BAAO/SAAO Bridge FUA Bridge Repairs
0914-00-574 · let Mar 5, 2026 · Travis, Austin · Bridge Maintenance
$327,386Low bid: TAYLOR BRIDGE LLC-36.9% vs estimate $518,718
$15,845Left on the table4.8% gap to the second bid
13BiddersSpread 258% low to high
30Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TAYLOR BRIDGE LLC | $327,386 | -36.9% | $15,845 | 9+$71,506 | 8-$650,368 | |
| 2 | BK FIELD OPERATIONS LLC | $343,231 | +4.8% | -33.8% | $17,934 | 9+$73,424 | 7-$621,543 |
| 3 | BECK-REIT & SONS, LTD. | $361,165 | +10.3% | -30.4% | $29,162 | 9+$81,197 | 9-$603,814 |
| 4 | ROY JORGENSEN ASSOCIATES, INC. | $390,327 | +19.2% | -24.8% | $35,362 | 4+$42,418 | 7-$564,331 |
| 5 | ICOS MANAGEMENT, LLC | $425,689 | +30.0% | -17.9% | $8,491 | 8+$108,143 | 6-$606,723 |
| 6 | GARRET SHIELDS INFRASTRUCTURE | $434,180 | +32.6% | -16.3% | $9,185 | ||
| 7 | BLACKSMITH VENTURES LLC | $443,365 | +35.4% | -14.5% | $935 | ||
| 8 | ROAD DOCTORS LLC | $444,300 | +35.7% | -14.3% | $149,115 | ||
| 9 | RESTEK, INC. | $593,415 | +81.3% | 14.4% | $10,450 | ||
| 10 | MPB, INC. | $603,865 | +84.5% | 16.4% | $88,605 | ||
| 11 | SCR CIVIL CONSTRUCTION, LLC | $692,470 | +111.5% | 33.5% | $114,880 | ||
| 12 | PREMIER CONTRACTORS LLC | $807,350 | +146.6% | 55.6% | $363,395 | ||
| 13 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $1,170,745 | +257.6% | 125.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TAYLOR BRIDGE LLC vs BK FIELD OPERATIONS LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 459-7008 GABION MATTRESSES (GALV)(18 IN) | 80 SY | $195.00 | $350.00 | $176.35 | $12,400 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $40,000.00 | $523,850.32 | $10,000 |
| 480-7002 CLEAN EXIST CULVERTS | 75 CY | $250.00 | $120.00 | $42.86 | -$9,750 |
| 788-7001 CONCRETE BEAM REPAIR | 5 EA | $1,500.00 | $3,000.00 | $4,623.25 | $7,500 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 5 LF | $2,100.00 | $800.00 | $199.12 | -$6,500 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 193 SF | $150.00 | $120.00 | $150.68 | -$5,790 |
| 735-7060 DRIFTWOOD REMOVAL | 40 CY | $250.00 | $120.00 | $72.46 | -$5,200 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 46 CY | $300.00 | $190.00 | $184.74 | -$5,060 |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY) | 100 SF | $50.00 | $100.00 | $9.78 | $5,000 |
| 776-7001 REPAIR (STEEL RAIL) | 25 LF | $200.00 | $350.00 | $138.55 | $3,750 |
| 734-7002 LITTER REMOVAL | 3 CYC | $50.00 | $1,200.00 | $1,937.87 | $3,450 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 429 LF | $50.00 | $55.00 | $15.92 | $2,145 |
| 459-7001 GABIONS (GALV) | 40 CY | $450.00 | $500.00 | $333.69 | $2,000 |
| 556-7001 PIPE UNDERDRAINS (TY 1) (6") | 10 LF | $50.00 | $250.00 | $36.09 | $2,000 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 45 SY | $200.00 | $240.00 | $35.01 | $1,800 |
| 401-7001 FLOWABLE BACKFILL | 8 CY | $1,000.00 | $800.00 | $298.77 | -$1,600 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 25 SF | $400.00 | $450.00 | $192.68 | $1,250 |
| 432-7029 RIPRAP (STONE COMMON)(DRY)(6 IN) | 3 CY | $1,000.00 | $600.00 | $165.45 | -$1,200 |
| 100-7004 PREP ROW (TREE REMOVE) (12"-24" DIA) | 6 EA | $500.00 | $300.00 | $834.16 | -$1,200 |
| 770-7010 REALIGN POSTS | 2 EA | $1,000.00 | $500.00 | $24.32 | -$1,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $13,995 of the $15,845 gap.
TAYLOR BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7002 CLEAN EXIST CULVERTS | 75 CY | $250.00 | $42.86 | 5.83x | $15,536 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 429 LF | $50.00 | $15.92 | 3.14x | $14,621 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 5 LF | $2,100.00 | $199.12 | 10.55x | $9,504 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 45 SY | $200.00 | $35.01 | 5.71x | $7,424 |
| 735-7060 DRIFTWOOD REMOVAL | 40 CY | $250.00 | $72.46 | 3.45x | $7,102 |
| 401-7001 FLOWABLE BACKFILL | 8 CY | $1,000.00 | $298.77 | 3.35x | $5,610 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 25 SF | $400.00 | $192.68 | 2.08x | $5,183 |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY) | 100 SF | $50.00 | $9.78 | 5.11x | $4,022 |
| 432-7029 RIPRAP (STONE COMMON)(DRY)(6 IN) | 3 CY | $1,000.00 | $165.45 | 6.04x | $2,504 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 200 DAY | $1.00 | $87.82 | 0.01x | -$17,364 |
| 788-7001 CONCRETE BEAM REPAIR | 5 EA | $1,500.00 | $4,623.25 | 0.32x | -$15,616 |
| 734-7002 LITTER REMOVAL | 3 CYC | $50.00 | $1,937.87 | 0.03x | -$5,664 |
| 700-7001 POTHOLE REPAIR(STANDARD)(0"-5" DEEP) | 15 SY | $150.00 | $406.89 | 0.37x | -$3,853 |
BK FIELD OPERATIONS LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 429 LF | $55.00 | $15.92 | 3.46x | $16,766 |
| 459-7008 GABION MATTRESSES (GALV)(18 IN) | 80 SY | $350.00 | $176.35 | 1.98x | $13,892 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 45 SY | $240.00 | $35.01 | 6.85x | $9,224 |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY) | 100 SF | $100.00 | $9.78 | 10.22x | $9,022 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 25 SF | $450.00 | $192.68 | 2.34x | $6,433 |
| 480-7002 CLEAN EXIST CULVERTS | 75 CY | $120.00 | $42.86 | 2.80x | $5,786 |
| 776-7001 REPAIR (STEEL RAIL) | 25 LF | $350.00 | $138.55 | 2.53x | $5,286 |
| 401-7001 FLOWABLE BACKFILL | 8 CY | $800.00 | $298.77 | 2.68x | $4,010 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 5 LF | $800.00 | $199.12 | 4.02x | $3,004 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $523,850.32 | 0.08x | -$483,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 200 DAY | $1.00 | $87.82 | 0.01x | -$17,364 |
| 100-7004 PREP ROW (TREE REMOVE) (12"-24" DIA) | 6 EA | $300.00 | $834.16 | 0.36x | -$3,205 |
| 700-7001 POTHOLE REPAIR(STANDARD)(0"-5" DEEP) | 15 SY | $200.00 | $406.89 | 0.49x | -$3,103 |
BECK-REIT & SONS, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 429 LF | $65.00 | $15.92 | 4.08x | $21,056 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 45 SY | $350.00 | $35.01 | 10.00x | $14,174 |
| 776-7001 REPAIR (STEEL RAIL) | 25 LF | $650.00 | $138.55 | 4.69x | $12,786 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 25 SF | $650.00 | $192.68 | 3.37x | $11,433 |
| 401-7001 FLOWABLE BACKFILL | 8 CY | $950.00 | $298.77 | 3.18x | $5,210 |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY) | 100 SF | $60.00 | $9.78 | 6.13x | $5,022 |
| 770-7010 REALIGN POSTS | 2 EA | $2,500.00 | $24.32 | 102.78x | $4,951 |
| 432-7029 RIPRAP (STONE COMMON)(DRY)(6 IN) | 3 CY | $1,300.00 | $165.45 | 7.86x | $3,404 |
| 480-7002 CLEAN EXIST CULVERTS | 75 CY | $85.00 | $42.86 | 1.98x | $3,161 |
| 500-7001 MOBILIZATION | 1 LS | $59,000.00 | $523,850.32 | 0.11x | -$464,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,000.00 | $11,585.04 | 0.17x | -$57,510 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 200 DAY | $1.00 | $87.82 | 0.01x | -$17,364 |
| 100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA) | 6 EA | $150.00 | $1,166.77 | 0.13x | -$6,101 |
| 700-7001 POTHOLE REPAIR(STANDARD)(0"-5" DEEP) | 15 SY | $100.00 | $406.89 | 0.25x | -$4,603 |
| 734-7002 LITTER REMOVAL | 3 CYC | $450.00 | $1,937.87 | 0.23x | -$4,464 |
| 100-7004 PREP ROW (TREE REMOVE) (12"-24" DIA) | 6 EA | $100.00 | $834.16 | 0.12x | -$4,405 |
ROY JORGENSEN ASSOCIATES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7002 CLEAN EXIST CULVERTS | 75 CY | $250.00 | $42.86 | 5.83x | $15,536 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 45 SY | $250.00 | $35.01 | 7.14x | $9,674 |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY) | 100 SF | $100.00 | $9.78 | 10.22x | $9,022 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 429 LF | $35.00 | $15.92 | 2.20x | $8,186 |
| 500-7001 MOBILIZATION | 1 LS | $65,000.00 | $523,850.32 | 0.12x | -$458,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,500.00 | $11,585.04 | 0.13x | -$60,510 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA) | 6 EA | $1.00 | $1,166.77 | 0.00x | -$6,995 |
| 734-7002 LITTER REMOVAL | 3 CYC | $100.00 | $1,937.87 | 0.05x | -$5,514 |
| 100-7004 PREP ROW (TREE REMOVE) (12"-24" DIA) | 6 EA | $1.00 | $834.16 | 0.00x | -$4,999 |
| 700-7001 POTHOLE REPAIR(STANDARD)(0"-5" DEEP) | 15 SY | $100.00 | $406.89 | 0.25x | -$4,603 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 45 SY | $856.00 | $35.01 | 24.45x | $36,944 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 429 LF | $64.00 | $15.92 | 4.02x | $20,627 |
| 480-7002 CLEAN EXIST CULVERTS | 75 CY | $214.00 | $42.86 | 4.99x | $12,836 |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY) | 100 SF | $128.00 | $9.78 | 13.09x | $11,822 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 25 SF | $642.00 | $192.68 | 3.33x | $11,233 |
| 735-7060 DRIFTWOOD REMOVAL | 40 CY | $214.00 | $72.46 | 2.95x | $5,662 |
| 776-7001 REPAIR (STEEL RAIL) | 25 LF | $321.00 | $138.55 | 2.32x | $4,561 |
| 401-7001 FLOWABLE BACKFILL | 8 CY | $856.00 | $298.77 | 2.87x | $4,458 |
| 500-7001 MOBILIZATION | 1 LS | $52,400.00 | $523,850.32 | 0.10x | -$471,450 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 200 DAY | $1.00 | $87.82 | 0.01x | -$17,364 |
| 734-7002 LITTER REMOVAL | 3 CYC | $642.00 | $1,937.87 | 0.33x | -$3,888 |