SH 71 from Stephen Austin Blvd to SH 21
0265-03-054 · let Jul 2, 2026 · Bastrop, Austin · Intersection & Operational Imprv
$1,095,804Low bid: E-Z BEL CONSTRUCTION, LLC+46.9% vs estimate $745,820
$126,908Left on the table11.6% gap to the second bid
5BiddersSpread 32% low to high
66Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | E-Z BEL CONSTRUCTION, LLC | $1,095,804 | 46.9% | $126,908 | 6+$212,393 | 5-$563,763 | |
| 2 | AARON CONCRETE CONTRACTORS, LLC | $1,222,712 | +11.6% | 63.9% | $42,389 | 9+$347,341 | 5-$577,537 |
| 3 | TEXAS MATERIALS GROUP, INC. | $1,265,101 | +15.4% | 69.6% | $59,245 | 9+$312,758 | 4-$533,813 |
| 4 | JOE BLAND CONSTRUCTION LLC | $1,324,347 | +20.9% | 77.6% | $126,847 | 10+$395,433 | 2-$472,061 |
| 5 | HUNTER INDUSTRIES, LTD. | $1,451,194 | +32.4% | 94.6% | 11+$476,516 | 2-$417,821 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
E-Z BEL CONSTRUCTION, LLC vs AARON CONCRETE CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 2,000 SF | $100.00 | $145.00 | $25.56 | $90,000 |
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $119,764.00 | $523,850.32 | $29,764 |
| 100-7002 PREPARING ROW | 10 STA | $3,000.00 | $330.00 | $6,072.92 | -$26,700 |
| 341-7003 D-GR HMA TY-B PG64-22 (EXEMPT) | 735 TON | $110.50 | $129.00 | $127.48 | $13,598 |
| 110-7001 EXCAV (ROADWAY) | 725 CY | $17.00 | $34.00 | $11.68 | $12,325 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 1,905 SF | $152.00 | $146.00 | $107.44 | -$11,430 |
| 105-7130 REMOVING STAB BASE & ASPH PAV(12"-27") | 1,024 SY | $15.00 | $26.00 | $6.93 | $11,264 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,840 SY | $7.00 | $5.00 | $1.43 | -$9,680 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,500.00 | $1,937.00 | $11,585.04 | -$9,378 |
| 450-7028 RAIL (TY T80SS) | 112 LF | $151.00 | $223.00 | $108.47 | $8,064 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 1,340 LF | $10.00 | $16.00 | $11.18 | $8,040 |
| 432-7007 RIPRAP (CONC) (CL B) (4 IN) | 19 CY | $975.00 | $584.00 | $564.22 | -$7,429 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $15.00 | $24.00 | $12.08 | $6,300 |
| 104-7006 REMOV CONC (RIPRAP) | 506 SY | $5.00 | $17.00 | $14.32 | $6,072 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,340 LF | $20.00 | $16.00 | $43.56 | -$5,360 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $7,550.00 | $9,935.00 | $9,253.78 | $4,770 |
| 341-7063 D-GR HMA TY-D SAC-B PG 76-22 (EXEMPT) | 134 TON | $192.00 | $224.00 | $185.72 | $4,288 |
| 686-7035 INS TRF SIG PL AM(S)1 ARM(32')LUM | 1 EA | $22,000.00 | $25,883.00 | $14,478.58 | $3,883 |
| 347-7002 TOM-C PG76-22 SAC-B | 67 TON | $305.00 | $357.00 | $130.62 | $3,484 |
| 450-7024 RAIL (TY SSTR) | 106 LF | $151.00 | $119.00 | $69.92 | -$3,392 |
Positive: the low bidder was cheaper on that item. These 20 items account for $128,483 of the $126,908 gap.
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 2,000 SF | $100.00 | $25.56 | 3.91x | $148,879 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,840 SY | $7.00 | $1.43 | 4.90x | $26,962 |
| 347-7002 TOM-C PG76-22 SAC-B | 67 TON | $305.00 | $130.62 | 2.33x | $11,683 |
| 450-7024 RAIL (TY SSTR) | 106 LF | $151.00 | $69.92 | 2.16x | $8,594 |
| 105-7130 REMOVING STAB BASE & ASPH PAV(12"-27") | 1,024 SY | $15.00 | $6.93 | 2.17x | $8,268 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 280 LF | $41.00 | $12.40 | 3.31x | $8,007 |
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,500.00 | $11,585.04 | 0.30x | -$48,510 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,340 LF | $20.00 | $43.56 | 0.46x | -$31,571 |
| 100-7002 PREPARING ROW | 10 STA | $3,000.00 | $6,072.92 | 0.49x | -$30,729 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $25.00 | $52.29 | 0.48x | -$19,102 |
AARON CONCRETE CONTRACTORS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 2,000 SF | $145.00 | $25.56 | 5.67x | $238,879 |
| 105-7130 REMOVING STAB BASE & ASPH PAV(12"-27") | 1,024 SY | $26.00 | $6.93 | 3.75x | $19,532 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,840 SY | $5.00 | $1.43 | 3.50x | $17,282 |
| 110-7001 EXCAV (ROADWAY) | 725 CY | $34.00 | $11.68 | 2.91x | $16,180 |
| 347-7002 TOM-C PG76-22 SAC-B | 67 TON | $357.00 | $130.62 | 2.73x | $15,167 |
| 450-7028 RAIL (TY T80SS) | 112 LF | $223.00 | $108.47 | 2.06x | $12,827 |
| 686-7035 INS TRF SIG PL AM(S)1 ARM(32')LUM | 1 EA | $25,883.00 | $14,478.58 | 1.79x | $11,404 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $24.00 | $12.08 | 1.99x | $8,342 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 280 LF | $40.00 | $12.40 | 3.22x | $7,727 |
| 500-7001 MOBILIZATION | 1 LS | $119,764.00 | $523,850.32 | 0.23x | -$404,086 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,937.00 | $11,585.04 | 0.17x | -$57,888 |
| 100-7002 PREPARING ROW | 10 STA | $330.00 | $6,072.92 | 0.05x | -$57,429 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,340 LF | $16.00 | $43.56 | 0.37x | -$36,931 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $22.00 | $52.29 | 0.42x | -$21,202 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 2,000 SF | $96.60 | $25.56 | 3.78x | $142,079 |
| 105-7130 REMOVING STAB BASE & ASPH PAV(12"-27") | 1,024 SY | $58.00 | $6.93 | 8.37x | $52,300 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,840 SY | $7.00 | $1.43 | 4.90x | $26,962 |
| 110-7001 EXCAV (ROADWAY) | 725 CY | $42.00 | $11.68 | 3.60x | $21,980 |
| 347-7002 TOM-C PG76-22 SAC-B | 67 TON | $450.00 | $130.62 | 3.45x | $21,398 |
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 321 CY | $102.00 | $50.95 | 2.00x | $16,388 |
| 450-7028 RAIL (TY T80SS) | 112 LF | $222.00 | $108.47 | 2.05x | $12,715 |
| 496-7007 REMOV STR (PIPE) | 67 LF | $182.07 | $23.96 | 7.60x | $10,593 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $24.00 | $12.08 | 1.99x | $8,342 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 100-7002 PREPARING ROW | 10 STA | $750.00 | $6,072.92 | 0.12x | -$53,229 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,340 LF | $16.00 | $43.56 | 0.37x | -$36,931 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $24.00 | $52.29 | 0.46x | -$19,802 |
JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 2,000 SF | $105.00 | $25.56 | 4.11x | $158,879 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,340 LF | $105.00 | $43.56 | 2.41x | $82,329 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $110.00 | $52.29 | 2.10x | $40,398 |
| 110-7001 EXCAV (ROADWAY) | 725 CY | $60.00 | $11.68 | 5.14x | $35,030 |
| 105-7130 REMOVING STAB BASE & ASPH PAV(12"-27") | 1,024 SY | $24.00 | $6.93 | 3.47x | $17,484 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,840 SY | $5.00 | $1.43 | 3.50x | $17,282 |
| 347-7002 TOM-C PG76-22 SAC-B | 67 TON | $335.00 | $130.62 | 2.56x | $13,693 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 1,340 LF | $20.00 | $11.18 | 1.79x | $11,813 |
| 420-7052 CL C CONC (RAIL FOUNDATION) | 19 CY | $1,150.00 | $552.17 | 2.08x | $11,359 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 280 LF | $38.00 | $12.40 | 3.06x | $7,167 |
| 500-7001 MOBILIZATION | 1 LS | $115,000.00 | $523,850.32 | 0.22x | -$408,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,050.00 | $11,585.04 | 0.09x | -$63,210 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 1,905 SF | $230.00 | $107.44 | 2.14x | $233,471 |
| 403-7001 TEMPORARY SPL SHORING | 2,000 SF | $77.00 | $25.56 | 3.01x | $102,879 |
| 450-7028 RAIL (TY T80SS) | 112 LF | $300.00 | $108.47 | 2.77x | $21,451 |
| 110-7001 EXCAV (ROADWAY) | 725 CY | $38.50 | $11.68 | 3.30x | $19,443 |
| 104-7006 REMOV CONC (RIPRAP) | 506 SY | $50.00 | $14.32 | 3.49x | $18,055 |
| 347-7002 TOM-C PG76-22 SAC-B | 67 TON | $363.00 | $130.62 | 2.78x | $15,569 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 4,840 SY | $4.60 | $1.43 | 3.22x | $15,346 |
| 450-7024 RAIL (TY SSTR) | 106 LF | $200.00 | $69.92 | 2.86x | $13,788 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $30.00 | $12.08 | 2.48x | $12,542 |
| 105-7130 REMOVING STAB BASE & ASPH PAV(12"-27") | 1,024 SY | $18.80 | $6.93 | 2.71x | $12,159 |
| 500-7001 MOBILIZATION | 1 LS | $144,339.39 | $523,850.32 | 0.28x | -$379,511 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,200.00 | $11,585.04 | 0.45x | -$38,310 |