US 287; N of Harmon Rd to N of IH 35W
0014-15-034 · let Aug 5, 2026 · Tarrant, Fort Worth · Intersection & Operational Imprv
$66,140,142Low bid: INDUS ROAD & BRIDGE, INC.-11.0% vs estimate $74,343,262
$809,635Left on the table1.2% gap to the second bid
11BiddersSpread 19% low to high
914Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INDUS ROAD & BRIDGE, INC. | $66,140,142 | -11.0% | $809,635 | 3+$9,644,298 | 0 | |
| 2 | HARPER BROTHERS CONSTRUCTION LLC | $66,949,776 | +1.2% | -9.9% | $385,080 | 3+$10,156,941 | 2-$1,159,398 |
| 3 | SEMA CONSTRUCTION, INC. | $67,334,856 | +1.8% | -9.4% | $2,427,090 | 3+$12,953,459 | 1-$423,709 |
| 4 | RAGLE CONSTRUCTION, INC. | $69,761,946 | +5.5% | -6.2% | $838,054 | 4+$13,225,456 | 2-$1,117,520 |
| 5 | REYES TX, INC. | $70,600,000 | +6.7% | -5.0% | $1,102,834 | 5+$11,785,430 | 0 |
| 6 | MARIO SINACOLA & SONS EXCAVATING, INC. | $71,702,834 | +8.4% | -3.6% | $1,187,514 | ||
| 7 | WEBBER, LLC | $72,890,348 | +10.2% | -2.0% | $33,292 | ||
| 8 | PULICE CONSTRUCTION, INC. | $72,923,640 | +10.3% | -1.9% | $369,927 | ||
| 9 | RPM XCONSTRUCTION, LLC | $73,293,567 | +10.8% | -1.4% | $4,319,960 | ||
| 10 | AUSTIN BRIDGE & ROAD SERVICES, LP | $77,613,527 | +17.3% | 4.4% | $934,728 | ||
| 11 | TISEO PAVING COMPANY, LLC | $78,548,255 | +18.8% | 5.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
INDUS ROAD & BRIDGE, INC. vs HARPER BROTHERS CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7004 EMBANK (FNL)(DC)(TY B) | 318,099 CY | $13.00 | $25.00 | $12.93 | $3,817,188 |
| 100-7002 PREPARING ROW | 84 STA | $43,539.24 | $7,500.00 | $6,072.92 | -$3,027,296 |
| 462-7033 CONC BOX CULV (10 FT X 5 FT) | 3,924 LF | $1,100.00 | $1,710.00 | $1,132.09 | $2,393,640 |
| 508-7001 CONSTRUCTING DETOURS | 32,874 SY | $99.00 | $60.00 | $83.58 | -$1,282,086 |
| 422-7002 REINF CONC SLAB (HPC) | 55,131 SF | $20.00 | $35.00 | $26.91 | $826,965 |
| 360-7005 CONC PVMT (CRCP) (11") | 50,703 SY | $95.00 | $80.00 | $94.72 | -$760,545 |
| 400-7006 CUT & RESTORING PAV | 930 SY | $732.00 | $40.00 | $171.81 | -$643,560 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 15,090 LF | $50.00 | $7.50 | $52.29 | -$641,325 |
| 416-7006 DRILL SHAFT (36 IN) | 2,455 LF | $165.00 | $400.00 | $280.58 | $576,925 |
| 7097-7008 48" STL AWWA C200 WP, CSS BF_RSTRN JNT | 1,125 LF | $1,600.00 | $1,100.00 | $1,600.00 | -$562,500 |
| 132-7012 EMBANK (FNL)(DC)(TY D) | 47,058 CY | $14.00 | $5.00 | $10.77 | -$423,522 |
| 400-7008 CUT & RESTORE ASPH PAVING | 1,879 SY | $262.00 | $40.00 | $140.13 | -$417,138 |
| 361-7049 FULL - DEPTH REPAIR CRCP (8") | 8,500 SY | $171.00 | $125.00 | $189.93 | -$391,000 |
| 423-7001 RETAINING WALL (MSE) | 27,064 SF | $69.00 | $55.00 | $74.07 | -$378,896 |
| 7097-7012 CONNECTION TO EX 48" WATER MAIN | 4 EA | $30,000.00 | $115,000.00 | $30,000.00 | $340,000 |
| 531-7002 CONC SIDEWALKS (5") | 17,603 SY | $61.00 | $80.00 | $68.80 | $334,457 |
| 425-7004 PRESTR CONC GIRDER (TX46) | 6,900.04 LF | $220.00 | $250.00 | $236.72 | $207,001 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 2,880 LF | $77.00 | $7.50 | $43.56 | -$200,160 |
| 403-7001 TEMPORARY SPL SHORING | 20,968 SF | $12.00 | $2.50 | $25.56 | -$199,196 |
| 260-7019 LIME TRT (EXIST MATL)(18") | 91,884 SY | $7.60 | $5.50 | $6.97 | -$192,956 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$624,004 of the $809,635 gap.
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 1HARPER BROTHERS CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,500,000.00 | $523,850.32 | 12.41x | $5,976,150 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 318,099 CY | $25.00 | $12.93 | 1.93x | $3,840,791 |
| 7097-7012 CONNECTION TO EX 48" WATER MAIN | 4 EA | $115,000.00 | $30,000.00 | 3.83x | $340,000 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 15,090 LF | $7.50 | $52.29 | 0.14x | -$675,863 |
| 403-7001 TEMPORARY SPL SHORING | 20,968 SF | $2.50 | $25.56 | 0.10x | -$483,535 |
SEMA CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,733,485.69 | $523,850.32 | 12.85x | $6,209,635 |
| 100-7002 PREPARING ROW | 84 STA | $76,152.51 | $6,072.92 | 12.54x | $5,886,685 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $36,795.00 | $11,585.04 | 3.18x | $857,139 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 15,090 LF | $24.21 | $52.29 | 0.46x | -$423,709 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,800,000.00 | $523,850.32 | 12.98x | $6,276,150 |
| 100-7002 PREPARING ROW | 84 STA | $75,000.00 | $6,072.92 | 12.35x | $5,789,875 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $35,000.00 | $11,585.04 | 3.02x | $796,109 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $500,000.00 | $136,676.66 | 3.66x | $363,323 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 4,400 CF | $50.00 | $206.00 | 0.24x | -$686,405 |
| 403-7001 TEMPORARY SPL SHORING | 20,968 SF | $5.00 | $25.56 | 0.20x | -$431,115 |
REYES TX, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,883,500.00 | $523,850.32 | 13.14x | $6,359,650 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 318,099 CY | $23.50 | $12.93 | 1.82x | $3,363,642 |
| 100-7002 PREPARING ROW | 84 STA | $19,275.68 | $6,072.92 | 3.17x | $1,109,032 |
| 403-7001 TEMPORARY SPL SHORING | 20,968 SF | $50.20 | $25.56 | 1.96x | $516,639 |
| 168-7001 VEGETATIVE WATERING | 13,827 TGL | $40.00 | $8.43 | 4.74x | $436,467 |