Downtown Ranch Road 12 Sidewalks
0285-03-066 · let Nov 4, 2026 · Hays, Austin · Pedestrian, Sidewalks & Curb Ramps
$950,337Low bid: LONE STAR SITEWORK, LLC+1.1% vs estimate $939,603
$133,497Left on the table14.0% gap to the second bid
9BiddersSpread 79% low to high
75Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONE STAR SITEWORK, LLC | $950,337 | 1.1% | $133,497 | 6+$126,386 | 5-$687,392 | |
| 2 | STX CIVIL | $1,083,834 | +14.0% | 15.4% | $19,922 | 7+$86,502 | 2-$480,284 |
| 3 | Rucoba & Maya Construction, LLC | $1,103,755 | +16.1% | 17.5% | $19,037 | 6+$202,980 | 2-$520,381 |
| 4 | MYERS CONCRETE CONSTRUCTION, LP | $1,122,792 | +18.1% | 19.5% | $12,545 | 5+$153,041 | 2-$490,030 |
| 5 | TI-ZACK CONCRETE, LLC | $1,135,337 | +19.5% | 20.8% | $64,464 | 5+$118,935 | 4-$560,125 |
| 6 | CENTERLINE TECHNOLOGIES, LLC | $1,199,801 | +26.3% | 27.7% | $28,909 | ||
| 7 | RATLIFF HARDSCAPE, LTD. | $1,228,710 | +29.3% | 30.8% | $43,290 | ||
| 8 | E-Z BEL CONSTRUCTION, LLC | $1,272,000 | +33.8% | 35.4% | $428,314 | ||
| 9 | TIGHT LINE CONSTRUCTION, LLC | $1,700,314 | +78.9% | 81.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONE STAR SITEWORK, LLC vs STX CIVIL, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $1,300.00 | $7,434.69 | $11,585.04 | $61,347 |
| 500-7001 MOBILIZATION | 1 LS | $31,100.00 | $86,717.18 | $523,850.32 | $55,617 |
| 465-7336 INLET (COMP)(TY SIDEWALK BRIDGE) | 2 EA | $3,150.00 | $22,282.43 | $13,781.04 | $38,265 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 3,093 SY | $16.75 | $7.67 | $7.43 | -$28,084 |
| 505-7001 TMA (STATIONARY) | 193 DAY | $300.00 | $155.00 | $217.57 | -$27,985 |
| 680-7003 INSTALL HWY TRF SIG (SYSTEM) | 1 EA | $8,250.00 | $35,750.00 | $36,231.94 | $27,500 |
| 531-7029 CONC SIDEWALKS (SPECIAL) (TYPE A) | 4 SY | $495.00 | $6,274.01 | $228.77 | $23,116 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 452 CY | $146.00 | $96.33 | $63.96 | -$22,451 |
| 530-7006 DRIVEWAYS (CONC) | 1,073 SY | $111.00 | $128.10 | $109.20 | $18,348 |
| 341-7001 D-GR HMA TY-B PG64-22 | 135 TON | $325.00 | $194.75 | $97.82 | -$17,584 |
| 466-7129 HEADWALL (CH - PW - A - 0) (DES= 3) | 1 EA | $2,850.00 | $13,601.43 | $2,850.00 | $10,751 |
| 530-7010 DRIVEWAYS (ACP) | 391 SY | $76.00 | $96.92 | $54.96 | $8,180 |
| 341-7056 D-GR HMA TY-D PG76-22 | 68 TON | $337.00 | $225.66 | $123.11 | -$7,571 |
| 529-7021 CONC CURB & GUTTER (SLOTTED) | 589 LF | $41.00 | $52.73 | $38.73 | $6,909 |
| 752-7002 SPOT TREE TRIMMING / BRUSH REMOVAL | 55 LF | $20.00 | $140.00 | $1.20 | $6,600 |
| 680-7004 REMOVING TRAFFIC SIGNALS | 1 EA | $2,370.00 | $7,840.00 | $5,086.47 | $5,470 |
| 531-7002 CONC SIDEWALKS (5") | 1,155 SY | $108.00 | $103.60 | $68.80 | -$5,082 |
| 618-7037 CONDT (PVC) (SCH 40) (3") (BORE) | 120 LF | $97.00 | $55.00 | $26.79 | -$5,040 |
| 628-7169 ELC SRV TY D 120/240 070(NS)AL(E)SP(O) | 1 EA | $11,830.00 | $8,250.00 | $7,979.59 | -$3,580 |
| 464-7042 RC PIPE (ARCH)(CL III)(DES 3) | 5 LF | $575.00 | $1,059.06 | $264.66 | $2,420 |
Positive: the low bidder was cheaper on that item. These 20 items account for $147,147 of the $133,497 gap.
LONE STAR SITEWORK, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 452 CY | $146.00 | $63.96 | 2.28x | $37,080 |
| 341-7001 D-GR HMA TY-B PG64-22 | 135 TON | $325.00 | $97.82 | 3.32x | $30,669 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 3,093 SY | $16.75 | $7.43 | 2.26x | $28,841 |
| 341-7056 D-GR HMA TY-D PG76-22 | 68 TON | $337.00 | $123.11 | 2.74x | $14,545 |
| 618-7037 CONDT (PVC) (SCH 40) (3") (BORE) | 120 LF | $97.00 | $26.79 | 3.62x | $8,425 |
| 416-7005 DRILL SHAFT (30 IN) | 22 LF | $550.00 | $239.74 | 2.29x | $6,826 |
| 500-7001 MOBILIZATION | 1 LS | $31,100.00 | $523,850.32 | 0.06x | -$492,750 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $1,300.00 | $11,585.04 | 0.11x | -$102,850 |
| 529-7017 CONC CURB (TY F1) | 353 LF | $48.00 | $168.53 | 0.28x | -$42,547 |
| 680-7003 INSTALL HWY TRF SIG (SYSTEM) | 1 EA | $8,250.00 | $36,231.94 | 0.23x | -$27,982 |
| 465-7336 INLET (COMP)(TY SIDEWALK BRIDGE) | 2 EA | $3,150.00 | $13,781.04 | 0.23x | -$21,262 |
STX CIVIL: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 531-7029 CONC SIDEWALKS (SPECIAL) (TYPE A) | 4 SY | $6,274.01 | $228.77 | 27.42x | $24,181 |
| 530-7010 DRIVEWAYS (ACP) | 391 SY | $96.92 | $54.96 | 1.76x | $16,408 |
| 341-7001 D-GR HMA TY-B PG64-22 | 135 TON | $194.75 | $97.82 | 1.99x | $13,085 |
| 466-7129 HEADWALL (CH - PW - A - 0) (DES= 3) | 1 EA | $13,601.43 | $2,850.00 | 4.77x | $10,751 |
| 752-7002 SPOT TREE TRIMMING / BRUSH REMOVAL | 55 LF | $140.00 | $1.20 | 116.77x | $7,634 |
| 416-7005 DRILL SHAFT (30 IN) | 22 LF | $579.24 | $239.74 | 2.42x | $7,469 |
| 341-7056 D-GR HMA TY-D PG76-22 | 68 TON | $225.66 | $123.11 | 1.83x | $6,973 |
| 500-7001 MOBILIZATION | 1 LS | $86,717.18 | $523,850.32 | 0.17x | -$437,133 |
| 529-7017 CONC CURB (TY F1) | 353 LF | $46.29 | $168.53 | 0.27x | -$43,151 |
Rucoba & Maya Construction, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 3,093 SY | $45.00 | $7.43 | 6.06x | $116,219 |
| 341-7001 D-GR HMA TY-B PG64-22 | 135 TON | $300.00 | $97.82 | 3.07x | $27,294 |
| 530-7010 DRIVEWAYS (ACP) | 391 SY | $105.00 | $54.96 | 1.91x | $19,567 |
| 531-7029 CONC SIDEWALKS (SPECIAL) (TYPE A) | 4 SY | $4,909.20 | $228.77 | 21.46x | $18,722 |
| 341-7056 D-GR HMA TY-D PG76-22 | 68 TON | $300.00 | $123.11 | 2.44x | $12,029 |
| 466-7129 HEADWALL (CH - PW - A - 0) (DES= 3) | 1 EA | $12,000.00 | $2,850.00 | 4.21x | $9,150 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $1,932.00 | $11,585.04 | 0.17x | -$96,530 |
MYERS CONCRETE CONSTRUCTION, LP: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 452 CY | $158.00 | $63.96 | 2.47x | $42,504 |
| 341-7001 D-GR HMA TY-B PG64-22 | 135 TON | $383.00 | $97.82 | 3.92x | $38,499 |
| 341-7056 D-GR HMA TY-D PG76-22 | 68 TON | $585.00 | $123.11 | 4.75x | $31,409 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 3,093 SY | $15.00 | $7.43 | 2.02x | $23,429 |
| 531-7029 CONC SIDEWALKS (SPECIAL) (TYPE A) | 4 SY | $4,529.00 | $228.77 | 19.80x | $17,201 |
| 500-7001 MOBILIZATION | 1 LS | $94,451.00 | $523,850.32 | 0.18x | -$429,399 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $5,522.00 | $11,585.04 | 0.48x | -$60,630 |
TI-ZACK CONCRETE, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 3,093 SY | $30.67 | $7.43 | 4.13x | $71,896 |
| 341-7001 D-GR HMA TY-B PG64-22 | 135 TON | $220.00 | $97.82 | 2.25x | $16,494 |
| 466-7129 HEADWALL (CH - PW - A - 0) (DES= 3) | 1 EA | $16,500.00 | $2,850.00 | 5.79x | $13,650 |
| 529-7011 CONCRETE GUTTER (MODIFIED) | 457 LF | $49.44 | $26.89 | 1.84x | $10,307 |
| 341-7056 D-GR HMA TY-D PG76-22 | 68 TON | $220.00 | $123.11 | 1.79x | $6,589 |
| 500-7001 MOBILIZATION | 1 LS | $110,591.33 | $523,850.32 | 0.21x | -$413,259 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $2,750.00 | $11,585.04 | 0.24x | -$88,350 |
| 505-7001 TMA (STATIONARY) | 193 DAY | $1.10 | $217.57 | 0.01x | -$41,779 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 193 DAY | $1.10 | $87.82 | 0.01x | -$16,736 |