF | $25.00 | $35.70 | $7.54 | $17,655 |
| 505-7003 TMA (MOBILE OPERATION) | 18 DAY | $950.00 | $0.0100 | $229.60 | -$17,100 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 1,400 LF | $27.40 | $38.08 | $25.60 | $14,952 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 8 EA | $1,680.00 | $3,064.25 | $2,218.70 | $11,074 |
| 420-7055 CL C CONC (RAC-R) | 5.6 CY | $2,442.86 | $4,337.55 | $1,909.49 | $10,610 |
| 451-7020 RETROFIT RAIL (TY T631) | 140 LF | $75.00 | $148.75 | $110.49 | $10,325 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 5,040 SY | $6.50 | $4.55 | $2.13 | -$9,828 |
| 505-7001 TMA (STATIONARY) | 194 DAY | $191.67 | $240.00 | $217.57 | $9,376 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 44,472 LF | $0.5300 | $0.7300 | $0.4757 | $8,894 |
Positive: the low bidder was cheaper on that item. These 20 items account for $148,562 of the $205,586 gap.
OVERLAND CORPORATION: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7003 EMBANK (FNL)(OC)(TY B) | 686 CY | $115.00 | $16.96 | 6.78x | $67,253 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,650 LF | $25.00 | $7.54 | 3.32x | $28,817 |
| 104-7003 REMOV CONC (MOWSTRIP) | 1,460 SY | $40.00 | $20.48 | 1.95x | $28,504 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 5,040 SY | $6.50 | $2.13 | 3.05x | $22,024 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,200.00 | $11,585.04 | 0.10x | -$72,695 |
ZACK BURKETT CO.: unbalanced items
Placed 2JAGOE-PUBLIC COMPANY: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 204 CY | $1,200.00 | $616.83 | 1.95x | $118,966 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $28,000.00 | $11,585.04 | 2.42x | $114,905 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 686 CY | $135.00 | $16.96 | 7.96x | $80,973 |
| 451-7006 RETROFIT RAIL (TY T222) | 96 LF | $600.00 | $217.20 | 2.76x | $36,749 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,650 LF | $25.00 | $7.54 | 3.32x | $28,817 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 5,040 SY | $6.50 | $2.13 | 3.05x | $22,024 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,650 LF | $55.00 | $7.54 | 7.30x | $78,317 |
| 451-7006 RETROFIT RAIL (TY T222) | 96 LF | $600.00 | $217.20 | 2.76x | $36,749 |
| 420-7148 CLASS K CONCRETE (MISC) | 7 CY | $5,800.00 | $1,507.23 | 3.85x | $30,049 |
| 420-7055 CL C CONC (RAC-R) | 5.6 CY | $5,900.00 | $1,909.49 | 3.09x | $22,347 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 4,600 SY | $120.00 | $60.19 | 1.99x | $275,120 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 686 CY | $350.00 | $16.96 | 20.63x | $228,463 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 204 CY | $1,500.00 | $616.83 | 2.43x | $180,166 |
| 6041-7002 SENSOR INSTALLATION | 2 EA | $75,000.00 | $4,839.97 | 15.50x | $140,320 |
| 104-7003 REMOV CONC (MOWSTRIP) | 1,460 SY | $100.00 | $20.48 | 4.88x | $116,104 |
| 451-7006 RETROFIT RAIL (TY T222) | 96 LF | $1,200.00 | $217.20 | 5.52x | $94,349 |
| 6041-7001 LOOP INSTALLATION | 175 LF | $500.00 | $17.71 | 28.23x | $84,401 |
| 134-7002 BACKFILL (TY B) | 235 STA | $475.00 | $206.94 | 2.30x | $62,994 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 5,040 SY | $10.00 | $2.13 | 4.69x | $39,664 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,650 LF | $30.00 | $7.54 | 3.98x | $37,067 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $4,000.00 | $11,585.04 | 0.35x | -$53,095 |