Interchange (New or Reconstructed)
OfficialCCSJ 0092-03-053 · lets Tuesday, Dec 1, 2026 · Ellis, Dallas · FM 664, IH 45 · Widen Road - Add Lanes And Shoulders
Where the low bid should land
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $90,583,464 | -22.4% | 90% |
| $99,567,726 | -14.6% | 75% |
| $108,646,063 | -6.9% | 50% |
| $116,059,716 | -0.5% | 25% |
| $116,541,942 | -0.1% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bids| Plan holder | Chance they bid | Bids | Wins | Avg bid vs est. | Their typical bid here |
|---|---|---|---|---|---|
| WEBBER, LLCBidders | 70%bid 1 of 1 plan sets we saw | 91 | 14 | 8.4% | $126,433,490 |
| MARIO SINACOLA & SONS EXCAVATING, INC.Bidders | 60% | 20 | 4 | 0.7% | $117,513,832 |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC.Bidders | 60% | 10 | 5 | 0.7% | $117,528,918 |
| XIT PAVING AND CONSTRUCTION INC.Informational Proposals | 60% | 20 | 3 | 2.3% | $119,358,401 |
| SEMA CONSTRUCTION, INC.Bidders | 60% | 10 | 2 | 1.7% | $118,693,565 |
| ZACHRY CONSTRUCTION CORPORATIONBidders | 60% | 34 | 3 | 7.0% | $124,785,057 |
| GRANITE CONSTRUCTION COMPANYBidders | 60% | 31 | 5 | 3.2% | $120,395,808 |
| AUSTIN BRIDGE & ROAD SERVICES, LPBidders | 60% | 94 | 15 | 2.8% | $119,919,687 |
| JAMES CONSTRUCTION GROUP, LLCBidders | 60% | 101 | 12 | 5.8% | $123,388,761 |
| RPM XCONSTRUCTION, LLCBidders | 60% | 13 | 2 | -1.6% | $114,827,281 |
| PULICE CONSTRUCTION, INC.Bidders | 60% | 42 | 3 | 6.3% | $124,026,859 |
| HARPER BROTHERS CONSTRUCTION LLCBidders | 60% | 41 | 4 | 5.2% | $122,760,260 |
| INDUS ROAD & BRIDGE, INC.Bidders | 60% | 39 | 9 | 5.8% | $123,467,917 |
| R CONSTRUCTION CIVIL, LLCBidders | 60% | 58 | 10 | 3.2% | $120,444,155 |
| Lumin8 Transportation Technologies, LLCBidders | 60% | 18 | 1 | 26.7% | $147,860,415 |
| BALFOUR BEATTY INFRASTRUCTURE, INC.Bidders | 45% | 7 | 1 | 15.3% | $134,463,646 |
| REYES TX, INC.Bidders | 45% | 5 | 1 | 1.8% | $118,734,952 |
Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| May 2026 | 0081-03-047 | DentonDallas | Widen Non-Freeway | 9 | $111,532,677 | $111,363,901-0.2% | WEBBER, LLC |
| Mar 2026 | 0261-01-041 | EllisDallas | Interchange (New or Reconstructed) | 9 | $63,765,204 | $63,703,074-0.1% | HIGHWAY 19 CONSTRUCTION LLC |
| Oct 2026 | 0095-03-100 | KaufmanDallas | Bridge Replacement | 10 | $55,640,546 | $55,012,735-1.1% | HIGHWAY 19 CONSTRUCTION LLC |
| Aug 2025 | 0195-02-081 | DentonDallas | Widen Freeway | 9 | $167,578,105 | $128,704,134-23.2% | INDUS ROAD & BRIDGE, INC. |
| Apr 2026 | 3510-05-047 | HarrisHouston | Widen Freeway | 10 | $135,992,054 | $119,970,903-11.8% | SER CONSTRUCTION PARTNERS, LLC |
| Oct 2025 | 0034-01-130 | TaylorAbilene | Interchange (New or Reconstructed) | 9 | $84,918,829 | $72,482,832-14.6% | JAMES CONSTRUCTION GROUP, LLC |
| Feb 2026 | 0050-06-092 | HarrisHouston | Rehabilitation of Existing Road | 10 | $78,925,854 | $74,036,475-6.2% | HARPER BROTHERS CONSTRUCTION LLC |
| Nov 2026 | 0195-02-092 | DentonDallas | Widen Freeway | 6 | $144,352,231 | $138,145,038-4.3% | INDUS ROAD & BRIDGE, INC. |
| Oct 2026 | 0009-11-248 | DallasDallas | Interchange (New or Reconstructed) | 7 | $51,740,494 | $54,378,798+5.1% | RAGLE CONSTRUCTION, INC. |
| Aug 2026 | 0014-15-034 | TarrantFort Worth | Intersection & Operational Imprv | 11 | $74,343,262 | $66,140,142-11.0% | INDUS ROAD & BRIDGE, INC. |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.