Win Price: 0700-04-056

Llano, Travis · lets Jan 6, 2027 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Bridge Maintenance

Unofficial

CCSJ 0700-04-056 · lets Wednesday, Jan 6, 2027 · Llano, Travis, Austin · SH 71, Various · Bridge Maintenance

$614,881Predicted low bid-12.3% vs the engineer's estimate of $700,723
$526,401 – $688,296Likely rangeThe low bid lands here about half the time. 8 in 10: $449,377 to $768,620
4.5Expected biddersFrom similar jobs; no plan holders posted yet
MediumConfidenceBacked by 1,394 closely comparable lettings (2,746 in all)

Where the low bid should land

$449,377: 1 in 10 low bids go lower$768,620: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$449,377-35.9% 90%
$526,401-24.9% 75%
$614,881-12.3% 50%
$688,296-1.8% 25%
$768,620+9.7% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids

No plan holders posted for this job yet. The expected field comes from similar jobs until they are.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Oct 20260204-01-075 WilliamsonAustinBridge Maintenance14 $607,197$344,329-43.3% TAYLOR BRIDGE LLC
Jul 20260700-04-058 LlanoAustinBridge Maintenance11 $792,464$526,435-33.6% TAYLOR BRIDGE LLC
Mar 20260914-00-574 TravisAustinBridge Maintenance13 $518,718$327,386-36.9% TAYLOR BRIDGE LLC
Mar 20260914-00-575 TravisAustinBridge Maintenance13 $1,033,376$769,928-25.5% BK FIELD OPERATIONS LLC
Sep 20266484-49-001 TravisAustinRoutine Maintenance Project - Sealed4 $778,587$620,666-20.3% RARE EARTH LANDSCAPE SOLUTIONS LLC
Nov 20260285-03-066 HaysAustinPedestrian, Sidewalks & Curb Ramps9 $939,603$950,337+1.1% LONE STAR SITEWORK, LLC
Aug 20250151-06-157 TravisAustinBridge Maintenance2 $806,400$498,058-38.2% STRUCTURAL TECHNOLOGIES, LLC
Jul 20260914-04-367 TravisAustinSafety Improvement Projects3 $666,867$685,485+2.8% ELECNOR BELCO ELECTRIC, INC.
Jul 20260265-03-054 BastropAustinIntersection & Operational Imprv5 $745,820$1,095,804+46.9% E-Z BEL CONSTRUCTION, LLC
Sep 20266498-20-001 TravisAustinRoutine Maintenance Project - Sealed4 $908,691$668,419-26.4% VACA UNDERGROUND UTILITIES INC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.