FM 756, SL 323 - GRANDE BLVD
0492-04-047 · let Jan 6, 2026 · Smith, Tyler · Overlay
$3,056,756Low bid: DREWERY CONSTRUCTION COMPANY, INCORPORATED+15.9% vs estimate $2,636,546
$114,229Left on the table3.7% gap to the second bid
4BiddersSpread 31% low to high
64Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $3,056,756 | 15.9% | $114,229 | 2+$88,278 | 3-$4,361,127 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $3,170,985 | +3.7% | 20.3% | $174,628 | 2+$103,851 | 2-$4,163,866 |
| 3 | LONGVIEW BRIDGE AND ROAD, LTD. | $3,345,613 | +9.4% | 26.9% | $656,606 | 3+$166,532 | 1-$4,061,611 |
| 4 | TEXAS MATERIALS GROUP, INC. | $4,002,219 | +30.9% | 51.8% | 4+$474,587 | 1-$4,061,611 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
DREWERY CONSTRUCTION COMPANY, INCORPORATED vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 800-7001 NO. OF WORKING DAYS | 7,500 $/D | $45.00 | $60.00 | $612.55 | $112,500 |
| 3005-7001 MEMBRANE UNDERSEAL | 16,890 GAL | $0.0100 | $5.00 | $4.76 | $84,281 |
| 100-7002 PREPARING ROW | 3 STA | $6,500.00 | $25,000.00 | $6,072.92 | $55,500 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 190 CY | $450.00 | $225.00 | $190.61 | -$42,750 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 9,303 TON | $186.75 | $190.00 | $152.44 | $30,235 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $100.00 | $450.00 | $217.57 | $21,000 |
| 354-7051 PLANE ASPH CONC PAV(2") | 83,821 SY | $3.00 | $2.75 | $1.86 | -$20,955 |
| 500-7001 MOBILIZATION | 1 LS | $295,000.00 | $280,000.00 | $523,850.32 | -$15,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 340 DAY | $100.00 | $125.00 | $87.82 | $8,500 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 66 CY | $625.00 | $750.00 | $616.83 | $8,250 |
| 344-7063 SP MIXES SP-D PG76-22 | 323 TON | $225.00 | $250.00 | $104.27 | $8,075 |
| 672-7004 REFL PAV MRKR TY II-A-A | 6,720 EA | $6.00 | $5.00 | $3.97 | -$6,720 |
| 132-7017 EMBANK (VEH)(OC)(TY C) | 36 CY | $250.00 | $100.00 | $37.09 | -$5,400 |
| 432-7001 RIPRAP (CONC)(4 IN) | 6 CY | $1,600.00 | $750.00 | $573.24 | -$5,100 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $3,500.00 | $5,000.00 | $11,585.04 | $4,500 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 16,357 SY | $3.00 | $2.75 | $2.24 | -$4,089 |
| 662-7065 WK ZN PAV MRK REMOV (W)6"(BRK) | 2,693 LF | $1.50 | $3.00 | $1.02 | $4,040 |
| 662-7098 WK ZN PAV MRK REMOV (Y)6"(BRK) | 2,693 LF | $1.50 | $3.00 | $1.04 | $4,040 |
| 505-7003 TMA (MOBILE OPERATION) | 60 DAY | $200.00 | $250.00 | $229.60 | $3,000 |
| 134-7001 BACKFILL (TY A) | 3 STA | $500.00 | $1,200.00 | $224.26 | $2,100 |
Positive: the low bidder was cheaper on that item. These 20 items account for $246,005 of the $114,229 gap.
DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 190 CY | $450.00 | $190.61 | 2.36x | $49,284 |
| 344-7063 SP MIXES SP-D PG76-22 | 323 TON | $225.00 | $104.27 | 2.16x | $38,995 |
| 800-7001 NO. OF WORKING DAYS | 7,500 $/D | $45.00 | $612.55 | 0.07x | -$4,256,611 |
| 3005-7001 MEMBRANE UNDERSEAL | 16,890 GAL | $0.0100 | $4.76 | 0.00x | -$80,261 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $3,500.00 | $11,585.04 | 0.30x | -$24,255 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 3 STA | $25,000.00 | $6,072.92 | 4.12x | $56,781 |
| 344-7063 SP MIXES SP-D PG76-22 | 323 TON | $250.00 | $104.27 | 2.40x | $47,070 |
| 800-7001 NO. OF WORKING DAYS | 7,500 $/D | $60.00 | $612.55 | 0.10x | -$4,144,111 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $36,000.00 | $11,585.04 | 3.11x | $73,245 |
| 344-7063 SP MIXES SP-D PG76-22 | 323 TON | $275.00 | $104.27 | 2.64x | $55,145 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 340 DAY | $200.00 | $87.82 | 2.28x | $38,142 |
| 800-7001 NO. OF WORKING DAYS | 7,500 $/D | $71.00 | $612.55 | 0.12x | -$4,061,611 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $70,268.00 | $11,585.04 | 6.07x | $176,049 |
| 354-7051 PLANE ASPH CONC PAV(2") | 83,821 SY | $3.42 | $1.86 | 1.84x | $131,012 |
| 344-7063 SP MIXES SP-D PG76-22 | 323 TON | $475.00 | $104.27 | 4.56x | $119,745 |
| 100-7002 PREPARING ROW | 3 STA | $22,000.00 | $6,072.92 | 3.62x | $47,781 |
| 800-7001 NO. OF WORKING DAYS | 7,500 $/D | $71.00 | $612.55 | 0.12x | -$4,061,611 |