US 83/84 Y INTERCHANGE
0034-01-130 · let Oct 8, 2025 · Taylor, Abilene · Interchange (New or Reconstructed)
$72,482,832Low bid: JAMES CONSTRUCTION GROUP, LLC-14.6% vs estimate $84,918,829
$3,117,156Left on the table4.3% gap to the second bid
9BiddersSpread 19% low to high
381Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JAMES CONSTRUCTION GROUP, LLC | $72,482,832 | -14.6% | $3,117,156 | 4+$15,987,314 | 1-$511,459 | |
| 2 | SUNDT CONSTRUCTION, INC. | $75,599,988 | +4.3% | -11.0% | $638,530 | 4+$15,815,816 | 2-$2,082,650 |
| 3 | WEBBER, LLC | $76,238,518 | +5.2% | -10.2% | $725,964 | 9+$27,235,825 | 7-$12,389,311 |
| 4 | ZACHRY CONSTRUCTION CORPORATION | $76,964,482 | +6.2% | -9.4% | $20,512 | 5+$13,890,876 | 1-$1,531,838 |
| 5 | FNF CONSTRUCTION, INC. | $76,984,994 | +6.2% | -9.3% | $552,919 | 6+$10,704,424 | 1-$965,377 |
| 6 | PULICE CONSTRUCTION, INC. | $77,537,913 | +7.0% | -8.7% | $1,653,367 | ||
| 7 | J. H. STRAIN & SONS, INC. | $79,191,280 | +9.3% | -6.7% | $3,082,222 | ||
| 8 | MARIO SINACOLA & SONS EXCAVATING, INC. | $82,273,503 | +13.5% | -3.1% | $4,052,621 | ||
| 9 | A. L. HELMCAMP, INC. | $86,326,123 | +19.1% | 1.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JAMES CONSTRUCTION GROUP, LLC vs SUNDT CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 423-7001 RETAINING WALL (MSE) | 75,860 SF | $60.00 | $116.00 | $74.07 | $4,248,160 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 190,921.273 CY | $28.24 | $8.00 | $13.19 | -$3,864,247 |
| 400-7010 CEM STABIL BKFL | 15,529 CY | $124.89 | $225.00 | $138.14 | $1,554,608 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 160,943 SY | $17.80 | $9.20 | $12.30 | -$1,384,110 |
| 500-7001 MOBILIZATION | 1 LS | $7,104,224.16 | $8,399,300.00 | $523,850.32 | $1,295,076 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 9,778.18 LF | $239.21 | $325.00 | $189.94 | $838,870 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 43 MO | $24,453.99 | $41,000.00 | $11,585.04 | $711,478 |
| 422-7002 REINF CONC SLAB (HPC) | 88,764 SF | $38.00 | $30.00 | $26.91 | -$710,112 |
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 61,021 SY | $25.26 | $15.00 | $34.64 | -$626,075 |
| 110-7001 EXCAV (ROADWAY) | 65,966.024 CY | $17.36 | $8.00 | $11.68 | -$617,442 |
| 105-7018 RMV (18"-22") TRT/UNTRT BASE & ASPH PAV | 125,018 SY | $8.34 | $5.00 | $9.31 | -$417,560 |
| 6123-7001 FULL COLOR MATRIX DMS (POLE MOUNTED) | 3 EA | $13,500.00 | $150,000.00 | $13,500.00 | $409,500 |
| 400-7001 STRUCT EXCAV | 18,475 CY | $24.16 | $3.00 | $13.82 | -$390,931 |
| 505-7001 TMA (STATIONARY) | 681 DAY | $713.01 | $165.00 | $217.57 | -$373,195 |
| 403-7001 TEMPORARY SPL SHORING | 38,025 SF | $12.11 | $2.30 | $25.56 | -$373,025 |
| 260-7006 LIME TRT (EXIST MATL)(6") | 203,150 SY | $5.05 | $3.25 | $3.80 | -$365,670 |
| 100-7002 PREPARING ROW | 190.3 STA | $37,500.00 | $39,000.00 | $6,072.92 | $285,450 |
| 450-7025 RAIL (TY SSTR)(HPC) | 16,956.7 LF | $69.36 | $85.00 | $96.82 | $265,203 |
| 529-7009 CONC CURB & GUTTER (TY II) | 12,212.7 LF | $28.63 | $50.00 | $32.57 | $260,985 |
| 416-7007 DRILL SHAFT (42 IN) | 1,708 LF | $259.16 | $400.00 | $318.92 | $240,555 |
Positive: the low bidder was cheaper on that item. These 20 items account for $987,518 of the $3,117,156 gap.
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $7,104,224.16 | $523,850.32 | 13.56x | $6,580,374 |
| 100-7002 PREPARING ROW | 190.3 STA | $37,500.00 | $6,072.92 | 6.17x | $5,980,573 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 190,921.273 CY | $28.24 | $13.19 | 2.14x | $2,873,002 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 43 MO | $24,453.99 | $11,585.04 | 2.11x | $553,365 |
| 403-7001 TEMPORARY SPL SHORING | 38,025 SF | $12.11 | $25.56 | 0.47x | -$511,459 |
SUNDT CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $8,399,300.00 | $523,850.32 | 16.03x | $7,875,450 |
| 100-7002 PREPARING ROW | 190.3 STA | $39,000.00 | $6,072.92 | 6.42x | $6,266,023 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 43 MO | $41,000.00 | $11,585.04 | 3.54x | $1,264,843 |
| 6123-7001 FULL COLOR MATRIX DMS (POLE MOUNTED) | 3 EA | $150,000.00 | $13,500.00 | 11.11x | $409,500 |
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 61,021 SY | $15.00 | $34.64 | 0.43x | -$1,198,166 |
| 403-7001 TEMPORARY SPL SHORING | 38,025 SF | $2.30 | $25.56 | 0.09x | -$884,484 |
WEBBER, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $7,623,851.45 | $523,850.32 | 14.55x | $7,100,001 |
| 100-7002 PREPARING ROW | 190.3 STA | $40,062.28 | $6,072.92 | 6.60x | $6,468,175 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 9,778.18 LF | $598.21 | $189.94 | 3.15x | $3,992,147 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 43 MO | $94,177.82 | $11,585.04 | 8.13x | $3,551,489 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 190,921.273 CY | $30.49 | $13.19 | 2.31x | $3,302,575 |
| 425-7003 PRESTR CONC GIRDER (TX40) | 2,818.88 LF | $576.36 | $213.86 | 2.69x | $1,021,836 |
| 110-7001 EXCAV (ROADWAY) | 65,966.024 CY | $24.61 | $11.68 | 2.11x | $852,796 |
| 420-7023 CL C CONC (CAP)(HPC) | 444.9 CY | $2,677.28 | $1,420.15 | 1.89x | $559,296 |
| 6123-7001 FULL COLOR MATRIX DMS (POLE MOUNTED) | 3 EA | $142,670.00 | $13,500.00 | 10.57x | $387,510 |
| 341-7001 D-GR HMA TY-B PG64-22 | 47,378 TON | $8.98 | $97.82 | 0.09x | -$4,209,294 |
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 23,576 TON | $9.67 | $120.21 | 0.08x | -$2,606,075 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 160,943 SY | $1.03 | $12.30 | 0.08x | -$1,813,119 |
| 400-7010 CEM STABIL BKFL | 15,529 CY | $50.11 | $138.14 | 0.36x | -$1,367,075 |
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 61,021 SY | $17.09 | $34.64 | 0.49x | -$1,070,632 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 2,414 TON | $27.09 | $345.77 | 0.08x | -$769,289 |
| 260-7006 LIME TRT (EXIST MATL)(6") | 203,150 SY | $1.07 | $3.80 | 0.28x | -$553,828 |
ZACHRY CONSTRUCTION CORPORATION: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $7,000,000.00 | $523,850.32 | 13.36x | $6,476,150 |
| 100-7002 PREPARING ROW | 190.3 STA | $36,784.03 | $6,072.92 | 6.06x | $5,844,324 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 43 MO | $25,495.65 | $11,585.04 | 2.20x | $598,156 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 251,514 SY | $3.48 | $1.43 | 2.43x | $515,780 |
| 6123-7001 FULL COLOR MATRIX DMS (POLE MOUNTED) | 3 EA | $165,655.46 | $13,500.00 | 12.27x | $456,466 |
| 400-7010 CEM STABIL BKFL | 15,529 CY | $39.50 | $138.14 | 0.29x | -$1,531,838 |
FNF CONSTRUCTION, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $7,698,000.00 | $523,850.32 | 14.70x | $7,174,150 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 9,778.18 LF | $345.00 | $189.94 | 1.82x | $1,516,214 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 43 MO | $25,500.00 | $11,585.04 | 2.20x | $598,343 |
| 168-7001 VEGETATIVE WATERING | 8,279 TGL | $70.00 | $8.43 | 8.30x | $509,707 |
| 425-7003 PRESTR CONC GIRDER (TX40) | 2,818.88 LF | $390.00 | $213.86 | 1.82x | $496,509 |
| 6123-7001 FULL COLOR MATRIX DMS (POLE MOUNTED) | 3 EA | $150,000.00 | $13,500.00 | 11.11x | $409,500 |
| 100-7002 PREPARING ROW | 190.3 STA | $1,000.00 | $6,072.92 | 0.16x | -$965,377 |