US 80 WESTBOUND AT BUFFALO CRE-9503100
0095-03-100 · let Oct 6, 2026 · Kaufman, Dallas · Bridge Replacement
$55,012,735Low bid: HIGHWAY 19 CONSTRUCTION LLC-1.1% vs estimate $55,640,546
$1,297,864Left on the table2.4% gap to the second bid
10BiddersSpread 27% low to high
1,035Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HIGHWAY 19 CONSTRUCTION LLC | $55,012,735 | -1.1% | $1,297,864 | 6+$7,211,699 | 0 | |
| 2 | R CONSTRUCTION CIVIL, LLC | $56,310,600 | +2.4% | 1.2% | $4,005,047 | 4+$4,169,833 | 0 |
| 3 | WEBBER, LLC | $60,315,647 | +9.6% | 8.4% | $2,928,613 | 4+$12,085,562 | 1-$548,260 |
| 4 | EAST TEXAS BRIDGE, INC. | $63,244,260 | +15.0% | 13.7% | $1,614,568 | 3+$5,914,322 | 0 |
| 5 | ZACHRY CONSTRUCTION CORPORATION | $64,858,828 | +17.9% | 16.6% | $2,332,872 | 5+$15,439,883 | 4-$5,844,712 |
| 6 | MARIO SINACOLA & SONS EXCAVATING, INC. | $67,191,700 | +22.1% | 20.8% | -$829,251 | ||
| 7 | JAMES CONSTRUCTION GROUP, LLC | $66,362,449 | +20.6% | 19.3% | $1,857,436 | ||
| 8 | GRANITE CONSTRUCTION COMPANY | $68,219,885 | +24.0% | 22.6% | -$55,150 | ||
| 9 | BALFOUR BEATTY INFRASTRUCTURE, INC. | $68,164,735 | +23.9% | 22.5% | $1,571,225 | ||
| 10 | INDUS ROAD & BRIDGE, INC. | $69,735,960 | +26.8% | 25.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HIGHWAY 19 CONSTRUCTION LLC vs R CONSTRUCTION CIVIL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 416-7006 DRILL SHAFT (36 IN) | 14,315 LF | $181.00 | $330.00 | $280.58 | $2,132,935 |
| 500-7001 MOBILIZATION | 1 LS | $5,000,000.00 | $3,000,000.00 | $523,850.32 | -$2,000,000 |
| 110-7001 EXCAV (ROADWAY) | 43,625 CY | $7.00 | $29.00 | $11.68 | $959,750 |
| 416-7008 DRILL SHAFT (48 IN) | 7,562 LF | $350.00 | $475.00 | $400.14 | $945,250 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 19,943 LF | $250.00 | $204.00 | $217.69 | -$917,378 |
| 416-7007 DRILL SHAFT (42 IN) | 4,820 LF | $250.00 | $420.00 | $318.92 | $819,400 |
| 420-7023 CL C CONC (CAP)(HPC) | 953.8 CY | $1,682.00 | $1,025.00 | $1,420.15 | -$626,647 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,061 CY | $18.00 | $100.00 | $44.90 | $579,002 |
| 423-7019 RETAINING WALL (DRILL SHAFT) (FASCIA) | 15,930 SF | $55.00 | $90.00 | $103.21 | $557,550 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 28,080 LF | $25.00 | $7.00 | $13.39 | -$505,440 |
| 450-7024 RAIL (TY SSTR) | 5,211.6 LF | $170.00 | $74.00 | $69.92 | -$500,314 |
| 450-7025 RAIL (TY SSTR)(HPC) | 3,926 LF | $180.00 | $83.00 | $96.82 | -$380,822 |
| 403-7001 TEMPORARY SPL SHORING | 19,991 SF | $55.00 | $38.00 | $25.56 | -$339,847 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 33,995 CY | $18.00 | $27.00 | $17.39 | $305,955 |
| 168-7001 VEGETATIVE WATERING | 22,354 TGL | $20.00 | $33.00 | $8.43 | $290,602 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 28,320 LF | $75.00 | $65.00 | $40.65 | -$283,200 |
| 420-7013 CL C CONC (ABUT)(HPC) | 509.8 CY | $1,500.00 | $950.00 | $1,329.26 | -$280,390 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 8,651 CY | $150.00 | $179.00 | $184.74 | $250,879 |
| 508-7001 CONSTRUCTING DETOURS | 21,332 SY | $85.00 | $74.00 | $83.58 | -$234,652 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 7,352 LF | $30.00 | $0.3800 | $0.0662 | -$217,766 |
Positive: the low bidder was cheaper on that item. These 20 items account for $554,868 of the $1,297,864 gap.
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,000,000.00 | $523,850.32 | 9.54x | $4,476,150 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 28,320 LF | $75.00 | $40.65 | 1.85x | $972,860 |
| 403-7001 TEMPORARY SPL SHORING | 19,991 SF | $55.00 | $25.56 | 2.15x | $588,523 |
| 450-7024 RAIL (TY SSTR) | 5,211.6 LF | $170.00 | $69.92 | 2.43x | $521,565 |
| 450-7025 RAIL (TY SSTR)(HPC) | 3,926 LF | $180.00 | $96.82 | 1.86x | $326,582 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 28,080 LF | $25.00 | $13.39 | 1.87x | $326,020 |
R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,000,000.00 | $523,850.32 | 5.73x | $2,476,150 |
| 110-7001 EXCAV (ROADWAY) | 43,625 CY | $29.00 | $11.68 | 2.48x | $755,489 |
| 168-7001 VEGETATIVE WATERING | 22,354 TGL | $33.00 | $8.43 | 3.91x | $549,155 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,061 CY | $100.00 | $44.90 | 2.23x | $389,039 |
WEBBER, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 54.8 STA | $105,000.00 | $6,072.92 | 17.29x | $5,421,204 |
| 500-7001 MOBILIZATION | 1 LS | $5,802,900.25 | $523,850.32 | 11.08x | $5,279,050 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 38 MO | $39,475.00 | $11,585.04 | 3.41x | $1,059,818 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,061 CY | $91.00 | $44.90 | 2.03x | $325,490 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 6 EA | $45,300.00 | $136,676.66 | 0.33x | -$548,260 |
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 4ZACHRY CONSTRUCTION CORPORATION: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 54.8 STA | $109,489.05 | $6,072.92 | 18.03x | $5,667,204 |
| 500-7001 MOBILIZATION | 1 LS | $6,000,000.00 | $523,850.32 | 11.45x | $5,476,150 |
| 423-7019 RETAINING WALL (DRILL SHAFT) (FASCIA) | 15,930 SF | $316.06 | $103.21 | 3.06x | $3,390,756 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 38 MO | $25,227.91 | $11,585.04 | 2.18x | $518,429 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 7,061 CY | $99.76 | $44.90 | 2.22x | $387,345 |
| 416-7008 DRILL SHAFT (48 IN) | 7,562 LF | $10.00 | $400.14 | 0.02x | -$2,950,256 |
| 416-7007 DRILL SHAFT (42 IN) | 4,820 LF | $10.00 | $318.92 | 0.03x | -$1,488,991 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 28,320 LF | $8.72 | $40.65 | 0.21x | -$904,190 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 6 EA | $53,130.74 | $136,676.66 | 0.39x | -$501,276 |